Council Car Park and Pedestrian Highway Works Contract

Decided Executive 1 paper

Executive decided this item on Monday 2 September 2013. Below is the council's own wording, with the papers it was decided on.

Item11(8)

Resolved

RESOLVED that the Executive accepts the tender submitted by the contractor ranked 1 (as set out in the confidential appendix), and being the most advantageous tender received, the contract is awarded to that company.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 2 September 2013 Portfolio: Policy and Resources Subject: Council Car Park and Pedestrian Highway Works Contract Director of Finance and Resources Report of: A dynamic, prudent, progressive and best value Council Strategy/Policy: Corporate Objective:

Purpose: This report considers the tenders received for resurfacing and repair works at numerous locations that include car park and footways throughout the borough and recommends an award of contract for the works.

Executive summary: Following the completion of a condition survey of the Council’s public car parks, footpaths and service areas, a programme of repair and improvement works were identified to maintain the assets to a good standard. In addition, new requirements have been identified for additional parking at Portchester Community Centre.

This report provides the Executive with information regarding the tenders received for these works and seeks an award of contract.

Recommendation: That the tender submitted by the contractor ranked 1 (as set out in the confidential appendix), being the most advantageous tender received, be accepted and the contract awarded to the company.

Reason: To maintain the value of the Council assets and provide well maintained car parks, service areas and pedestrian footways for public use.

Cost of proposals: The cost of this project is estimated to be £330,000. These works are to be predominately funded from the previously approved car park improvements capital programme and this will supplemented by revenue and capital budgets from each of the respective service areas. Appendix A: Executive Briefing Paper Tender Prices and Evaluation (Confidential Appendix)

Background papers: Executive Briefing Paper Date: 2 September 2013

Subject: Council Car Park and Pedestrian Highway Works Contract

Briefing by: Director of Finance and Resources

Portfolio: Policy and Resources

INTRODUCTION

1. During 2012 a condition survey was carried out by the Building Services Team. This identified a number of car park sites that required repairs. In addition the Leisure and Community team had identified a requirement to provide additional parking at the new Portchester Community Centre.

2. This project includes for the following works:

 The reconstruction of eight car park surfaces at Abshot Community Centre, Broadcut, Cams Alders, Fareham Job Centre, Malthouse Lane, Meon Shore, Titchfield Recreation Ground and Wicor Recreation Ground  Repairs to pedestrian, service and garage areas at housing sites in Bishopsfield Road  Line marking works to 28 car park sites throughout the borough  The extension of the car park at Portchester Community Centre  Additional parking at Fareham Leisure Centre  Repair works at Northmore Close and Barnfield Court housing sites.  Across all the above services works to carry patch repair work, kerb, channel repairs, drain clearance and general car park maintenance items were included.

3. A packaged contract was developed for these works in order to ensure achieving the best value for money for the Council. The project was advertised on the South East Business Portal for organisations to submit their expressions of interest and complete a pre-qualification questionnaire. The subsequent applicants were evaluated and the tender list determined.

4. Invitations to tender for the project were issued on 5th June 2013 to 6 contractors. PROPOSAL

5. On the 3rd July, three tenders were received and opened by Councillor K Evans, Executive Member for Strategic Planning and Environment, and the tender price details are presented in the confidential appendix A.

EVALUATION PROCESS

6. The contract documents define a pre-determined scoring mechanism whereby tenders are assessed on price, service and quality.

7. The tender submissions were evaluated and the scores weighted as specified in the invitation to tender. The scores and ranking for all three tenders received are represented in the confidential appendix A.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Council Car Park and Pedestrian Highway Works ContractReport 116 KB DownloadRead as text

At this meeting

Whole meeting
2MinutesOn the agenda 7Minutes / References from Other CommitteesDecided 8(1)Leisure Strategy ReviewApproved 8(2)Review of Tourist Information CentreAgreed 8(3)2014 Commemorates World War I Centenary and D Day 70th AnniversaryAgreed 8(4)Portchester MUGAAgreed 9(1)Development Sites and Policies Plan: Fareham College and other new site allocations: ConsultationDecided 9(2)Titchfield Abbey Conservation Area Character Appraisal and Management StrategyAgreed 9(3)Additions to the Local List of Buildings of Special Architectural or Historic InterestDecided 9(4)Preparation of Welborne Plan: Quarterly Financial UpdateDecided 9(5)Response to Consultation: Highway Proposals for Newgate Lane and Peel Common, Fareham and Western Access to GosportAgreed 10(1)Parking Enforcement Service Annual ReportDecided 10(2)Emergency Planning Annual ReportAgreed 10(3)Health and Safety Performance 2012/13Decided 10(4)Scrap Metal Dealers Act 2013On the agenda 11(1)Annual Review of the Corporate Strategy 2011/2017Decided 11(2)Council Tax Support - Year 2Approved 11(3)Annual Update - Local Service AgreementsDecided 11(4)Quarterly Financial Monitoring Report 2013/14Decided 11(5)Treasury Management Monitoring Report 2013/14Decided 11(6)Taxi TariffApproved 11(7)New Homes Bonus and the Local Growth Fund: Response to ConsultationApproved
11(8)Council Car Park and Pedestrian Highway Works ContractThis decision
12Exclusion of Public and PressDecided 13(1)Purchase of Properties from the Homes and Communities AgencyPrivate

Who was there

6 of 18 attended
SW
Councillor Seán WoodwardCommittee Member, present
TC
Councillor Trevor CartwrightCommittee Member, present
BB
Councillor Brian BayfordCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
CH
Councillor Connie HockleyCommittee Member, present
LK
Councillor Leslie KeebleCommittee Member, present
LU
Leigh UsherCommittee Officer, in attendance
SB
Councillor Susan BellGuest, in attendance
JB
Councillor John BryantGuest, in attendance
PD
Councillor Peter DaviesGuest, in attendance
ME
Councillor Marian EllertonGuest, in attendance
MF
Councillor Michael Ford, JPGuest, in attendance

All 18 on the meeting page

On this subject at Fareham

Search all
  1. Council Car Park and Pedestrian Highway Works ContractThis decision
  2. Electric Vehicle Charging Tariff for Osborn Road Car ParkApproved
  3. Review of Implementation of car parking charges at coastal car parksDecided
  4. Petition regarding car parking at Middle Road car park, Park GateAgreed
  5. Petition - Middle Road, Parkgate car parkDecided
  6. Osborn Road Multi Storey car parkApproved

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies