MISCELLANEOUS 1 - LAND AT COLDEAST HOSPITAL (LOT 2) SARISBURY GREEN

Agreed Planning 1 paper

Planning Committee agreed this item on Wednesday 27 March 2013. Below is the council's own wording, with the papers it was decided on.

Item6(11)

Resolved

RESOLVED that in addition to those matters already secured through the resolution of the Planning Committee on the 23rd October 2012, that the Section 106 planning obligation also secures the following: ( i ) the applicant/owner undertakes the partial external restoration of the Mansion House in the event that a developer is not signed up to undertake the refurbishment/ restoration of the Mansion House within two years; (ii) that the necessary funds to enable the partial external restoration are secured and made available for such use if no developer has been secured within two years; (iii) the details of the precise scheme of restoration works are agreed with Fareham Borough Council prior to their execution.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Planning Committee

P/12/0299/FP PARK GATE HOMES & COMMUNITIES AGENT: WYG PLANNING & AGENCY & MILLER HOMES LTD DESIGN HYBRID PLANNING APPLICATION: FULL CONSENT FOR THE ERECTION OF 168 RESIDENTIAL DWELLINGS WITH ASSOCIATED ACCESS, PARKING, LANDSCAPING AND INFRASTRUCTURE; EQUIPPED PLAY SPACE; CHANGE OF USE, EXTENSION & RESTORATION OF THE MANSION HOUSE FOR USE AS A HOTEL WITH FUNCTION ROOMS & FACILITIES, ANCILLARY ACCOMMODATION, ASSOCIATED WORKS, LANDSCAPING, PARKING & ACCESS; RESTORATION & REUSE OF EXISTING BROOK LANE GATE LODGE FOR RESIDENTIAL PURPOSES WITH ERECTION OF NEW GARAGE, CURTILAGE & ACCESS; REINSTATE BRICK PIERS & WING WALLS TO BROOK LANE ENTRANCE; USE OF LAND & WOODLAND FOR OPEN SPACE/RECREATION WITH NEW PATHS.

OUTLINE CONSENT FOR THE ERECTION OF SHELTERED ACCOMMODATION AND THE PROVISION OF COMMUNITY FACILITIES TO INCLUDE SPORTS PITCHES, COMMUNITY BUILDING/PAVILION WITH CHANGING FACILITIES & COMMUNITY MEETING ROOM, ALLOTMENTS, CEMETERY, PUBLIC SWIMMING POOL WITH FACILITIES, PUBLIC CAR PARK & NEW ACCESS FROM BARNES LANE, WITH DEMOLITION OF FORMER FARM BUILDINGS LAND AT COLDEAST HOSPITAL (LOT 2) SARISBURY GREEN HAMPSHIRE

Report By Kim Hayler - Ext 2367 Introduction This application was reported to a special meeting of the Planning Committee on 23 October 2012. Following consideration, Members resolved that planning permission should be granted subject to the completion of the necessary legal agreements and the imposition of conditions.

Extensive dialogue has continued between the applicants, the developer, Officers and Hampshire County Council since the Committee resolution. Due to the extent of the issues to be resolved relating to the legal agreements planning permission has not been issued to date but it is anticipated that it will be shortly.

Planning Considerations - Key Issues Policy CS10 Coldeast Hospital Strategic Development Allocation is one of the key policies for the site. Amongst other things this policy states that the repair and restoration of all the locally listed buildings at the site should be resolved as part of any planning permission.

At the time that the planning application was considered by the Planning Committee the Homes and Communities Agency (HCA) advised that discussions were well advanced with Sanguine Hospitality Ltd as a preferred developer for the refurbishment of the hotel. Sanguine had essentially agreed legal documents with the site owner but wanted to await the outcome of the planning process before committing to a legal contract. The intention at that time was to commence refurbishment in 2013.

In light of the circumstances the Planning Committee sought to secure two key elements in respect of the Mansion House through the planning obligation.

Firstly the applicant/land owner was required to commission a yearly condition survey of the building to ensure it was fully wind and weather tight. In the event this was not the case they were required to carry out the necessary works to meet this obligation. It was also agreed that a financial bond should be put in place to ensure the funding was available to cover these works.

Secondly a commitment was also given by the HCA that if Sanguine did not proceed then then they would market the Mansion House again within 12 months. Details of any future marketing of the Mansion House was to be agreed with Fareham Borough Council.

The HCA has recently contacted officers to explain the latest situation with the Mansion House. Negotations with Sanguine followed a marketing exercise in the summer of 2011. Since then, with negotiations on-going, the condition of the Mansion House has continued to deteriorate. The legal discussions became protracted as the interested party were unhappy with the increasing costs of refurbishment. Sanguine have subsequently walked away from the negotiations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MISCELLANEOUS 1: LAND AT COLDEAST HOSPITAL (LOT 2) SARISBURY GREENReport 531 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
NW
Councillor Nick WalkerChairman, present
AM
Councillor Arthur MandryVice-Chairman, present
BB
Councillor Brian BayfordCommittee Member, apologies, sent representative
PD
Councillor Peter DaviesCommittee Member, present
MF
Councillor Michael Ford, JPCommittee Member, present
RP
Councillor Roger Price, JPCommittee Member, present
DS
Councillor David SwanbrowCommittee Member, present
DW
Councillor David WhittinghamCommittee Member, present
PW
Councillor Paul Whittle, JPCommittee Member, apologies
KE
Councillor Keith EvansReserve, present as substitute

More from Fareham Planning Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 12 August 2026 be confirmed and signed as a c... Decided Open
9 Sep 2026 Q/0559/26 - Land Between 75 & 77 Church Road Warsash Southampton SO31 9GDRESOLVED that Members delegate authority to the Head of Planning, in consultation with the Solicitor to the Council, ... Agreed Open
9 Sep 2026 P/26/0722/FP - Single Storey Side Extension at 44 Crispin Close Locks Heath SO31 6TDRESOLVED that: - (i) IT BE CONFIRMED that had the planning application for a side extension at 44 Crispin Close (as p... Decided Open
9 Sep 2026 P/26/0791/AD - Barchester Care Home Stubbington Lane Stubbington PO14 2NFRESOLVED that: - (i) Advertisement Consent for Five Years be GRANTED , subject to:- (a) the Conditions in the report;... Decided Open
12 Aug 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 15 July 2026 be confirmed and signed as a cor... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies