The report of the Head of Treasury Services was submitted, reporting on the current position in respect of the Council’s revised annual capital programme. The Head of Treasury Services reported that a review of the capital programme had been undertaken to identify the extent to which uncommitted schemes could be deferred, reduced or removed from the programme and to identify any potential savings. He identified the main variances and other issues. Scrutiny Committee - Resources considered the report at the meeting of 24 November 2010 and the support of members was noted. Executive noted the current position in respect of the capital programme. Executive recommended that Council note and approve the current position in respect of the annual capital programme.
Word for word from the decision Exeter published for this meeting.Source: committees.exeter.gov.uk
1.1To report the current position in respect of the Council’s revised annual capital programme.
1.2This report is prepared on a quarterly basis in order to update Members with any known cost variations, slippage and acceleration of projects.
1.3As part of the first quarter’s monitoring exercise, Officers instigated a review of the capital programme, to identify the extent to which schemes were not yet committed, to consider whether some of the uncommitted schemes could be deferred, reduced or removed from the programme and to identify any potential savings.
1.4The review of the capital programme has been progressed further as part of the second quarter’s monitoring exercise.
Background
2.1Local authorities are required to estimate the total of capital expenditure that they plan to incur during the financial year when it sets the prudential indicators for capital expenditure. This shows that its asset management and capital investment strategies are affordable, prudent and sustainable.
2.2Capital expenditure is a significant source of risk and uncertainty since cost variations, delays and changing specifications are often features of large and complex capital projects.
2.3The Council has become more dependant on borrowing to finance its capital programme and the cost of servicing the borrowing has to be met from revenue. Bearing in mind the future budget reductions faced by the City Council, it is important to ensure that the Council’s future capital spending is affordable and sustainable.
2.4The June monitoring report identified schemes within the 2010/11 capital programme totaling £4.1 million which could potentially be deferred. This was based around those schemes which were not yet committed, which were largely put on hold until the review was complete and could be considered fully. Schemes which are mostly funded from external sources, schemes which were expected to generate revenue savings and works which are considered to be urgent, were largely unaffected. 3.0 REVISIONS TO THE CAPITAL PROGRAMME
3.1The 2010/11 Capital Programme, including commitments brought forward from 2009/10, was last reported to Scrutiny Committee - Resources on 15 September 2010. Since that meeting the following changes have been made that have increased the programme:
Description £ Approval / funding Capital Programme, as at 15 30,086,670 September 2010 Disabled Facilities Grants 198,330 Executive 29th September Energy Conservation 32,420 External funding contributions Children’s Play Area 60,190 Additional S106 contributions Social Housing Grants (30,700) Transferred to Revenue projects Riverside Valley Park 17,250 S106 Contributions Improvements Mincinglake / Northbrook 120,000 Environment Agency Grant Watercourse Study scheme
Revised Capital Programme 30,484,160
4.0PERFORMANCE
4.1Progress The revised capital programme for the current financial year is £30.484 million. During the first six months of the year the Council spent £6.964 million on the programme, which equates to 22.8% of the revised programme. This compares with £6.013 million (23.8%) being spent in the first six months of 2009/10.
4.2The current programme is detailed in Appendix 1. The Appendix shows a total forecast spend for 2010/11 of £27.974 million, with schemes totaling £4.189 million deferred to 2011/12, and other variances totaling £1.678 million (adverse). The major variances are explained further in Section 5 of the report.
4.3The other variances of £1.678 million include a number of scheme savings and also some reductions for schemes which are proposed to be removed from the 2010/11 programme. Expenditure on these schemes, which are uncommitted, will not occur in 2010/11. Where members consider any of these schemes to be a high enough priority then those schemes can be reconsidered as part of the 2011/12 capital programme deliberations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of Exeter Business Centre Ltd.AGREED: RESOLVED that Executive: (1) note the current position of Exeter Business Centre Ltd and the review of Exeter...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.