EEBC 2025-2027 Strategic Priority 4: Community Asset Review
NotedCommittee6 papers
AI summaryEpsom and Ewell's Strategy and Resources Committee has approved £30,000 from the LGR Reserve for Phase 2 of the Community Asset Review, producing business cases for Bourne Hall, the Community & Wellbeing Centre and Epsom Playhouse before transfer to the new East Surrey Unitary Council.
Written from the decision and the officer reportPDF Pro
OutcomeNoted4 votes for, 3 against
Money£30,000from LGR Reserve
What happens nextComplete Phase 2 workproduce business case for each asset
Who it affects3 community assetsBourne Hall, C&W Centre, Epsom Playhouse
What was decided
The Committee noted the progress update on the Community Asset Review Phase 1 work. Report P4
Members agreed to complete the more detailed Phase 2 work at a cost of £30,000. Report P5
Members agreed to release the £30,000 Phase 2 funds from the LGR Reserve. Report P6
Why
The Council has a statutory duty under section 123 of the Local Government Act 1972 to seek Best Value from its land and property assets. Report 7.1
Around £2m per year of Council budget is currently needed to maintain the three key community buildings, so the assets need to be reimagined and supported by business cases. Report 3.11, 3.12
Phase 2 will prepare the three assets for transfer to the new East Surrey Unitary Council and support sound future decision making. Report 1.2, 4.5, 4.6
What happens next
Complete Phase 2 work, covering finance and business planning, stewardship and partnerships, building and asset management, and community and stakeholder needs. Report 4.1, 4.3, 4.4
Produce a business case for each of the three key community assets and consolidate the learning into a framework. Report 4.5, P2
Position the assets so they are ready for transfer ahead of Local Government Reorganisation Vesting Day on 1 April 2027. Report 2.6, 8.6
The money
£30,000 Cost of completing Phase 2 of the Community Asset Review, to be released from the LGR Reserve Report 4.4, P5, P6
circa £2m per annum Current Council budget required to maintain the three key community buildings Report 3.11
Implications
Legal: Statutory duty under section 123 of the Local Government Act 1972 to obtain Best Value from land and property assets. Report 7.1
Financial: £30,000 will be drawn from the LGR Reserve to fund Phase 2 work. Report 4.4, P6
Other: Phase 2 is intended to prepare the three community assets for transfer to the new East Surrey Unitary Council before Vesting Day on 1 April 2027. Report 2.6, 8.6
Equalities: No equality impact assessment required for this report. Report P54
Climate: No climate or environmental impact identified for these recommendations. Report 8.3
Who and where
Residents and community users of Bourne Hall, the Community & Wellbeing Centre and Epsom Playhouse in the Borough of Epsom and Ewell Report 3.9, 3.10
The future East Surrey Unitary Council, which will inherit the three community assets Report 1.2, 4.6
Existing community organisations and partners working with the three key assets Report 3.5, P45
Timeline
6 May 2025: Full Council approved seven Strategic Priorities for 2025-2027, including Priority 4 on the Asset Review. Report 2.1, P78
11 November 2025: Strategy and Resources Committee considered EEPIC, Operational and Surplus Assets and received an initial Community Asset Review update. Report 2.4, P75
9 December 2025: Community Governance Review considered at Full Council. Report P77
17 March 2026: Strategy and Resources Committee approved Phase 2 of the Community Asset Review and £30,000 from the LGR Reserve.
1 April 2027: Local Government Reorganisation Vesting Day for the new East Surrey Unitary Council. Report 8.6
Plain English for the jargon
LGR: Local Government Reorganisation, the move to a new East Surrey Unitary Council.
LGR Reserve: Council reserve held to fund work related to Local Government Reorganisation.
s123 LGA 1972: Section 123 of the Local Government Act 1972, requiring best value from land and property disposals.
SWOT: Strengths, Weaknesses, Opportunities and Threats analysis used in Phase 1.
EEPIC: Epsom and Ewell Property Investment Company, a council-owned commercial property entity.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item59
Resolved
Following consideration, the Committee resolved with four votes for and three votes against to: (1) Note the update and progress made as set out in the report. (2) Agree to complete the more detailed Phase 2 work at a cost of £30,000 as set out in paragraphs 4.1 to 4.4 of the report. (3) Agree to release the £30,000 Phase 2 funds from the LGR Reserve.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
This report outlines the progress made in respect of the Council’s 2025-2027 Strategic Priority 4 in relation to Community Assets.
It recommends completion of the Phase 2 work to ensure each of the 3 key Community Assets (Bourne Hall, Community & Wellbeing Centre and Epsom Playhouse) are provided with a business case to help safeguard their future success.
Recommendation (s) The Committee is asked to:
(1) Note the update and progress made as set out in this report.
(2) Agree to complete the more detailed Phase 2 work at a cost of £30,000 as set out in paragraphs 4.1 to 4.4.
(3) Agree to release the £30,000 Phase 2 funds from the LGR Reserve.
1 Reason for Recommendation Strategy and Resources Committee 17 March 2026 1.1 The Council has a statutory obligation under s123 Local Government Act 1972 to seek Best Value from its land and property assets.
1.2The Phase 2 work (as described in paragraphs 4.1 to 4.3) will ensure that each of the 3 key Community Assets is provided with a business case for transfer to the new East Surrey Unitary Council.
1.3The recommendations represent the outcome of the work undertaken to date (and reported below) demonstrating the Council’s commitment to its s123 statutory obligation.
Background
2.1At its 6 May 2025 meeting, Full Council approved seven Strategic Priorities to be delivered in 2025-2027. The revised Priorities replaced the Council’s Four-Year Plan and focused its strategic delivery in the context of Local Government Reorganisation (LGR) timescales.
2.2To ensure the 2025-2027 Strategic Priorities continue to be delivered swiftly alongside business as usual and existing commitments, support has been provided by an external specialist property consultant.
2.3This report relates to the Community Assets of Strategic Priority 4, which stated:
Priority 4: Carry out and complete major Asset Review Outcome: To Review key council owned property assets, including EEPIC, Bourne Hall, Playhouse and C&W Centre but excluding commercial assets on long term leases, to understand market values. Identify assets that could transfer to a new local governance entity (subject to the creation of new entity/ies) and likely revenue/maintenance costs for that new entity.
2.4Strategy & Resources Committee had previously considered EEPIC, Operational and Surplus Assets at its 11 November 2025 meeting. The report also included an update on the initial work to review the Community Assets including:
As part of the wider review of all Council assets, those assets held for community purposes, and which might be considered appropriate for a Community Transfer had been identified.
As requested by Strategy Priority 4, particular focus was applied to:
o Bourne Hall
o The Epsom Playhouse
o Community & Wellbeing Centre Strategy and Resources Committee 17 March 2026 Work was undertaken to better understand the implications of holding the assets in any new local governance entity - which was linked to Strategic Priority 1: Explore and implement future local governance (i.e. Town Community Council).
2.5This report provides further information of the Community Asset Review work to date (Phase 1) and outlines the second phase of the Community Asset Review work (Phase 2).
2.6Phase 2 is designed to put the above assets in the strongest position possible as the Council moves towards becoming part of the new East Surrey Unitary Council.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.