RESOLVED that, subject to: a) The applicant providing a completed unilateral undertaking to the satisfaction of the solicitor to the Council pursuant to Section 016 of the Town and Country Planning Act 1990 to secure the proposed nitrogen mitigation solution; b) Members delegating to Officers the making of an Appropriate Assessment under the habitat regulations and that assessment concluding the development would not adversely affect the integrity of the designated sites; c) Officers consulting Natural England as the appropriate nature conservation body in relation to that Appropriate Assessment; d) Members delegating to Officers to impose any additional planning conditions including those necessary for mitigation purposes following the making of an Appropriate Assessment; e) No objection being raised by the lead flood authority Hampshire County Council in response to the additional information provided by the applicant in relation to surface water drainage; f) The additional condition in the Update Report; and g) A further condition stating that the parking spaces shown on the approved plans shall be retained and kept available for parking at all times; and remove permitted development rights so that no carports or garages can be erected over the approved parking spaces unless planning permission has first been obtained for them. Reserved Matter application be APPROVED.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
P/19/0864/RM FAREHAM NORTH RESIDE DEVELOPMENTS LIMITED AGENT: TURLEY AND ATHERFOLD INVESTMENTS LTD
TWENTY-SEVEN DWELLINGS, INTERNAL ROADS AND PARKING (LAYOUT ONLY)
LAND NORTH OF FUNTLEY ROAD, FUNTLEY
Report By Richard Wright – direct dial 01329 824758.
1.0Introduction 1.1 This application has been reported to the Planning Committee for a decision to be made due to the number of third party comments received in response to its publication.
1.2Outline planning permission was granted in November 2018 for up to twenty- seven dwellings on this site along with associated infrastructure, means of access and demolition of existing agricultural building. A Section 106 agreement secured, amongst other things, the provision of a permissive footpath from Funtley Road to Thames Drive and associated works to upgrade the existing bridge over the M27 motorway.
1.3Since the grant of outline consent the applicant has been working to discharge and meet the requirements of the Section 106 agreement. The applicant has developed a scheme of works to be carried out to the M27 bridge and has agreement from the highway authority Highways England to carry out those works immediately at the start of the new year. Highways England have agreed a two week window to carry out the works starting on the 7th January 2020. As a result of these works being carried out in the very near future the applicant has requested that this application be considered by the Planning Committee at this meeting. This is to provide enough certainty that an acceptable layout of 27 dwellings on the site can be achieved in order that the works and the investment required in those bridge works may proceed.
2.0Site Description 2.1 The site measures 0.96 hectares (2.4 acres) in area and is situated immediately to the north of Funtley Road. 2.2 To the north and east the site adjoins housing development on the site of the former Funtley Abattoir. To the north west of the site is a designated area of public open space. To the west of the site are a small number of frontage dwellings with long rear gardens.
2.3The site is relatively flat, falling gently to the north. It currently comprises horse paddocks.
2.4There is an existing access to the site in the south eastern corner and an unmade track runs diagonally across the site to an agricultural storage building/stables located in the north west corner.
2.5The existing southern boundary to Funtley Road is marked by a hedgerow containing some trees towards its eastern end. The western boundary is largely defined by an evergreen hedgerow, with the eastern and northern boundaries formed with varying types and sizes of planting.
2.6The site lies outside of the urban settlement boundary.
3.0Description of Proposal 3.1 This reserved matters application seeks approval of the layout of the site following the grant of outline permission for up to twenty-seven dwellings which was granted in November 2018. The means of access to the site was a matter agreed at the outline stage.
3.2The layout proposed comprises a mixture of detached, semi-detached and terraced 2, 3 & 4-bed houses all with private rear gardens and allocated parking spaces.
3.3Aside from this application which deals with the layout of the development only, a separate planning application for the remaining reserved matters of scale, appearance and landscaping has also been submitted (ref P/19/1185/RM).
4.0Policies 4.1 The following policies apply to this application:
Adopted Fareham Borough Core Strategy CS2 – Housing Provision CS4 – Green Infrastructure, Biodiversity and Geological Conservation CS5 – Transport Strategy and Infrastructure CS6 – The Development Strategy CS14 – Development Outside Settlements CS15 – Sustainable Development and Climate Change CS16 – Natural Resources and Renewable Energy CS17 – High Quality Design CS18 – Provision of Affordable Housing CS20 – Infrastructure and Development Contributions
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.