RESOLVED that the Executive agrees:- (a) that the capital programme for the period 2016/17 to 2020/21, amounting to £65,686,000 as set out at Appendix A to the report be approved; (b) that the proposed fees and charges for 2017/18, as set out in Appendix B to the report be approved; (c) that the revised 2016/17 general fund budget, amounting to £8,903,300 be approved; (d) that the base 2017/18 general fund revenue budget amounting to £8,616,700 be approved; and (e) that the use of the surplus on the spending reserve as set out in paragraphs 49-51 be approved.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 09 January 2017 Portfolio: Policy and Resources Finance Strategy, Capital Programme, Revenue Subject: Budget and Council Tax 2017/18 Report of: Director of Finance and Resources
Strategy/Policy: Finance Strategy 2017/18
Corporate Objective: A dynamic, prudent and progressive Council
Purpose: This report reviews the Council’s finance strategy and makes recommendations regarding the capital programme, the revised revenue budget for 2016/17, the fees and charges and the revenue budget for 2017/18.
Executive summary: This report gives the Executive the opportunity to consider the Council's capital programme, revised service budget for 2016/17, fees and charges for 2017/18 and proposed service budgets for 2017/18.
Capital Programme and Resources 2016/17 to 2020/21 The revised capital programme amounts to £65,686,000, and there are capital resources totalling £67,764,000 over the programme period. Whilst a surplus of capital resources exists, there are likely to be emerging spending requirements that require new resources to be accumulated now so that the Council can meet its future commitments.
Revised General Fund Revenue Budget 2016/17 The revised general fund revenue budget for 2016/17 amounts to £12,388,300 for service budgets with other budgets totalling -£3,485,000 giving an overall position of £8,903,300 which shows no change from the base budget for 2016/17.
General Fund Revenue Budget 2017/18 The proposed general fund budget for 2017/18 totals £11,800,700 for service budgets along with -£3,184,000 for other budgets giving an overall position of £8,616,700 which is a reduction of £286,600 against the original budget for 2016/17. Recommendation/Recommended Option: That the Executive agrees:
(a) that the capital programme for the period 2016/17 to 2020/21, amounting to £65,686,000 as set out at Appendix A to the report be approved;
(b) that the proposed fees and charges for 2017/18, as set out in Appendix B to the report be approved;
(c) that the revised 2016/17 general fund budget, amounting to £8,903,300 be approved;
(d) that the base 2017/18 general fund revenue budget amounting to £8,616,700 be approved; and
(e) that the use of the surplus on the spending reserve as set out in paragraphs 49-51 be approved.
Reason: The Council has a co-ordinated strategic, service and financial planning process and this report brings together the spending plans for the Council's services for 2017/18 and will allow the Council to approve the capital programme, general fund revised revenue budget for 2016/17, fees and charges for 2017/18 and draft revenue budget for 2017/18.
Cost of proposals: As detailed in the briefing paper contained in the report.
Appendices: A: Capital Programme 2016/17 to 2020/21 B: Fees and Charges for 2017/18 C: Revenue Budget Summary for 2017/18 D: Revenue Budget 2017/18 Executive Briefing Paper Date: 09 January 2017 Subject: Finance Strategy, Capital Programme, Revenue Budget and Council Tax 2017/18 Briefing by: Director of Finance and Resources Portfolio: Policy and Resources
INTRODUCTION
1. This report brings together the revenue and capital spending plans for the Council's local service agreements, as part of the Council's co-ordinated strategic, service and financial planning process.
2. The finance strategy was considered in October 2016, in advance of the budget process. The Finance Strategy reviewed the Council’s overall financial position, taking into the following fundamental principles:
Resources Capital Expenditure Revenue Expenditure Transparency and Openness Partnership Working
3. It is against this background that the budget setting principles for the forthcoming financial year were agreed.
4. This report provides a further update to the Council’s overall financial position in the light of the updated capital programme and the approved service budgets and allows the ability to accommodate new revenue and capital spending plans to be considered.
GENERAL FUND CAPITAL PROGRAMME
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.