RESOLVED that the Executive: (a) approves the Master Plan for the Western Wards Community Action Team area; (b) agrees that the designation of the land at Hook Recreation Ground be changed from “parks and amenity open space” to “natural green space”, be no longer for formal sports provision and that the changing rooms be demolished within 12 months, if a suitable alternative use for the building cannot be found; and (c) approves a project to improve the WC facilities and replace the main hall flooring at the Whiteley Community Centre at a budget cost of £100,000 with a maximum of £90,000 to be funded from the Whiteley Development Fund and the balance to be funded by the Whiteley Community Association.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Leisure and Community Policy Development and Review Panel – 23 July 2014 – Review of Community Buildings Draft Master Plan.
Appendix A – Community facilities in the Locks Heath ward. Appendix B – Community facilities in the Park Gate ward. Appendix C – Community facilities in the Sarisbury ward. Appendix D – Community facilities in the Warsash ward Executive Briefing Paper Date: 03 November 2014
Subject: Review of Community Buildings – Western Wards CATs Area
Briefing by: Director of Community
Portfolio: Leisure and Community
INTRODUCTION
1. As part of Fareham Borough Councils commitment to provide high quality community facilities across the Borough, a review of all of the Council owned community buildings was carried out in 2008.
2. In July 2008, the Executive agreed a broad vision for providing high quality community facilities across the Borough. The agreed way forward was to carry out a needs assessment in each of the CATs areas and then to prepare a master plan for implementing the outcome of each needs assessment.
3. The Executive agreed to a phased approach to implementing this, based on the CATs area as defined at that time:-
Phase 1 - Portchester; Phase 2 - Crofton; Phase 3 - Titchfield; Phase 4 - Fareham Town; and Phase 5 - Western Wards and Whiteley.
4. In November 2011, the Executive amended the phasing so that Fareham Town was carried out in phase 3 with the Titchfield area in phase 4. Phases one, two and three of the review have been completed.
WESTERN WARDS CATS AREA NEEDS ASSESSMENT
5. The Western Wards CATs area is made up of four wards; Sarisbury, Locks Heath, Park Gate and Warsash.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.