Resolved
RESOLVED that the Executive approve the open spaces improvement programme 2013 - 2023.
Executive approved this item on Monday 4 November 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Executive approve the open spaces improvement programme 2013 - 2023.
Report to the Executive for Decision 4 November 2013 Portfolio: Leisure and Community Subject: Open Spaces Improvement Programme Report of: Director of Community Strategy/Policy: Leisure Strategy
Corporate Leisure for Health and for Fun Objective:
Purpose: To update the Executive on the implementation of the existing open spaces improvement programme and to recommend a new programme from 2014-15 to 2022-23.
Executive summary: In November 2012, the Executive approved an open spaces improvement programme for the Councils outdoor sports facilities and for play areas and other recreational space.
This report reviews progress against this plan and presents an updated programme for the period up to March 2023. The projects will be funded from developers contributions where available or from contributions from the Community Infrastructure Levy, subject to collection of funds and individual scheme approval reports to the Executive.
The draft programme was considered and supported by the Leisure and Community Policy Development and Review Panel on 4 September 2013.
Recommendation: That the Executive approve the open spaces improvement programme 2013 - 2023.
Reason: To facilitate the improvement of the outdoor sport, play spaces and other recreational areas utilising available developer contributions and to guide the implementation of the Community Infrastructure Levy.
Cost of proposals: Schemes will be funded from existing developers contributions where available and or external funding, subject to individual scheme approval reports to the Executive for funding from the Community Infrastructure Levy. Executive Briefing Paper Date: 4 November 2013
Subject: Open Spaces Improvement Programme
Briefing by: Director of Community
Portfolio: Leisure and Community
INTRODUCTION
1. In November 2012, the Executive approved a five year improvement programme for the Council's outdoor sports facilities, play space and other recreational facilities utilising developer contributions.
2. This report reviews progress against this plan and presents an updated programme for the period from April 2014. The projects will be funded from developer contributions where available or from contributions from the Community Infrastructure Levy (CIL), subject to collection of funds and successful bids to the Executive. External funding opportunities will also be explored where available.
OPEN SPACE IMPROVEMENT PROGRAMME
Progress on 2012 -2013 Projects 3. All projects in the 2012-13 programmes have been completed on time and within budget with the exception of the protective netting at the Green, Sarisbury. Difficulties have been encountered with sourcing a system that is sufficiently robust, easy to erect and is compliant with the planning requirements in a conservation area. Further research and investigations are therefore required and the project has been deferred to 2013/14 with the aim of being in place prior to the 2014 cricket season if a practical solution can be found. 4. Whilst the new changing rooms at the Wicor Recreation Ground have been completed, some further improvement works to the car park at this location will be undertaken in November 2013. 5. The project to replace the dilapidated flat roof, install new electrics and redecorate the building at Red Barn allotments has been completed
Progress on 2013 - 2014 Projects. 6. The installation of the drainage scheme at Burridge Recreation Ground has been completed and is now in the initial maintenance period. 7. The project to install drainage to the football pitch at Allotment Road Recreation Ground has been removed from the programme and this site is no longer considered suitable for dual use due to the conflict between football and cricket and therefore is now a cricket only site. With cricket being a summer sport the drainage concerns affecting the football pitch do not need to be addressed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Open Spaces Improvement ProgrammeReport | 180 KB | DownloadRead as text |
Follow Executive at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... | Agreed | Open |
| 7 Sep 2026 | References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... | Agreed | Open |
| 7 Sep 2026 | Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... | Approved | Open |
| 7 Sep 2026 | Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... | Approved | Open |
| 7 Sep 2026 | Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.