Exeter City Council
Executive, Tuesday 13 February 2018 at 5.30pm

Leisure Complex and Bus Station Programme Board Minutes - 30 January 2018

Agreed Executive 1 paper

Executive agreed this item on Tuesday 13 February 2018. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

Agreed That it is recommended to Council to approve:- (1) Rescission of the Council Resolution passed on 12 October 2017 (Minute 3) stating that the Bus Station would close by the end of February 2018, at the latest; and (2) The Chief Executive & Growth Director, in consultation with the Leader and the Portfolio Holder for Health & Wellbeing, Communities & Sport be authorised to decide the precise date of the closure of the Bus Station. Reason for As set out in the minutes.
Word for word from the decision Exeter published for this meeting. Source: committees.exeter.gov.uk

Follow this further

Built from Exeter's papers

What the report saysPro

Report to Executive, 4 pages

LEISURE COMPLEX AND BUS STATION PROGRAMME BOARD

Tuesday 30 January 2018

Present:-

Councillor Bialyk (Chair) Councillors Edwards, Pearson, [name removed] and Wardle

Also Present

Chief Executive & Growth Director, Director (JY), Chief Finance Officer, City Surveyor, Communications Officer, Project Manager - Leisure Operations and Democratic Services Officer (Committees) (SLS)

Justin Pickford - Baker Ruff Hannon Iain McNeill - WSP Group Phil Lewis - Randall Simmonds

1 MINUTES

The minutes of the meeting held on 28 September 2017 were taken as read and signed by the Chair as correct.

2 DECLARATIONS OF INTEREST

No declarations of pecuniary interest were made.

3 PRESENTATION

The Chief Executive & Growth Director introduced presenters who would provide an update on the Bus Station closure timescale and outline the preferred procurement strategy for the main contractor/builder. Members would be asked to rescind the planned closure of the Bus Station at the end of February 2018. A copy of the presentation would be attached to the minutes, which would also include a review of the timelines in the short term and an update on the Bus Station and Leisure Centre development.

The Chief Executive & Growth Director made a brief statement and stated that the Bus Station and Leisure Complex site remained a strategic priority, despite the challenges to deliver the site in a comprehensive way, and ensure that such a significant development would continue to safeguard the economic future of the city centre. Following the withdrawal of Crown Estate from the commercial retail element of the site, there was the chance to take stock and revisit the purpose of the development, and the procurement process to secure a contractor who would be able to build to budget. The land belongs to the City Council, and it was important to note that its value had increased in recent years. This project represented a fantastic opportunity for the city, and was consistent with the drive to create a destination and leisure facility for the city. A Member welcomed the news that the land had gained value and she sought an assurance that every effort would be made to ensure the city could meet the challenges of the internet /online shopping and provide what people wanted from their city.

Justin Pickford set out the high level indicative timeline for Members to note:-  March – September 2018 Retender/procurement for Leisure Centre & Bus Station Build  October/November 2018 Return to Council with confirmed Costs  November 2018 Appoint Contractor  Winter 2018/ Early 2019 Commence work on site  November/December 2020 Facilities open to the public

Justin Pickford invited Phil Lewis to present details of the Procurement Strategy and outline details of the enabling works. He also invited Iain McNeill to provide details of the highway elements for the Bus Station following the withdrawal of the Crown Estate.

Iain McNeill confirmed that following further investigation and planning by the Build team, there was no imperative to close the Bus Station before May 2018. It was currently anticipated that Stagecoach would be able to remain in the Bus Station buildings after May 2018 until the new Bus Station opens.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Leisure Complex and Bus Station Programme Board Minutes: 30 January 2018Minutes 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Exeter

Search all
  1. Leisure Complex and Bus Station Programme Board Minutes - 30 January 2018This decision
  2. Minutes of the Leisure Complex and Bus Station Programme BoardAgreed
  3. Leisure Complex and Bus Station Programme Board MinutesAgreed
  4. Leisure Complex and Bus Station Programme Board Minutes 5 March 2018Agreed
  5. Leisure Complex and Bus Station Programme Board Minutes - 22 March 2017Agreed
  6. Leisure Complex and Bus Station Programme Board - Minutes 28 June 2016Agreed

More from Exeter Executive

All decisions
MeetingDecisionOutcome
17 Aug 2026 Neighbourhood Community Infrastructure Levy ConsultationAgreed: RESOLVED that Executive: (1) approve the continued use of Neighbourhood Community Infrastructure Levy (CIL) f... Agreed Open
17 Aug 2026 Review of Exeter Business Centre Ltd.AGREED: RESOLVED that Executive: (1) note the current position of Exeter Business Centre Ltd and the review of Exeter... Agreed Open
17 Aug 2026 Members’ Allowances and Expenses Paid 2025/26AGREED: RESOLVED that the Executive note the allowances paid to and expenses claimed by Members in 2025/26. Reason fo... Agreed Open
28 Apr 2026 Exeter City Centre Vision and Strategy 2026 – 2031 Public ConsultationAgreed: RESOLVED that: 1) the publication of the draft City Centre Strategy 2026 – 2031 be approved for public consul... Agreed Open
28 Apr 2026 Exeter Cultural Strategy 2026 – 2031 Public ConsultationAgreed: RESOLVED that: 1) the publication of the draft Cultural Strategy 2026 - 2031 be approved for public consultat... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies