Audit and Governance Committee noted this item on Monday 25 September 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Committee note the contents of the report.
This report provides the assurances arising from the latest internal audit work and gives an update on progress being made with the delivery of the audit plans.
It is recommended that the Committee notes the progress and findings arising from Internal Audit work. INTRODUCTION
1. This report highlights the progress made to date on the delivery of the Internal Audit Plans and the assurances that can be obtained from the work now completed.
FINALISING PREVIOUS AUDIT PLANS
2. The current status of the 12 audits remaining from the previous Audit Plans is detailed in Appendix One. A further 2 have now been finalised and work has now commenced on the main outstanding audit on Contract Deeds Management.
DELIVERY OF 2017/18 AUDIT PLAN
3. Work is progressing on the delivery of the current years audit plan, as noted in Appendix Two. The first audit has now been finalised.
FINDINGS FROM COMPLETED AUDITS
4. The three latest final reports that have been issued are listed below with the opinions given and number of recommendations made:
Recommendations Made Assurance Audit New New Outstanding Opinion Previous Essential Essential Important or Important
Multiple Parking Permits and at Single Not - - - Person Discount Properties 2017/18 Applicable
Housing Rents 2016/17 Reasonable - 5 1
Effectiveness of Ethics related activities Reasonable - 1 - (physical security) 2016/17
5. Detail of the recommendations made and the actions to be taken is provided in Appendix Three.
RISK ASSESSMENT
6. There are no significant risk considerations in relation to this report
Appendix One - Update on Outstanding Audits from Previous Plans
Appendix Two - Audits in the 2017/18 Audit Plan
Appendix Three - Findings from the Latest Completed Audits
Appendix Four - Reference Tables
Background Papers: None Reference Papers: Report by the Director of Finance and Resources to the Audit and Governance Committee on 10 March 2014 on the Contractor Annual Audit Plan 2014/15 Report by the Director of Finance and Resources to the Audit and Governance Committee on 16 March 2015 on the Internal Audit Strategy and Annual Audit Plan 2015/16 Report by the Head of Finance and Audit to the Audit and Governance Committee on 14 March 2016 on the Internal Audit Plan 2016/17 Report by the Head of Finance and Audit to the Audit and Governance Committee on 17 March 2017 on the Internal Audit Plan 2017/18
Enquiries: For further information on this report please contact Elaine Hammell. (Ext 4344) APPENDIX ONE Update on Outstanding Audits from Previous Plans
The following table shows those audits that were outstanding in the last quarterly report and shows the current position with finalising the work.
Stage New Recommendations* Previous Recs. (E and I only) Days in Assurance Audit Title Type of Audit** Plan reached of Not 10* Opinion* Essential Important Advisory Implemented Cancelled Implemented
2014/15 Income Collection & Banking Fundamental 15 Stage 8 Information Governance Opinion Computer 6 Stage 8 Corporate, Specialist, Contract Completion Governance 10 Stage 8
2015/16 Corporate, Specialist, Recruitment and Selection Governance (V) 15 Stage 9
Land Charges Service and Systems – HR 12 Stage 8 Contract Deeds Management Thematic Review 15 Stage 4 2016/17 Housing Rents Fundamental System 15 Stage 10 Reasonable - 5 3 2 - 1 Service and Systems – Daedalus Project High Risk 12 Stage 8
Cloud Based Computing Computer 15 Stage 8 Leaseholder Charges Joint working project Stage 5 Follow Up / Joint working Building Health and Safety Risks project Stage 5
Effectiveness of Ethics related Thematic Review Stage 10 Reasonable - 1 2 - - - activities (physical security)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Quarterly Audit ReportReport | 339 KB | DownloadRead as text |
Follow Audit and Governance Committee at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Business ContinuityRESOLVED that the Audit and Governance Committee note the contents of the report. | Noted | Open |
| 8 Sep 2026 | Corporate Complaint Handling - Performance and Learnings 2025/26RESOLVED that the Audit and Governance Committee: - (a) note the content of the Fareham Housing specific 2025/26 Comp... | Noted | Open |
| 8 Sep 2026 | Chief Internal Auditor's Quarterly ReportRESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. | Decided | Open |
| 8 Sep 2026 | Committee ReportRESOLVED that the Audit and Governance Committee: - a) notes the contents of Part One of the report, including the Co... | Approved | Open |
| 27 Jul 2026 | External Audit - Annual Plan and Fee 2026/27RESOLVED that the Audit and Governance Committee: a) approves the 2025/26 Audit Plan, attached as Appendix A to this ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.