RESOLVED that the Executive: (a) approves the updated capital programme as set out in Appendix A to the report; (b) approves the revised revenue budget for 2014/15 and the proposed revenue budget for 2015/16, as set out in Appendix B to the report; (c) approves the proposed fees and charges for 2015/16, as set out in Appendix D to the report; (d) agrees the use of Section 13A to provide a Council Tax discount to flooded properties in accordance with guidance issued by Government as set out in paragraphs 23 – 29 of the report; and (e) recommends to Council an unchanged Local Council Tax Scheme for 2015/16, as set out in Appendix E of the report.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 01 December 2014 Portfolio: Policy and Resources Subject: 2015/16 Draft Spending Plans Report of: Director of Finance and Resources Strategy/Policy: Finance Strategy 2015/16
Corporate Dynamic, prudent and progressive Council Objective:
Purpose: This report seeks the Executive's approval for the updated capital programme, the revised budget for 2014/15 and the proposed fees and charges, and revenue budgets for 2015/16.
Executive summary: The capital programme, which has been updated to reflect the slippage in 2013/14 and new schemes that have been added to the programme during the year, now totals £33,176,000 for the years 2014/15 to 2018/19, as set out in Appendix A to this report.
The 2014/15 base revenue budget for Executive and non-Executive services of £13,027,400, was finally approved by the Executive on 10 February 2014.
The revised revenue budget for 2014/15 is £13,009,700, a reduction of £17,700 or 0.1%. The briefing paper contained in the report provides details of the budgets for each of the portfolios, together with an explanation of all of the significant variations in each area.
The Executive reviewed the Council’s finance strategy on 6 October 2014, taking account of significant budget issues and the future level of general government support.
Against this background of uncertainty, the Executive approved strict budget guidelines for 2015/16 and these are also set out in the briefing paper. The Finance Strategy also recognised the requirement for action to be taken to reduce service expenditure through a range of actions (for example efficient ways of working, savings through procurement and business transformation/value for money reviews and maximising income generating opportunities).
The base revenue budget for 2015/16 is £11,616,200, a decrease of £1,411,200 or - 10.8%. The budgets for the individual services are set out in the briefing paper, together with an explanation of the variations. The existing fees and charges have been reviewed and the proposed fees and charges for 2015/16 are set out in Appendix D to this report.
Recommendations: (a) That the updated capital programme as set out in Appendix A to the report, be approved;
(b) That the revised revenue budget for 2014/15 and the proposed revenue budget for 2015/16, as set out in Appendix B to the report, be approved;
(c) That the proposed fees and charges for 2015/16, as set out in Appendix D to the report, be approved;
(d) That the Executive agrees the use of Section 13A to provide a Council Tax discount to flooded properties in accordance with guidance issued by Government as set out in paragraphs 23 – 29 of the report; and
(e) That the Executive recommend to Full Council an unchanged Local Council Tax Scheme for 2015/16, as set out in Appendix E.
Reason: The Council has a co-ordinated strategic, service and financial planning process and this report brings together the spending plans for the Council's services for 2015/16.
The overall revenue budget will be presented to the Executive for approval on 5 January 2015 and will form a major element of the council tax for 2015/16 that will be approved at a special meeting of the Council in February 2015.
Cost of proposals: As detailed in the briefing paper contained in the report.
Appendices A: Capital Programme 2014/15 to 2018/19 B: Revenue Budget - Revised 2014/15 and Proposed 2015/16 C: Service Narrative & Responsibilities D: Executive Portfolio Fees and Charges 2015/16 E: Local Council Tax Support Scheme 2015/16
Background papers: Executive Briefing Paper Date: 01 December 2014
Subject: 2015/16 Draft Spending Plans
Briefing by: Director of Finance and Resources
Portfolio: Policy and Resources
INTRODUCTION
1. The Council has a co-ordinated strategic, service and financial planning process and this report brings together the revenue and capital spending and fees & charges for 2015/16, allowing members to consider in detail these plans for the provision of services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.