Leisure Complex and Bus Station Programme Board Minutes 5 March 2018

Agreed Executive 1 paper

Executive agreed this item on Tuesday 13 March 2018. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

Agreed That the minutes of the Leisure Complex and Bus Station Programme Board meeting held on 5 March 2018 be received and, where appropriate, adopted. Reason for As set out in the minutes.
Word for word from the decision Exeter published for this meeting. Source: committees.exeter.gov.uk

Follow this further

Built from Exeter's papers

What the report saysPro

Report to Executive, 3 pages

LEISURE COMPLEX AND BUS STATION PROGRAMME BOARD

Monday 5 March 2018 Present:-

Councillor Bialyk (Chair) Councillors Denham, Edwards, Pearson, [name removed] and Wardle

Apologies:-

Councillor Prowse

Also Present

Chief Executive & Growth Director, City Surveyor, Communications Officer, Project Manager - Leisure Operations and Democratic Services Officer (Committees) (SLS)

Justin Pickford - Baker Ruff Hannon Iain McNeill – WSP Group Phil Lewis - Randall Simmonds

5 MINUTES

The minutes of the meeting held on 30 January 2018 were taken as read and signed by the Chair as correct, subject to the correction of the resolution in Minute 3 by the replacement of the word ‘noted’ with ‘approved’.

6 DECLARATIONS OF INTEREST

No declarations of pecuniary interest were made.

7 PRESENTATION - PROJECT DELIVERY GOVERNANCE

Justin Pickford made a presentation which detailed proposals for the future project delivery for the Leisure Complex and Bus Station project through a number of work stream projects within the programme. He sought Members’ approval for the establishment of five Project Working Groups to facilitate a more targeted approach to better address the changing activity through the project lifecycle. The Project Working Groups would offer a more focused environment for the project’s delivery and progress vital elements of the project. The established governance of the Steering Group and the Programme Board would continue and all pertinent matters and decisions would continue to be presented to Members of the Programme Board.

Justin Pickford referred to his role as Programme Manager and identified the Project Managers who would oversee five specific Project Working Groups to pursue the various work streams which were detailed as follows:-

 Leisure Centre Build;  Bus Station Build (to include Bus Station leases and Long Distance coaches);  Remaining Site;  Interim Bus Station Arrangements; and  Leisure Operator Procurement The presentation to Members included the governance arrangements and terms of reference for the Project Working Groups as well as details of the attendees. Each would include a core membership of Project Manager, Client Lead, and Programme Manager and invited Members with additional attendees including specialist consultants as required. It was the intention to draw on expertise from within Exeter City Council including officers from Estates; Communications, Legal, Procurement, Finance, City Development and Human Resources.

A Member expressed her disquiet about the lack of Conservative Members included and a potential lack of scrutiny. The Chair explained that the individual Project Managers would have specifically defined authority and he emphasised that this would not change the overarching role of the Programme Board. If there was a need to step outside of the authorisation parameters, a meeting of the Programme Board would be called to enable Members to be consulted. This would not change his role as Portfolio Holder for Health and Wellbeing, Communities & Sport, or that of the Leader and their respective responsibilities for the St Sidwells Point and Bus Station projects. The individual Project Working Groups would enable the increasingly heavy workload to be more appropriately shared, and create a much needed opportunity to allow more in depth and targeted discussion. He also referred to the positive current lead being taken on the project and the desire for it to continue in that way. It was confirmed that the Members invited to the Project Working Groups would be a sounding board for the Project Manager, they would not be making any decisions or granting any approvals.

Each of the Project Managers presented the scope of their work under the authorisation levels identified, the detail of which would be included in the presentation to be attached to the minutes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Leisure Complex and Bus Station Programme Board Minutes 5 March 2018Minutes 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Exeter

Search all
  1. Leisure Complex and Bus Station Programme Board Minutes 5 March 2018This decision
  2. Minutes of the Leisure Complex and Bus Station Programme BoardAgreed
  3. Leisure Complex and Bus Station Programme Board MinutesAgreed
  4. Leisure Complex and Bus Station Programme Board Minutes - 30 January 2018Agreed
  5. Leisure Complex and Bus Station Programme Board Minutes - 22 March 2017Agreed
  6. Leisure Complex and Bus Station Programme Board - Minutes 28 June 2016Agreed

More from Exeter Executive

All decisions
MeetingDecisionOutcome
17 Aug 2026 Neighbourhood Community Infrastructure Levy ConsultationAgreed: RESOLVED that Executive: (1) approve the continued use of Neighbourhood Community Infrastructure Levy (CIL) f... Agreed Open
17 Aug 2026 Review of Exeter Business Centre Ltd.AGREED: RESOLVED that Executive: (1) note the current position of Exeter Business Centre Ltd and the review of Exeter... Agreed Open
17 Aug 2026 Members’ Allowances and Expenses Paid 2025/26AGREED: RESOLVED that the Executive note the allowances paid to and expenses claimed by Members in 2025/26. Reason fo... Agreed Open
28 Apr 2026 Exeter City Centre Vision and Strategy 2026 – 2031 Public ConsultationAgreed: RESOLVED that: 1) the publication of the draft City Centre Strategy 2026 – 2031 be approved for public consul... Agreed Open
28 Apr 2026 Exeter Cultural Strategy 2026 – 2031 Public ConsultationAgreed: RESOLVED that: 1) the publication of the draft Cultural Strategy 2026 - 2031 be approved for public consultat... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies