P/17/0681/OA - LAND EAST OF POSBROOK LANE TITCHFIELD FAREHAM PO14 4EZ

Refused Planning 1 paper

Planning Committee refused this item on Wednesday 13 December 2017. Below is the council's own wording, with the papers it was decided on.

Item7(1)

Resolved

RESOLVED that PLANNING PERMISSION be REFUSED. Reasons for Refusal: The development would be contrary to Policies CS2, CS4, CS5, CS6, CS14, CS16, CS17, CS18, CS20, CS21 and CS22 of the Adopted Fareham Borough Core Strategy 2011 and Policies DSP5, DSP6, DSP13, DS14, DSP15 and DSP40 of the adopted Local Plan Part 2: Development Sited and Policies Plan; And, Paragraphs 109, 129, 131, 132 and 134 of the National Planning Policy Framework; and is unacceptable in that: (a) the application site lies outside of the defined urban settlement boundary on land which is considered to form part of a ‘valued landscape’. As a result the proposed development would result in a range of significant adverse landscape and visual effects, harmful to the landscape character, appearance and function of the countryside and failing to respect or respond positively to the key characteristics of the surrounding area. In addition the proposed development would adversely affect the integrity of the strategic gap and the physical and visual separation of settlements; (b) the proposal would be harmful to, and fail to preserve and enhance, the setting of nearby Grade ll * Listed Buildings; (c) the proposal would result in the loss of best and most versatile agricultural land; (d) had it not been for the overriding reasons for refusal the Council would have sought details of the SuDS strategy including the mechanism for securing its long-term maintenance; (e) had it not been for the overriding reasons for refusal the Council would have sought the on-site provision of affordable housing at a level in accordance with the requirements of the local plan; (f) had it not been for the overriding reasons for refusal the Council would have sought ecological mitigation, compensation and enhancement measures to ensure that all protected species are taken into account during and after construction. These would include alternative provision for habitats, including networks and connectivity and future management and maintenance arrangements; (g) in the absence of a legal agreement to secure such, the proposal would fail to provide satisfactory mitigation of the ‘in combination’ effects that the proposed increase in residential units on the site would cause through increased recreational disturbance on the Solent Coastal Special Protection Areas; (h) in the absence of a legal agreement to secure such, the proposal fails to provide satisfactory details of the design long term management and ownership and associated costs of the proposed Bird Conservation Area to the east of the application site. As a result the proposal fails to provide adequate mitigation, compensation and enhancement measures in relation to the effects of the development on qualifying features of the Solent and Southampton Water Special Protection Area (SPA); (i) in the absence of a legal agreement securing provision of open space and facilities and their associated management and maintenance, the recreational needs of residents of the proposed development would not be met; (j) in the absence of a legal agreement to secure such, the proposal fails to mitigate against the adverse effects of the development on the safety and operation of the strategic and local highway network in the form of a financial contribution towards off-site highway improvements; (k) in the absence of a legal agreement to secure the submission and implementation of a full Travel Plan, payment of the Travel Plan approval and monitoring fees and provision of a surety mechanism to ensure implementation of the Travel Plan, the proposed development would not make the necessary provision to ensure measures are in place to assist in reducing the dependency on the use of the private motorcar; and (l) in the absence of a legal agreement to secure a financial contribution towards improvements to the local public rights of way network , the proposal fails to mitigate the harm from the increased usage of public rights of way as a direct result of the development. Note for information: Had it not been for the overriding reasons for refusal to the proposal, the Local Planning Authority would have sought to address point d) above through the imposition of a suitably worded planning condition and points e) – l) above by inviting the applicant to enter into a legal agreement with Fareham Borough Council under Section 106 of the Town & Country Planning Act 1990.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Planning Committee

P/17/0681/OA TITCHFIELD FOREMAN HOMES LTD. AGENT: FOREMAN HOMES LTD. OUTLINE PLANNING APPLICATION FOR SCOUT HUT, UP TO 150 DWELLINGS, COMMUNITY GARDEN, ASSOCIATED LANDSCAPING, AMENITY AREAS AND A MEANS OF ACCESS FROM POSBROOK LANE LAND EAST OF POSBROOK LANE TITCHFIELD FAREHAM HAMPSHIRE PO14 4EZ

Report By Richard Wright - direct dial 01329 824758 Introduction The Council's position on 5-year housing land supply was challenged by way of planning appeal at a site in Cranleigh Road Portchester (Ref: APP/A1720/W/16/3156344) in April this year with the appeal decision issued in August.

In deciding that planning appeal the Inspector concluded that the Council's housing requirements should be based upon Objectively Assessed Housing Need, not the housing requirements set out in Local Plan Parts 1 and 2. On this basis the Inspector concluded that the Council's housing land supply position was little more than 2 years.

Finding that Fareham Borough Council does not have a 5YHLS represents a significant material change in planning circumstances. The most significant implication of the Council's current position on 5YHLS is that the approach that the Council must take in determining applications for residential development will have to be altered until the Council can robustly demonstrate that it has a 5YHLS. The approach which will need to be undertaken was set out in detail in the report titled 'How proposals for residential development should be considered in the context of this Council's 5 year housing land supply position' presented to the Planning Committee on the 15th November 2017.

This report sets out all the relevant planning policies and considerations and applies the planning balance (often referred to as the 'tilted balance') as required by National Planning Policy Framework and established planning case law.

A separate report is included on this Agenda setting out this Council's current 5-year housing land supply position.

Site Description The application site comprises a field located to the south of the Bellfield housing estate and public open space on the south side of Titchfield. The site measures approximately 6.6 hectares in area.

The policies maps of the adopted local plan identifies the land as being outside of the defined urban settlement boundaries. The site is therefore considered for planning purposes to lie within the countryside. It is designated as a strategic gap (The Meon Gap) within the local plan. Furthermore, as defined in the local plan, the site is an "Uncertain" Brent Geese and Wader Site.

The field is currently used for the grazing of horses. Two pedestrian public rights of way (Footpaths 34 & 39) cross the site.

The western edge of the site runs alongside Posbrook Lane where there is a mature hedgerow with a field gate set within it. Two dwellings set in large plots and agricultural land lie on the opposite side of the lane. Approximately 300m to the north is the junction of Posbrook Lane with Coach Hill/Common Lane from where Titchfield village centre lies to the east, Warsash to the west and access on to the A27 via St Margaret's Lane to the north. In the opposite direction to the south of the site Posbrook Lane leads to the coast and Hill Head.

At the south-western edge of the site is a row of substantial and mature trees along the boundary with a cluster of dwellings at Posbrooke House, Great Posbrooke and Barn Close. The houses of Great Posbrooke and the barn are Grade II* Listed Buildings. Some other houses in Barn Close are locally listed (on the Council's Local List of Buildings of Special Architectural or Historic Interest).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P/17/0681/OA: LAND EAST OF POSBROOK LANE TITCHFIELD FAREHAM PO14 4EZReport 1.7 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 25 attended
NW
Councillor Nick WalkerChairman, present
AM
Councillor Arthur MandryVice-Chairman, present
BB
Councillor Brian BayfordCommittee Member, present
TC
Councillor Trevor Cartwright, MBECommittee Member, present
PD
Councillor Peter DaviesCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
MF
Councillor Michael Ford, JPCommittee Member, present
KM
Councillor Kay MandryCommittee Member, present
RP
Councillor Roger Price, JPCommittee Member, present
SC
Councillor Shaun CunninghamGuest, in attendance
CH
Councillor Connie HockleyGuest, in attendance
CH
Councillor Carolyn HeneghanGuest, in attendance

All 25 on the meeting page

On this subject at Fareham

Search all
  1. P/17/0681/OA - LAND EAST OF POSBROOK LANE TITCHFIELD FAREHAM PO14 4EZThis decision
  2. Q/1287/25 - Land East of Posbrook Lane Titchfield FarehamDecided
  3. Q/1287/25 - Land East of Posbrook Lane Titchfield FarehamDecided
  4. P/25/0783/VC - Horse Field Land North Of Brune Lane And East Of Broom Way Lee-On-The-Solent Fareham PO13 9PBDecided
  5. Q/0142/25 - Land East of Southampton Road, TitchfieldAgreed
  6. P/23/1549/oa - land east of north wallington roadAgreed

More from Fareham Planning Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 12 August 2026 be confirmed and signed as a c... Decided Open
9 Sep 2026 Q/0559/26 - Land Between 75 & 77 Church Road Warsash Southampton SO31 9GDRESOLVED that Members delegate authority to the Head of Planning, in consultation with the Solicitor to the Council, ... Agreed Open
9 Sep 2026 P/26/0722/FP - Single Storey Side Extension at 44 Crispin Close Locks Heath SO31 6TDRESOLVED that: - (i) IT BE CONFIRMED that had the planning application for a side extension at 44 Crispin Close (as p... Decided Open
9 Sep 2026 P/26/0791/AD - Barchester Care Home Stubbington Lane Stubbington PO14 2NFRESOLVED that: - (i) Advertisement Consent for Five Years be GRANTED , subject to:- (a) the Conditions in the report;... Decided Open
12 Aug 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 15 July 2026 be confirmed and signed as a cor... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies