Community Infrastructure Levy (CIL) Spending Protocol 2025
ApprovedPlanning2 papers
Licensing and Planning Policy Committee approved this item on Tuesday 11 March 2025. Below is the council's own wording, with the papers it was decided on.
Following consideration, the Committee unanimously resolved to: (1) Approve the updated Epsom and Ewell Borough CIL Spending Protocol 2025 attached at Appendix 1.? (2) Note that spending decisions will be taken to the Strategy and Resources Committee and that the CIL MWG will report to S&R Committee. (3) Recommend to the Strategy and Resources Committee the MWG TOR in Appendix 1.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
The report seeks the approval of an updated CIL spending protocol which will provide the framework for how the council allocates Community Infrastructure Levy funding that has been received from eligible developments in the borough to contribute towards the delivery of infrastructure.
Recommendation (s) The Committee is asked to:
(1) Approve the updated Epsom and Ewell Borough CIL Spending Protocol 2025 attached at Appendix 1.
(2) Note that spending decisions will be taken to the Strategy and Resources Committee and that the CIL MWG will report to S&R Committee.
(3) Recommend to the Strategy and Resources Committee the MWG TOR in Appendix 1.
Reason for recommendation
1.1The CIL spending protocol was adopted in January 2024 by the Licensing and Planning Policy Committee and was used for the assessment of both strategic and neighbourhood CIL bids in Spring 2024.
1.2Following the successful use of the Spending Protocol to approve the release of CIL funds to deliver infrastructure in the borough, members of the councils CIL Member working group (MWG) and officers identified some improvements that could be made to the Spending Protocol and decision process, and this report seeks approval of the Spending Protocol amendments. Licensing and Planning Policy Committee 11 March 2025 2 Background
2.1On 29 April 2014 EEBC adopted the CIL Charging Schedule which came into effect on 1st July 2014.
2.2CIL monies are to mitigate the cumulative impact of development but are rarely sufficient to fund all of the infrastructure that is required to support development of an area. Therefore, to ensure that they are used effectively, they should be prioritised to funding and delivering essential infrastructure. A spending protocol helps makes clear and transparent decisions around spending of CIL.
Spending CIL
2.3Legislation sets some parameters for the way in which CIL can be used. For most authorities, including EEBC, the breakdown of how CIL receipts are ring-fenced and spent is as follows:
70–80% of receipts on infrastructure projects – the provision, improvement, replacement, or operation of infrastructure to support the development of the area. The charging authority decides what these priorities are and when and where to spend CIL. This can be outside an authority area, providing it addresses the impacts of development within it.
15% (capped at £100 plus indexation per dwelling) rising to 25% (uncapped) in areas with an adopted neighbourhood plan for spend within the neighbourhood within which the CIL was received. These receipts must be spent on projects that support development of the area but is not limited to infrastructure. In areas with parish councils or community councils these funds are passed to them. Outside of these areas the council should engage with communities on how the money should be spent.
5% of CIL receipts in the first 3 years of operation and annually thereafter can be spent on the cost of administering CIL. These administration costs can include staff, software and, in the first three years of charging CIL, costs associated with setting the CIL Charge.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Licensing and Planning Policy Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
Authority Monitoring Report 2025-2026The Committee resolved (8 for, 1 against) to: 1) Note the content of the Authority Monitoring Report for the 2025/26 ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.