Resolved
RESOLVED that the Committee notes the contents of the report and the findings arising from the Internal Audit work.
Audit and Governance Committee decided this item on Monday 23 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Committee notes the contents of the report and the findings arising from the Internal Audit work.
This report provides the assurances arising from the latest internal audit work and gives an update on progress being made with the delivery of the audit plans.
It is recommended that the Committee notes the progress and findings arising from Internal Audit work. INTRODUCTION
1. This report highlights the progress made to date on the delivery of the Internal Audit Plans and the assurances that can be obtained from the work now completed.
FINALISING PREVIOUS AUDIT PLANS
2. The current status of the 9 audits remaining from the previous Audit Plans is detailed in Appendix One. Two reports have now been finalised and 2 more reports have moved to the draft report stage.
DELIVERY OF 2017/18 AUDIT PLAN
3. Work is progressing on the delivery of the revised audit plan, as noted in Appendix Two, such that a further 10 audits have now been finalised.
PROGRESS OF 2018/19 AUDIT PLAN
4. Work has started to deliver the 2018/19, as noted in Appendix Three, such that 1 audit has now reached the fieldwork stage.
FINDINGS FROM COMPLETED AUDITS
5. The twelve latest final reports that have been issued are listed below with the opinions given and number of recommendations made:
Recommendations Made Assurance Outstanding Audit New New Previous Opinion Essential Important Essential or Important
Housing Benefits 2017/18 Strong - - -
Employer’s Pension Responsibilities 2017/18 Strong - 1 -
Accounts Receivable 2017/18 Strong - 1 1
Income Management 2017/18 Reasonable - 2 2
Income Collection and Banking 2014/15 Reasonable - 3 1
Outdoor Recreation Follow Up 2017/18 Reasonable - 3 3
Leisure Centre Contracts 2017/18 Reasonable 1 1 -
Contract Procedure Rules N/A - - -
Contract Deeds Management 2015/16 N/A 1 4 -
Employee Performance Management N/A - 5 - 2017/18
Effectiveness of Ethics Related Activities – N/A - 9 - Follow Up surveys 2017/18 Recommendations Made Assurance Outstanding Audit New New Previous Opinion Essential Important Essential or Important
Data Protection in Services 2017/18 N/A 3 3 -
6. Detail of the recommendations made and the actions to be taken is provided in Appendix Four. The findings from the work on Contract Procedure Rules is the subject of a separate report on the agenda.
RISK ASSESSMENT
7. A few areas where controls could be strengthened in relation to compliance with the General Data Protection Regulation have been identified. This is the subject of a corporate project being overseen by senior managers.
Appendix One - Update on Outstanding Audits from Previous Plans Appendix Two - Audits in the 2017/18 Audit Plan Appendix Three - Audits in the 2018/19 Audit Plan Appendix Four - Findings from the Latest Completed Audits Appendix Five - Reference Tables
Background Papers: None Reference Papers: Report by the Director of Finance and Resources to the Audit and Governance Committee on 10 March 2014 on the Contractor Annual Audit Plan 2014/15 Report by the Director of Finance and Resources to the Audit and Governance Committee on 16 March 2015 on the Internal Audit Strategy and Annual Audit Plan 2015/16 Report by the Head of Finance and Audit to the Audit and Governance Committee on 14 March 2016 on the Internal Audit Plan 2016/17 Report by the Head of Finance and Audit to the Audit and Governance Committee on 17 March 2017 on the Internal Audit Plan 2017/18 Report by the Head of Finance and Audit to the Audit and Governance Committee on 18 March 2018 on the Internal Audit Plan 2018/19
Enquiries: For further information on this report please contact Elaine Hammell. (Ext.4344) APPENDIX ONE Update on Outstanding Audits from Previous Plans
The following table shows those audits that were outstanding in the last quarterly report and shows the current position with finalising the work.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress ReportReport | 627 KB | DownloadRead as text |
Follow Audit and Governance Committee at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Business ContinuityRESOLVED that the Audit and Governance Committee note the contents of the report. | Noted | Open |
| 8 Sep 2026 | Corporate Complaint Handling - Performance and Learnings 2025/26RESOLVED that the Audit and Governance Committee: - (a) note the content of the Fareham Housing specific 2025/26 Comp... | Noted | Open |
| 8 Sep 2026 | Chief Internal Auditor's Quarterly ReportRESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. | Decided | Open |
| 8 Sep 2026 | Committee ReportRESOLVED that the Audit and Governance Committee: - a) notes the contents of Part One of the report, including the Co... | Approved | Open |
| 27 Jul 2026 | External Audit - Annual Plan and Fee 2026/27RESOLVED that the Audit and Governance Committee: a) approves the 2025/26 Audit Plan, attached as Appendix A to this ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.