Internal Audit Progress Report

Noted Finance 1 paper

Audit and Governance Committee noted this item on Monday 19 October 2020. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

RESOLVED that the Audit and Governance Committee: - (a) noted the progress and findings arising from the Internal Audit work; and (b) approved the close down of the oldest audits of Contract Completion and Leasehold Charges with the issues to be picked up in other areas of work.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Audit and Governance Committee

Summary

This report provides the assurances arising from the latest internal audit work and gives an update on the progress being made with delivering the audit plans.

The Audit and Governance Committee's areas of responsibility for Internal Audit include: - d) to approve significant interim changes to the internal audit plan and resource requirements;

e) to make appropriate enquiries of both management and the head of internal audit to determine if there are any inappropriate scope or resource limitations;

g) to consider reports from the head of internal audit on internal audit’s performance, including RECOMMENDATION the performance of external providers of internal audit services. These will include:  updates on the work of internal audit including key findings, issues of concern and action in hand as a result of internal audit work. i) to receive reports outlining the action taken where the head of internal audit has concluded that management has accepted a level of risk that may be inacceptable to the authority or there are concerns about progress with the implementation of agreed actions.

Recommendation

It is RECOMMENDED that the Audit and Governance Committee: -

(a) notes the progress and findings arising from Internal Audit work; and

(b) approves the close down of the older audits of Contract Completion and Leaseholder Charges with the issues to be picked up in other areas of work. INTRODUCTION

1. This report highlights the progress made to date on the delivery of the Internal Audit Plans and the assurances that can be obtained from the work now completed.

2. It should be noted that since February 2020 which is traditionally the busiest period of the audit year, the Covid-19 pandemic has impacted on the resources available to the service due to: a) reduced productivity from the audit team arising from changes in working arrangements during lock down; b) time lost due to the need to allow auditees to prioritise their pandemic responses over audits and; c) the need to divert auditor resources to assist with the Council responses to the pandemic at both Fareham BC and Portsmouth CC.

The completion of the plans has therefore been impacted; although the team is now making strides to achieve the required coverage. The plans have also been reviewed to identify audits which can be postponed to future audit years.

DELIVERY OF THE 2019/20 AUDIT PLAN

3. Due to the work that was carried out supporting the roll out of the new Procurement and Contract Procedure Rules last year, it has not been possible to progress the next stage of the work which is to look at contract management. This work will therefore roll over to the next audit plan. A decision has also been taken to remove the Anti-Bribery Policy audit due to the loss of resources at the end of the year.

4. This leaves 22 audits in the 2019/20 plan as detailed in Appendix Two. 21/22 audits have been finalised in this internal audit plan. The remaining audit (Recording of Sickness through the HR system) to be completed has reached Stage 5, “A first draft of the report has been received by the Support Officer to be reviewed”.

PROGRESS OF 2020/21 AUDIT PLAN

5. Work has started to deliver the 2020/21, as noted in Appendix Three, such that 6 audits have been started including 4 which have reached Stage 4, “the Auditor has started to deliver the agreed scope of work”.

FINALISING PREVIOUS AUDIT PLANS

6. The 10 remaining audits from the previous Audit Plans are detailed in Appendix One. As requested by members, the plan of how to finalise these audits is provided in the table. Considerable work has been carried out to progress 2 audits (Housing Options and Risk Inspections) which should have reached the final stage by the next meeting.

7. It is also proposed that 2 audits (leaseholder charges and contract completion) are now closed down and picked up as parts of other reviews.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Progress ReportReport 878 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 10 attended
JB
Councillor Jonathan ButtsChairman, present
SM
Councillor Simon MartinVice-Chairman, present
SC
Councillor Shaun CunninghamCommittee Member, present
PD
Councillor Peter DaviesCommittee Member, present
TD
Councillor Tom DaviesCommittee Member, present
TE
Councillor Tina EllisCommittee Member, present
GK
Councillor Gerry KellyCommittee Member, present
EH
Elaine HammellOfficer, expected
AW
Andrew WannellOfficer, expected
AH
Astra HughesCommittee Officer, expected

On this subject at Fareham

Search all
  1. Internal Audit Progress ReportThis decision
  2. Chief Internal Auditor's Quarterly ReportDecided
  3. Chief Internal Auditor's Quarterly ReportDecided
  4. Chief Internal Auditors Annual Opinion 2025/26Noted
  5. Chief Internal Auditor's Quarterly ReportApproved
  6. Chief Internal Auditor's Quarterly ReportDecided

More from Fareham Audit and Governance Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Business ContinuityRESOLVED that the Audit and Governance Committee note the contents of the report. Noted Open
8 Sep 2026 Corporate Complaint Handling - Performance and Learnings 2025/26RESOLVED that the Audit and Governance Committee: - (a) note the content of the Fareham Housing specific 2025/26 Comp... Noted Open
8 Sep 2026 Chief Internal Auditor's Quarterly ReportRESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. Decided Open
8 Sep 2026 Committee ReportRESOLVED that the Audit and Governance Committee: - a) notes the contents of Part One of the report, including the Co... Approved Open
27 Jul 2026 External Audit - Annual Plan and Fee 2026/27RESOLVED that the Audit and Governance Committee: a) approves the 2025/26 Audit Plan, attached as Appendix A to this ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies