Resolved
RESOLVED that the Executive approves a capital budget to refurbish the air conditioning system and undertake minor building upgrade works at Faretec at the Cams Estate Business Park, as set out in the confidential Appendix A to the report.
Executive approved this item on Monday 2 March 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Executive approves a capital budget to refurbish the air conditioning system and undertake minor building upgrade works at Faretec at the Cams Estate Business Park, as set out in the confidential Appendix A to the report.
Confidential Appendix A: Faretec - Estimated costs and revenue income Executive Briefing Paper Date: 02 March 2020 Subject: Capital Expenditure at Faretec, Cams Estate Business Park Briefing by: Director of Planning and Regeneration Portfolio: Policy and Resources
INTRODUCTION
1. Faretec is a two storey multi-let office building located on the Cams Estate Business Park split into eight office suites. It was acquired in 2001 and was bought as part of the Economic Initiatives Fund. The intention was to provide a high-quality IT hub within the Borough. Since the acquisition, the market and demand for offices of this nature has changed and there is now significant provision for IT and technology occupiers at the Fareham Innovation Centre at Solent Airport.
2. Faretec is now considered to be a basic specification office, which no longer attracts the IT occupiers originally envisaged. Consequently, achieving lettings when suites become vacant is proving to be increasingly difficult. This is, in part, reflective of the wider office market but also the nature of the accommodation.
3. Suites 1, 2 and 3 have been vacant since July 2019 but are currently subject to negotiations for a new ten-year lease. Terms have been agreed with the two tenants of the other suites to renew on new six-year leases. Historically, leases have been based on a single payment which is inclusive of business rates, service charge, insurance and utilities. This has, in effect, been subsidising the tenants’ rent and was put in place to reflect the original use of the property.
PROPOSAL
4. The opportunity is now being taken to put new terms in place for tenants to pay the rent, business rates, service charge, insurance and utilities separately, which is in line with market terms and the same approach taken to other properties which sit within the Council’s investment portfolio.
5. However, the air-conditioning system, which provides heating and cooling, has not been replaced since the Council acquired the building. Consequently, it is becoming beyond repair, with issues around the system’s performance and reliability. This has been a major concern for existing and prospective tenants when negotiating new leases. In addition, there are some minor building upgrade works required to facilitate the new lettings, including the provision of electricity sub-meters and the replacement of parts of the alarm system. FINANCIAL IMPLICATIONS
6. A confidential Appendix A to the Executive report sets out the estimated cost of the air- conditioning refurbishment and building upgrade works at Faretec. The Appendix also outlines the positive impact that the completion of new leases will have on the Council’s rental income.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Expenditure at Faretec, Cams Estate Business ParkReport | 92 KB | DownloadRead as text |
Follow Executive at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... | Agreed | Open |
| 7 Sep 2026 | References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... | Agreed | Open |
| 7 Sep 2026 | Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... | Approved | Open |
| 7 Sep 2026 | Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... | Approved | Open |
| 7 Sep 2026 | Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.