The report of the Head of Treasury Services was submitted, advising Members of the overall projected financial position of the General Fund Revenue Budget after six months, for the 2010/11 financial year. He identified the main variances and issues influencing the projected outturn figure. Members thanked officers for successfully delivering a very challenging budget and requested clarification on various issues. In response to a request, the Head of Treasury Services agreed to provide a year-on-year comparison in respect of the debt situation in future years, though noting that the current accounting system had only been in place for 12 months. Scrutiny Committee – Resources considered the report at the meeting of 24 November 2010 and the support of members was noted. Executive recommended that Council approve:- (1) the General Fund forecast financial position for the 2010/11 financial year; (2) the HRA forecast financial position for 2010/11 financial year; (3) the outstanding Sundry Debt position as at June 2010; and (4) the Statutory Performance Indicator BVPI8 for creditors’ payments.
Word for word from the decision Exeter published for this meeting.Source: committees.exeter.gov.uk
1.1To advise Members of the overall projected financial position of the General Fund Revenue Budget after six months, for the 2010/11 financial year.
2. REVENUE POSITION – EXECUTIVE SUMMARY
FUND Latest Approved Stewardship Outturn Forecast Budget Variance September 2010/11 2010 £ £ £ General Fund 18,030,360 (32,356) 17,998,004
HRA* (642,570) 222,017 (420,553) * Net deficit
GENERAL FUND – Appendix A
2.1The Service Committee budgets shows a forecast under spend of £372,890 (2.15%) against a revised Service Committee Net Expenditure budget of £17,356,360 and an overall under spend of £32,356 against the General Fund Expenditure including investment interest, Business Growth Incentive Grant, Area Based Grant, the provision for redundancy, the provision for the repayment of debt and the potential impairment loss re the Icelandic investments.
2.2The budgets for 2010/11 included a provision of 0.7% for the pay award. The current position is that Local Government Employers have not offered a pay award for the current year, however as this has not been finalised, this has not yet been fully reflected.
2.3Details of the variances are being disclosed in stewardship reports to individual Scrutiny Committees during the current cycle of meetings. However the main variances are as follows:
2.3.1 Scrutiny Committee Community – (An under spend of £416,280)
A new contract for management of the sports facilities came into force on 1st October 2010 and is expected to result in material savings in the current year and future years. The outturn forecast reflects the estimated impact for the current year on this Committee. There will be a negative impact on Resources Committee as a result of additional discounts arising on NNDR, and this has been reflected in the outturn forecasts for that Committee. Overall the projected saving for sports facilities is £470,000 Income from the sale of recyclates is expected to exceed the estimates, while the cost of freight is expected to show a saving. While the prices at which materials are currently being sold exceed those assumed for the estimates, the volatility of these prices makes it difficult to predict the outturn. Overall a saving of £148,720 is anticipated.
In General Fund Housing, there is a reduction in the amount of revenue expenditure which can be capitalised in relation to the Council Own Build sites at Sivell Place and Merlin Crescent, in accordance with capital accounting regulations and a further overspend, which will be met from earmarked reserves for expenditure relating to Empty Home Initiatives and the Housing Market Assessment. The projected overspend is £58,750, however £34,650 will be funded from earmarked reserves.
A number of overspends have occurred in General Fund Housing Advisory Services. These include higher than inflation rental payment increases and additional demand, a reduction in the number of landlords registered for Extralet reducing income, additional costs in respect of Shaul’s Court and Glencoe and increased demand for housing advice. The projected overspend is £155,550.
2.3.2 Scrutiny Committee Economy – (An under spend of £265,170)
Property income is lower than expected at various properties due to a general increase in void periods and downward pressures on rent levels across the portfolio, however this has been offset by savings on employment costs resulting in a saving of £28,490.
Income from off street car park fees is above the budgeted income figure as at 30 September 2010 and there have been savings on employment costs. Additional income is expected in respect of rental of car park spaces; this additional income will be partially offset by income from Car Park Investment properties being less than budgeted. The projected saving is £103,420.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of Exeter Business Centre Ltd.AGREED: RESOLVED that Executive: (1) note the current position of Exeter Business Centre Ltd and the review of Exeter...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.