RESOLVED that the Executive: (a) approves the capital budget as outlined in the confidential Appendix A to the report to provide additional power infrastructure to Faraday Business Park; and (b) delegates authority to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources, to award the contract(s) for the installation of the power upgrade after a procurement exercise in accordance with the Council’s Procurement and Contract Procedure Rules 2019.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Confidential Appendix A: Provision of upgraded power supplies at Faraday Business Park, Daedalus – Estimated Costs
Background papers: None
Reference papers: None Executive Briefing Paper Date: 02 March 2020 Subject: Provision of upgraded power supplies at Faraday Business Park, Daedalus Briefing by: Director of Planning and Regeneration Portfolio: Policy and Resources
Background
1. On the 7th January 2019 the Executive approved funding of £5.0 million for the construction of new industrial/business units at Faraday Business Park at Daedalus, and delegated authority for the appointment of a contractor to the Director of Finance and Resources, following consultation with the Executive Member for Policy and Resources. The paper highlighted that additional electricity infrastructure may be required for Faraday Business Park.
2. Further design work has confirmed that the existing power supplies are insufficient to serve the needs of the on-going developments. The Council’s design team has investigated potential solutions to provide additional electricity infrastructure.
3. Initial investigations showed that any reinforcement of the power supplies would need to be provided from sub-stations remote from the Daedalus site with significant cost and time implications.
4. Further work has identified power supplies that have previously been installed for areas within the wider Daedalus site that remain unutilised. Working with the utility supplier, the Council’s team has developed an alternative, more economic and timely solution to provide the required further electricity infrastructure to Faraday Business Park.
5. This proposal allows for the standard provision of power to the Council’s approved industrial/business unit development on Faraday Business Park and additional provision for any high user occupiers and purchasers.
6. This proposal has been presented to and is supported by the Daedalus Members’ Working Group.
DESIGN / COST
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.