Exeter City Council
Executive, Tuesday 4 October 2022 at 5.30pm

2022/23 General Fund Capital Monitoring Statement - Quarter 1

Agreed Executive 5 papers

Executive agreed this item on Tuesday 4 October 2022. Below is the council's own wording, with the papers it was decided on.

Item104

Resolved

Agreed: RECOMMENDED that Council approve: (1) the overall financial position for the 2022/23 annual capital programme; and (2) the amendments and further funding requests to the Council’s annual capital programme for 2022/23. Reason for As set out in the report.
Word for word from the decision Exeter published for this meeting. Source: committees.exeter.gov.uk

Follow this further

Built from Exeter's papers

What the report saysPro

Report to Executive, 9 pages

REPORT TO EXECUTIVE Date of Meeting: 4 October 2022

REPORT TO COUNCIL Date of Meeting: 18 October 2022

Report of: Director Finance

Title: 2022/23 General Fund Capital Monitoring Statement – Quarter 1

Is this a Key Decision? No

Is this an Executive or Council Function? Council

1. What is the report about? To report the current position in respect of the Council’s revised annual capital programme and to advise Members of the anticipated level of deferred expenditure into future years.

The report seeks Member approval to amend the annual capital programme in order to reflect the reported variations.

2. Recommendations: It is recommended that Executive Committee supports and recommends to Council to approve:

(1) The overall financial position for the 2022/23 annual capital programme; and

(2) The amendments and further funding requests to the Council’s annual capital programme for 2022/23.

3. Reasons for the recommendation: 3.1. Local authorities are required to estimate the total of capital expenditure that it plans to incur during the financial year when it sets the prudential indicators for capital expenditure. This shows that its asset management and capital investment strategies are affordable, prudent and sustainable.

Capital expenditure is a significant source of risk and uncertainty since cost variations, delays and changing specifications are often features of large and complex capital projects.

In order to manage the risks associated with capital programming the annual capital programme is updated every three months to reflect any cost variations, slippage or acceleration of projects. 4. What are the resource implications including non financial resources The financial resources required are set out in the body of this report.

5. Section 151 Officer comments: 5.1 Members should note the significant deferrals in the schemes approved. The current economic climate, with rising interest rates however makes the existing programme unaffordable. Interest rates have risen by over 2.5% since the start of the year. Members are reminded that the interest rate charged by the PWLB is based on the cost of the Government’s borrowing, not the base rate set by the Bank of England, thus the rate rise being higher than the increase in base rate currently seen. If the full amount required for the Capital Programme, as it stands, was borrowed it would add around £1.3m cost to the General Fund. This is unaffordable and therefore the management Team will be undertaking a review of the programme to determine areas that can be removed or postponed.

6. What are the legal aspects? The capital expenditure system is framed by the Local Government and Housing Act 1989.

7. Monitoring Officer’s comments: It is clear from the S.151 Officers comments that the Capital Programme as it currently stands is unaffordable. SMB is alive to this issue and are working on reporting back to Members with proposals as to how we reduce this area of budgetary pressure.

8. Report details: 8.1. REVISIONS TO THE CAPITAL PROGRAMME

The 2022/23 Capital Programme, including commitments brought forward from 2021/22, was last reported to Executive on 5 July 2022. Since that meeting the following changes have been made that have increased the programme:

Description £ Approval/Funding

Capital Programme, 131,182,860 as reported to Council 19 July 2022

Energy Saving Projects 64,000

Fleet Leasing Costs 2,110,830 Approved by Council 19 July 2022

Pinhoe Playing Fields Upgrades 49,280

Revised Capital Programme 133,406,970 8.2. PERFORMANCE

he revised capital programme for the current financial year is £133.407 million. During the first three months of the year the Council spent £46.772 million on the programme, which equates to 35.06% of the revised programme. This compares with £5.046 (7.48%) that was spent in the first three months of 2021/22.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2022/23 General Fund Capital Monitoring Statement: Quarter 1Report 9 pages DownloadRead as text
PDF
Appendix 1Appendix 1 3 pages Download
PDF
Appendix 2Appendix 2 3 pages Download
PDF
Appendix 3Appendix 3 1 pages Download
PDF
Appendix 4Appendix 4 1 pages Download

At this meeting

Whole meeting

Who was there

11 of 24 attended
PB
Councillor Philip Bialyk Leader of the CouncilChair, present
LW
Councillor Laura Wright Deputy Leader and Portfolio Holder for Arts, Culture and Corporate ServicesDeputy Chair, present
BD
Councillor Barbara DenningCommittee Member, present
AG
Councillor Amal Ghusain Portfolio Holder for City Management & Environmental ServicesCommittee Member, present
EM
Councillor Emma Morse Portfolio Holder for City Development and PlanningCommittee Member, present
JP
Councillor Josie ParkhouseCommittee Member, present
MP
Councillor Martin PearceCommittee Member, present
RW
Councillor Ruth Williams Portfolio Holder for Recycling, Waste Management & WaterwaysCommittee Member, present
DW
Councillor Duncan Wood Portfolio Holder for Climate ChangeCommittee Member, present
KH
Karime HassanOfficer, in attendance
BA
Bindu ArjoonOfficer, in attendance
BA
Baan Al-KhafajiOfficer, expected

All 24 on the meeting page

On this subject at Exeter

Search all
  1. 2022/23 General Fund Capital Monitoring Statement - Quarter 1This decision
  2. General Fund Estimates and Capital Programme 2026/27Agreed
  3. Overview of General Fund Revenue Budget 2023/24 - Quarter 4Agreed
  4. General Fund Capital Monitoring 2023/24 and Revised Capital Programme for 2024/25 and Future YearsAgreed
  5. Overview of General Fund Revenue Budget 2023/24 – Quarter 3Agreed
  6. 2023/24 General Fund Capital Monitoring Statement – Quarter 3Agreed

More from Exeter Executive

All decisions
MeetingDecisionOutcome
17 Aug 2026 Neighbourhood Community Infrastructure Levy ConsultationAgreed: RESOLVED that Executive: (1) approve the continued use of Neighbourhood Community Infrastructure Levy (CIL) f... Agreed Open
17 Aug 2026 Review of Exeter Business Centre Ltd.AGREED: RESOLVED that Executive: (1) note the current position of Exeter Business Centre Ltd and the review of Exeter... Agreed Open
17 Aug 2026 Members’ Allowances and Expenses Paid 2025/26AGREED: RESOLVED that the Executive note the allowances paid to and expenses claimed by Members in 2025/26. Reason fo... Agreed Open
28 Apr 2026 Exeter City Centre Vision and Strategy 2026 – 2031 Public ConsultationAgreed: RESOLVED that: 1) the publication of the draft City Centre Strategy 2026 – 2031 be approved for public consul... Agreed Open
28 Apr 2026 Exeter Cultural Strategy 2026 – 2031 Public ConsultationAgreed: RESOLVED that: 1) the publication of the draft Cultural Strategy 2026 - 2031 be approved for public consultat... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies