Following consideration, the Committee unanimously agreed to: (1) Approve the proposal to appoint the Preferred Supplier for the delivery of leisure services at the Rainbow Leisure Centre (Option A), as identified through the procurement process and in accordance with the Council’s Contract Standing Orders. (2) Approve the award of the contract to the second placed bidder, should the contract be unable to be finalised with the Preferred Supplier; and if the same should happen with the second placed bidder, the contract awarded to the third placed bidder. (3) Nominate and authorise the Assistant Director of Corporate Services, in consultation with the Director of Corporate Services and Head of Legal Services to take all necessary steps to bring into effect the recommendations resolved by this Committee.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
This report details the outcome of the procurement exercise which has taken place to find an operator for the Rainbow Leisure Centre for the next 10 years. The contract with the current operator, Greenwich Leisure Limited (GLL) expires at the end of September 2025, without an option to extend. An invitation to tender was published last year to secure an operator for the next contract period. The procurement exercise has finished, and this report makes a recommendation to the Committee, in accordance with our Contract Standing Orders, for the award of contract to the Preferred Supplier.
Recommendation (s) The Committee is asked to:
(1) Approve the proposal to appoint the Preferred Supplier for the delivery of leisure services at the Rainbow Leisure Centre (Option A), as identified through the procurement process and in accordance with the Council’s Contract Standing Orders.
(2) Approve the award of the contract to the second placed bidder, should the contract be unable to be finalised with the Preferred Supplier; and if the same should happen with the second placed bidder, the contract awarded to the third placed bidder.
(3) Nominate and authorise the Assistant Director of Corporate Services, in consultation with the Director of Corporate Services and Head of Legal Services to take all necessary steps to bring into effect the recommendations resolved by this Committee. Strategy and Resources Committee 17th June 2025
Reason for recommendation
1.1Under the Council’s Contract Standing Orders, there is a requirement that any Threshold 4 contracts - the award of the contract for the Leisure Centre is a Threshold 4 contract - must be approved by the relevant committee before the contract can be awarded.
1.2The terms of reference for the Community and Wellbeing Committee cover the provision of leisure services, and so approval is required of Community and Wellbeing Committee. However, as the financial impact of the contract on the finances of the council is significant, approval of the contract award is also sought from Strategy and Resources Committee, as their terms of reference cover the council’s budget.
1.3The recommendation above reflects the outcome of the procurement process that has been followed over the course of the past year.
1.4Approving the recommendation will ensure there is a continuity of high- quality leisure, health and wellbeing services delivered by the Rainbow Leisure Centre (the ‘Centre’), and that it remains a financially sustainable council-owned facility.
1.5In relation to Recommendation 2, this has been included in the unlikely circumstance that the council cannot proceed with the Preferred Supplier.
1.6Please note that Appendix 1 has been categorised as an Exempt Paper as it contains commercially sensitive information relating to the preferred bid, which in order to uphold and protect the commercial interests of this council, cannot be shared in the public domain.
Background
2.1The council owns one leisure centre in the Borough. The facilities at the Centre include swimming pools, sports hall, fitness suite, exercise / dance studios, soft play, seniors’ room, and spa.
2.2Since the Centre was rebuilt and opened in 2003, it has been operated by a third-party leisure operator, Greenwich Lesure Limited (GLL), trading under the name ‘Better’.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.