RESOLVED that the Executive: (a) agrees the governance and decision-making structure as set out in Appendix A to the report; (b) delegates authority to the Director of Finance and Resources to: i. appoint a Quantity Surveyor and Construction Project Manager for the project; ii. conclude land transactions within the Enterprise Zone, sufficient to enable construction to be undertaken; iii. formally sign off the final design specification for the built assets; iv. award the construction contracts for the three project elements, to the most economically advantageous bidder, using previously agreed award criteria; and v. award the contract for operate the Innovation Centre; with all above listed delegations being subject to the costs being contained within the overall budget available for the project and, in relation to iii, iv and v above, only following consultation with the Project Member Working Group with all decisions being reported retrospectively to the Executive; and (c) confirms the composition of the Project Member Working Group as Councillor T M Cartwright (Chairman), Councillor Mrs K Mandry, Councillor M J Ford, JP and Councillor J S Forrest.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 4 November 2013 Portfolio: Policy and Resources Subject: Daedalus Investment Project: Project Appraisal and Governance Arrangements Report of: Director of Finance and Resources Strategy/Policy: Corporate To promote the economic success of the Borough Objective:
Purpose: To update Members on the overall progress with the Daedalus Investment project and to seek approval for governance arrangements including setting up a Project Member Working Group and certain delegations of authority to ensure that the project can proceed within the agreed timescales.
Executive summary: In July 2013 the Executive supported a proposal to provide improvements to the airfield, provision of new hangar space and an Innovation Centre for small businesses at the Solent Enterprise Zone, Daedalus. Subsequently, at its last meeting on 7 October 2013, the Executive agreed revised funding arrangements for the project.
Overall, the project contains some very challenging timescales. Principally among these is the need to complete the Innovation Centre by March 2015. Work has already commenced on initial design work and a procurement process to appoint a Design and Build contractor and other professional consultants with a view to a start on site in May 2014.
Specification and design work on the airfield improvements is underway and work is scheduled to take place between March and June 2014. Preparatory works will also be undertaken to the secondary runway to allow its use during works to the main runway.
Negotiations are underway concerning the location of the new hangar and the timing of its construction with the Homes And Communities Agency (HCA). The nature of its specification and design will be sufficiently flexible to ensure its’ suitably for the length of its useful life, but initially will be guided to a certain extent on the outcome of a pre-letting marketing approach.
The report sets out a proposed decision making structure for the project, including the setting up of a member Working Group. Recommendations: It is recommended that the Executive
(a) Agree the governance and decision-making structure as set out in appendix A to the report; (b) Consider the composition of the Project Member Working Group and to nominate representatives on the group
Reason: To enable the project to proceed in line with the proposed timescales whilst ensuring Member involvement and scrutiny.
Cost of proposals: The cost of supporting the governance structure will be met within existing resources.
Appendices A: Decision Making structure B: Outline project timetable C: Outline project budget D: Preliminary sketches of the Innovation Centre for illustrative purposes Executive Briefing Paper Date: 4 November 2013
Subject: Daedalus Investment Project: Project Appraisal and Governance Arrangements
Briefing by: Director of Finance and Resources Job Title
Portfolio: Policy and Resources
INTRODUCTION
1. The Daedalus Investment Project comprises three distinct, but inter-related elements. A new Innovation Centre will provide office and workshop space for emerging small business and will be funded by a grant of £5.3m from the HCA. This grant is conditional on the provision of improvements to the airfield at a cost of £1.5m and provision of new hangar space, also costing £1.5m, both of which will be funded via borrowing by the Borough Council.
2. The timescale for achieving the completion of these projects by March is very challenging. This is particularly so in the case of the Innovation Centre, a major new build project in a prominent location at the entrance to the site, adjacent to Fareham College’s new Centre for Excellence for Engineering, Manufacturing and Advanced Skills Training (CEMAST).
3. The following paragraphs describe the progress in relation to each aspect of the project.
PROPOSAL DETAILS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.