The report of the Acting Assistant Director Finance was submitted, reporting on the current position in respect of the Council’s revised annual capital programme and advising Members of the anticipated level of deferred expenditure into future years. Members were asked to approve an urgent request for an additional sum of £36,000 to complete essential resurfacing of Leighton Terrace car park. The works were necessary to ensure that the car park could continue to operate and comply with Health and Safety Regulations. The Deputy Chief Executive claified that, as a result of this valuation, the Council had updated its estimates process. Members discussed the wider issue of the tendering and procurement process within the City Council and the need to ensure that small local businesses were not precluded from tendering for Council Projects. The Chair suggested that the tendering and procurement process could be an issue for Scrutiny Committee – Resources to scrutinise. The Portfolio Holder for Housing and Customer Access expressed disappointment that the scheme to help bring empty properties back into use had been withdrawn due to lack of interest from landlords. The Acting Assistant Director Finance would clarify if these funds would have to be given back to the Government. The Portfolio Holder for Economy and Culture advised that the scheme to replace the running track at Exeter Arena had been deferred to take account of the weather conditions required for works to be undertaken. Scrutiny Committee – Resources considered the report at its meeting on 18 September and the comments of the Members were noted. Executive recommended that Council notes and approves the current position in respect of the annual capital programme and requested to approve an urgent request for an additional £36,000 to complete the resurfacing of Leighton Terrace car park.
Word for word from the decision Exeter published for this meeting.Source: committees.exeter.gov.uk
1.1To report the current position in respect of the Council’s revised annual capital programme and to advise Members of the anticipated level of deferred expenditure into future years.
Background
2.1Local authorities are required to estimate the total of capital expenditure that they plan to incur during the financial year when it sets the prudential indicators for capital expenditure. This shows that its asset management and capital investment strategies are affordable, prudent and sustainable.
2.2Capital expenditure is a significant source of risk and uncertainty since cost variations, delays and changing specifications are often features of large and complex capital projects.
2.3This report is prepared on a quarterly basis in order to update Members with any known cost variations, slippage and acceleration of projects.
3. REVISIONS TO THE CAPITAL PROGRAMME
3.1The 2013/14 Capital Programme, including commitments brought forward from 2012/13, was last reported to Scrutiny Committee – Resources on 19 June 2013. Since that meeting the following changes have been made that have increased the programme:
Description £ Approval/Funding Capital Programme, 21,511,060 as at 19 June 2013
Approved by the Executive 1 July HRA Structural Repairs to four 120,000 2013 (financed from Major Council dwellings Repairs Reserve) Delegated powers 14 February HRA Acquisition of Social 136,550 2013 (financed from HRA Capital Housing - 1 Elaine Close Receipts)
HRA Asbestos Surveys (13,960) Budget transferred to revenue COB Wave 2 - Rennes House Approved by Executive 5 (410,740) Car Park February 2013
Approved by Executive 5 COB Wave 2 - Newport Road (147,660) February 2013
COB Wave 2 - Whipton Approved by Executive 5 (202,600) Methodist Church February 2013
Approved by Executive 5 COB Wave 2 - Bennett Square (174,850) February 2013
National Cycle Network 71,940 Contributions from DCC
Bury Meadow 4,500 Contribution from DCC
Childrens Play Areas 2,500 Contribution from DCC
Additional S106 funding and Childrens Play Areas 96,790 interest Environmental Improvements to Revenue contribution to capital 20,000 Cowick Street outlay
Well Oak Footpath/Cycleway 5,650 S106 contribution
Other Amendments 900
Revised Capital Programme 21,020,080
4. PERFORMANCE
4.1The revised capital programme for the current financial year is £21.020 million. During the first three months of the year the Council spent £2.748 million on the programme, which equates to 13.1% of the revised programme. This compares with £1.971 million (9.9%) being spent in the first three months of 2012/13.
4.2The current programme is detailed in Appendix 1. The Appendix shows a total forecast spend for 2013/14 of £17.391 million with £3.344 million of the programme potentially deferred to 2014/15.
4.3Appendix 2 shows the overall position for those schemes which span more than one financial year.
5. AVAILABLE CAPITAL RESOURCES
5.1In previous years the annual capital programme has been financed from Government allocated grants together with money from the Council’s own capital receipts and capital reserves. However the funding from these sources has now reduced and as a result the Council has to use borrowing instead to fund a significant part of its proposed capital programme. 5.2 The available capital resources for the General Fund for 2013/14 are £2.626 million. An estimated spend of £6.687 million is required of which £4.061 million will have to be funded from borrowing. The available capital resources for the HRA for 2013/14 are £12.579 million. An estimated spend of £10.704 million is required leaving £1.875 million to be carried forward into 2014/15. Appendix 3 sets out the forecast use of the resources available for the General Fund and the HRA and the likely amounts of borrowing that will be necessary to fund the capital programme over the next two years.
6. EXPENDITURE VARIANCES
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of Exeter Business Centre Ltd.AGREED: RESOLVED that Executive: (1) note the current position of Exeter Business Centre Ltd and the review of Exeter...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.