Fareham Borough Council
Executive, Monday 3 April 2017 at 6.00pm

Hill Head Coastal Protection Project: Phase 2 - Preferred Option and Award of Tender

Approved Executive 4 papers

Executive approved this item on Monday 3 April 2017. Below is the council's own wording, with the papers it was decided on.

Item8(1)

Resolved

RESOLVED that the Executive: (a) approves funding up to the sum of £649,834.60 including contingency, funded from Community Infrastructure Levy contributions, to deliver Phase 2 of the Hill Head Coastal Protection Project; (b) awards the contract for the Phase 2 works to the preferred supplier as set out in Appendix B (Confidential); and (c) approves that ground rent is not charged for the 39 beach hut owners during the construction period when they will be unable to access their beach huts (approximately 3 months).
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 03 April 2017 Portfolio: Planning and Development

Subject: Hill Head Coastal Protection Project: Phase 2 – Award of Tender

Report of: Director of Planning and Regulation

Strategy/Policy: River Hamble to Portchester Flood and Erosion Risk Management Strategy and North Solent Shoreline Management Plan

Corporate Protect and enhance the environment, Safe and Healthy place Objective: to live and work, leisure opportunities for health and fun.

Purpose: This report is to seek approval of Phase 2 of the Hill Head Coastal Protection Project, the construction of a replacement seawall to secure the long term future of the sea defences at Hill Head. Executive summary: The Council owned coastal defences at Hill Head include the beach, groynes and seawall. Beach levels have fallen in recent years exposing the seawall to additional and increased wave action, leading to failure of the seawall at Hill Head in winter 2015. The seawall has also failed on a number of previous occasions since 2005 and, through exposure as well as natural deterioration with age, has now reached the end of its serviceable life, is unmaintainable and has a high risk of future failure in storm conditions.

The Hill Head Coastal Protection Project proposes to address the frontage issues through delivery of two phases:

Phase 1 improvements (beach recharge and groyne repairs) were approved at the July 2016 meeting of the Executive, and were completed in September 2016. This initial phase of works formed part of the long term solution for the frontage and allowed time for design work for the Phase 2 replacement sea defences to be carried out.

Phase 2 of the works, the subject of this report, is the construction of a replacement seawall to secure the long term future of the sea defences at Hill Head. Tenders have been received and assessed based on quality and price to identify the most advantageous offer for the Council. The details set out in this report have been developed in collaboration with the Hill Head Ward Members Working Group, chaired by the Executive Member for Planning and Development.

Recommendation: That the Executive:

(a) approves funding up to the sum of £649,834.60 including contingency, funded from Community Infrastructure Levy contributions, to deliver Phase 2 of the Hill Head Coastal Protection Project; and

(b) awards the contract for the Phase 2 works to the preferred supplier as set out in Appendix B (Confidential).

Reason: With the seawall and associated promenade at the end of its serviceable life, the asset is at immediate risk of failure during stormy conditions which would render the 39 beach huts unsafe for use. If allowed to deteriorate, the toe of the cliff would become open to erosion, posing a longer term risk to Cliff Road (estimated in year 20) as well as the 10 residential properties to the landward side of the road.

The construction of a replacement seawall will secure the long term future of the sea defences and public promenade at Hill Head.

Cost of proposals: The total cost of the proposals are indicated in confidential Appendix B and will be funded from Community Infrastructure Levy contributions.

Appendix A: Location Plan & Cross Section Appendix B: Confidential – Tender Prices and Evaluation Appendix C: Exhibition Event feedback Appendix D: Project Timeline Executive Briefing Paper Date: 03 April 2017

Subject: Hill Head Coastal Protection Project: Phase 2 – Award of Tender

Briefing by: Director of Planning and Regulation

Portfolio: Planning and Development

INTRODUCTION

1. Fareham Borough Council’s (FBC) coastal team, the Eastern Solent Coastal Partnership (ESCP), propose to replace the FBC owned coastal defences at Hill Head. The Phase 1 improvements were approved by the July 2016 Executive, and were completed in September 2016. This initial phase of works formed part of the long term solution for the frontage and allowed time for design work for the Phase 2 replacement sea defences to be carried out.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(1)Appendix A 383 KB Download
PDF
(1)Appendix C 281 KB Download
PDF
(1)Appendix D 202 KB Download
PDF
Hill Head Coastal Protection Project: Phase 2: Preferred Option and Award of TenderReport 178 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
SW
Councillor Seán WoodwardCommittee Member, present
TC
Councillor Trevor Cartwright, MBECommittee Member, present
SB
Councillor Susan BellCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
TH
Councillor Tiffany HarperCommittee Member, present
KM
Councillor Kay MandryCommittee Member, present
LU
Leigh UsherCommittee Officer, expected
SW
Samantha WightmanCommittee Officer, expected
RI
Richard IvoryOfficer, expected
MF
Councillor Michael Ford, JPGuest, in attendance
LK
Councillor Leslie KeebleGuest, in attendance
AM
Councillor Arthur MandryGuest, in attendance

All 16 on the meeting page

On this subject at Fareham

Search all
  1. Hill Head Coastal Protection Project: Phase 2 - Preferred Option and Award of TenderThis decision
  2. P/24/1553/OA - Land West of Old Street, Hill HeadRefused
  3. P/25/0798/FP - Seafield Park Open Space, Illustrious Road, Hill HeadDecided
  4. Licensing Act 2003 - Application for a new premises licence - The Osborn View Hotel, 67 Hill Head Road, Fareham PO14 3JRApproved
  5. Fareham Housing Disposal of 29 Cottes Way, Hill Head - Variation to previous agreement for a tenure change at the propertyAgreed
  6. P/24/1544/fp - the osborne view, 67 hill head road, fareham, po14 3jpAgreed

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies