Resolved

RESOLVED that the Executive: (a) notes the progress with the IFA2 project, including the conclusion of the detailed land agreement documents; and (b) endorses the scope of work for the two technical studies, set out in the appendices A and B of the report.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 03 April 2017 Portfolio: Policy & Resources

Subject: National Grid IFA2 Project Update

Report of: Director of Finance and Resources

Strategy/Policy: Corporate Strategy

Corporate Objective: A Dynamic, prudent and progressive Council

Purpose: To note the progress in agreeing detailed terms for the National Grid IFA2 project, and to agree the scope of work for the forthcoming technical studies.

Executive summary: In December 2015, the Executive agreed terms for the lease of land at Daedalus to National Grid for the purposes of constructing the IFA2 Interconnector and delegated authority to the Director of Finance and Resources to agree the detailed terms. The Executive further agreed to reinvest the proceeds of the disposal of land to support the Vision for Daedalus.

Over the course of 2016, National Grid undertook a range of site investigations and detailed design work to enable them to progress a planning application and procure a construction partner for the project. The Planning Committee considered the hybrid application, and resolved to grant planning permission in January 2017. At the same time, work was undertaken to develop the detailed land agreements and, after extensive negotiations with National Grid representatives, these have now been concluded.

The next key stage is the commissioning of two technical studies to consider the compatibility of IFA2 with the Council's future plans for Daedalus, with one study considering the technical elements and the other considering business compatibility.

The Report includes the scope of work for each study, which the Executive are asked to endorse. Recommendation: That the Executive:

a) notes the progress with the IFA2 project, including the conclusion of the detailed land agreement documents; and

b) endorses the scope of work for the two technical studies, set out in the appendices A and B of the report.

Reason: To enable the technical studies relating to the IFA2 project to commence.

Cost of proposals: Consultancy costs related to the technical studies are met by National Grid, and the full financial implications are set out in appendix D.

Appendices: A: Technical Study - scope of work for future Airport operations B: Technical Study - scope of work for business compatibility C: CONFIDENTIAL Heads of Terms as agreed in December 2015) D: CONFIDENTIAL Summary of agreed terms E: CONFIDENTIAL Legal report of Land agreements

Background papers: File of correspondence

Reference papers: Executive report (December 2015) Technical studies submitted by National Grid in support of the IFA2 planning applications Executive Briefing Paper Date: 03 April 2017 Subject: National Grid IFA2 Project Update Briefing by: Director of Finance and Resources Portfolio: Policy and Resources

INTRODUCTION

1. At its meeting in December 2015, the Executive considered proposals for the lease of land at Daedalus to National Grid, for the purposes of constructing the IFA2 Interconnector.

2. Having considered the proposal, the Executive resolved to

a. approve the draft Heads of Terms, as set out in the confidential Appendix; (see Appendix C to this report);

b. delegate authority to the Director of Finance and Resources in consultation with the Executive Member for Policy and Resources to agree the detailed terms, as appropriate; and

c. agree to reinvest the proceeds of the disposal of land under this agreement into the delivery of actions that support the Vision for Daedalus, including the airport, the business park and the open space.

3. This report provides an update on progress with the land agreement, including the steps that were put in place to provide assurance that the Interconnector use was compatible with the wider uses and vision for Daedalus.

PROGRESS OF THE PROJECT

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(1)Appendix A 15 MB Download
PDF
(1)Appendix B 131 KB Download
PDF
National Grid IFA2 Project UpdateReport 121 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
SW
Councillor Seán WoodwardCommittee Member, present
TC
Councillor Trevor Cartwright, MBECommittee Member, present
SB
Councillor Susan BellCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
TH
Councillor Tiffany HarperCommittee Member, present
KM
Councillor Kay MandryCommittee Member, present
LU
Leigh UsherCommittee Officer, expected
SW
Samantha WightmanCommittee Officer, expected
RI
Richard IvoryOfficer, expected
MF
Councillor Michael Ford, JPGuest, in attendance
LK
Councillor Leslie KeebleGuest, in attendance
AM
Councillor Arthur MandryGuest, in attendance

All 16 on the meeting page

On this subject at Fareham

Search all
  1. National Grid IFA2 Project UpdateThis decision
  2. P/16/0557/ma/b - ifa2 national grid land at daedalus airfield lee-on-the-solent po13 9yaApproved
  3. P/16/0557/dp/k - national grid ifa2 ltd room 25/26 fareham innovation centre merlin house meteor way po13 9fuApproved
  4. Q/0087/18 - ifa2 national grid land at daedalus airfield lee-on-the-solent po13 9yaAgreed
  5. P/17/0835/rm - ifa2 national grid land at daedalus airfield lee-on-the-solent po13 9yaDecided
  6. P/17/0834/rm - ifa2 national grid land at daedalus airfield lee-on-the-solent po13 9yaApproved

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies