The report of the Head of Treasury Services was submitted, setting out the current position in respect of the Council’s 2010/11 capital programme and advising Members of the anticipated variations. Scrutiny Committee - Resources considered the report at their meeting on 23 March 2011 and their comments and support were noted. Executive recommended that Council approves:- (1) the current position in respect of the annual capital programme; and (2) a reduction in the disabled facilities grants budget of £198,330.
Word for word from the decision Exeter published for this meeting.Source: committees.exeter.gov.uk
1.1In accordance with the Prudential Code for Capital Finance in Local Authorities, it is necessary to monitor performance against the prudential indicator for capital expenditure and highlight significant deviations from expectations. This report therefore sets out the current position in respect of the Council’s 2010/11 capital programme and advises Members of the anticipated variations.
Background
2.1Local authorities are required to estimate the total of capital expenditure that they plan to incur during the financial year when it sets the prudential indicators for capital expenditure. This shows that its asset management and capital investment strategies are affordable, prudent and sustainable.
2.2Capital expenditure is a significant source of risk and uncertainty since cost variations, delays and changing specifications are often features of large and complex capital projects.
2.3This report is prepared on a quarterly basis in order to update Members with any known cost variations, slippage or acceleration of projects.
3.0REVISIONS TO THE CAPITAL PROGRAMME
3.1The 2010/11 Capital Programme was last reported to Scrutiny Committee - Resources on 24 November 2010. From that report, schemes totaling £4.2 million within the 2010/11 capital programme have now been deferred and are included within the 2011/12 budget. A number of specific savings and reductions of £0.343 million were also reported for which the 2010/11 budget has now been adjusted.
Since that meeting, these and other revisions have been made to the programme as shown in the following table: Description £ Approval / funding Capital Programme, as at 24 30,484,160 November 2010 Budget Deferred to 2011/12 (4,188,550) Approved by Executive 7 December 2010 Overspends / Underspends (net) (342,690) Additional budget approved by RAMM Redevelopment 2,187,580 Executive 7 December 2010 Energy Conservation 116,520 External funding contributions
National Cycle Network 176,670 Contributions from DCC
HRA Increase in Budget Deferred (400,000) Deferral built into 2011/12 Budget
Revised Capital Programme 28,033,690
4.0PERFORMANCE
4.1Projected Outturn The revised capital programme for the current financial year is £28.034 million. From the current monitoring review it is projected that a further £4.908 million of the programme will need to be carried forward into future years. For details, please refer to Appendix 1 and to the explanations below.
4.2Progress During the nine months of the year to 31 December, the Council spent £12.264 million on the capital programme, which equates to 43.7% of the revised 2010/11 programme. This compares with £10.561m million (41.6%) being spent in the first nine months of 2009/10.
4.3Other variances shown in Appendix 1 of £0.233 million include a number of further scheme savings which can be achieved from the 2010/11 programme, which are explained below.
5.0VARIANCES and OTHER ISSUES
5.1The main items are as follows:
5.1.1 Community & Environment
Cultural City
• RAMM Re-development (Budget £11,074,620) Following approval of a revised budget for this scheme by the Executive on 7 December, the projected costs have been reviewed to determine the revised spending profile over the two years 2010/11 – 2011/12. As a result, it is now estimated that £1.783 million of the 2010/11 revised budget will need to be carried forward into the next financial year.
Page 2 of 6 Following some last minute delays to ensure that the air conditioning was operating to its proper specification, the interior of the building was due to be handed over by the contractor in mid-March. Exhibition fit out is due to commence on 28 March. The scheme is expected to be complete and the museum reopened mid December.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of Exeter Business Centre Ltd.AGREED: RESOLVED that Executive: (1) note the current position of Exeter Business Centre Ltd and the review of Exeter...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.