Resolved
RESOLVED that the Committee note the content of the report.
Planning Committee noted this item on Wednesday 12 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Committee note the content of the report.
At their meeting on the 15th November 2017, the Planning Committee received a report providing an overview of the Cranleigh Road, Portchester planning appeal decision. The report set out the implications of the planning appeal decision for the Council’s 5 Year Housing Land Supply (5YHLS) position and advised Members on the approach they should adopt in the determination of planning applications for residential development.
A judgment by the Court of Justice of the European Union in April 2018 followed by the publication of the revised National Planning Policy Framework on 24 th July, have implications for how planning applications for residential development should now be determined.
The following report sets out the implications of the Court of Justice of the European Union judgment and the revised National Planning Policy Framework, for those making decisions on planning applications for residential development.
That the Committee note the content of the report. INTRODUCTION
1. On 14th August 2017 planning permission was granted on appeal for the erection of 120 dwellings on land North of Cranleigh Road in Portchester (Appeal Ref: APP/A1720/W/16/3156344). One of the Council’s grounds for refusing planning permission was that it was unnecessary development in the countryside given the Council’s five year housing land supply (5YHLS).
2. The Inspector concluded, contrary to the Council’s case that the Council could not demonstrate a 5YHLS, and that permission should be granted. The Inspector’s conclusion was that the Council could demonstrate just over two years housing supply in August 2017, considerably below a 5YHLS.
Implications for this Council’s decision making on residential proposals prior to 24th July 2018
3. In the report to the Planning Committee on the 15th November 2017, Members were advised of the following:
As Members will be aware, the starting point for the determination of planning applications is section 38(6) of the Planning and Compulsory Purchase Act 2004:
"If regard is to be had to the development plan for the purpose of any determination to be made under the Planning Acts the determination must be made in accordance with the plan unless material considerations indicate otherwise".
In determining planning applications therefore, there is a presumption in favour of the policies of the extant Development Plan, unless material considerations indicate otherwise. Material considerations include the planning policies set out in the NPPF, and this contains specific guidance in paragraphs 47, 49 and 14 for Councils unable to demonstrate a 5YHLS.
Paragraph 47 of the NPPF seeks to boost significantly the supply of housing, and provides the requirement for Councils to meet their OAHN, and to identify and annually review a 5YHLS including an appropriate buffer. Where a Local Planning Authority cannot do so, paragraph 49 of the NPPF clearly states that:
“Housing applications should be considered in the context of the presumption in favour of sustainable development. Relevant policies for the supply of housing should not be considered up-to-date if the local planning authority cannot demonstrate a 5-year supply of deliverable housing sites.” (emphasis added)
Paragraph 14 of the NPPF then clarifies what is meant by the presumption in favour of sustainable development for decision-taking, including where relevant policies are “out-of- date”. For decision-taking (unless material considerations indicate otherwise) this means:
Approving development proposals that accord with the development plan without delay; and
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
How Proposals for Residential Development should be considered in the context of this Council's current 5 Year Housing Land Supply PositionReport | 324 KB | DownloadRead as text |
Follow Planning Committee at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 12 August 2026 be confirmed and signed as a c... | Decided | Open |
| 9 Sep 2026 | Q/0559/26 - Land Between 75 & 77 Church Road Warsash Southampton SO31 9GDRESOLVED that Members delegate authority to the Head of Planning, in consultation with the Solicitor to the Council, ... | Agreed | Open |
| 9 Sep 2026 | P/26/0722/FP - Single Storey Side Extension at 44 Crispin Close Locks Heath SO31 6TDRESOLVED that: - (i) IT BE CONFIRMED that had the planning application for a side extension at 44 Crispin Close (as p... | Decided | Open |
| 9 Sep 2026 | P/26/0791/AD - Barchester Care Home Stubbington Lane Stubbington PO14 2NFRESOLVED that: - (i) Advertisement Consent for Five Years be GRANTED , subject to:- (a) the Conditions in the report;... | Decided | Open |
| 12 Aug 2026 | Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 15 July 2026 be confirmed and signed as a cor... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.