Resolved
RESOLVED that the Audit and Governance Committee noted the progress and findings arising from the Internal Audit work.
Audit and Governance Committee noted this item on Monday 23 November 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Audit and Governance Committee noted the progress and findings arising from the Internal Audit work.
This report provides the assurances arising from the latest internal audit work and gives an update on the progress being made with delivering the audit plans.
The Audit and Governance Committee's areas of responsibility for Internal Audit include: - a) to approve significant interim changes to the internal audit plan and resource requirements;
b) to make appropriate enquiries of both management and the head of internal audit to determine if there are any inappropriate scope or resource limitations;
c) to consider reports from the head of internal audit on internal audit’s performance, including the performance of external providers of internal audit services. These will include: updates on the work of internal audit including key findings, issues of concern and action in hand as a result of internal audit work. d) to receive reports outlining the action taken where the head of internal audit has concluded that management has accepted a level of risk that may be inacceptable to the authority or there are concerns about progress with the implementation of agreed actions.
It is RECOMMENDED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. INTRODUCTION
1. This report highlights the progress made to date on the delivery of the Internal Audit Plans and the assurances that can be obtained from the work now completed.
PROGRESS OF 2020/21 AUDIT PLAN
2. There has been one change to the 2020/21 plan in that we have now had confirmation that no certification work is required for the Disabled Facilities Grants this year so this audit can be removed from the plan. We are therefore planning to deliver one of the reserve audits instead.
3. Work has commenced on 18 of the 19 remaining audits in the current internal audit plan, as noted in Appendix Two, such that 7 of the audits are at Stage 4 (the auditor has started to deliver the agreed scope of work) and 5 are at Stage 5 (A first draft of the report has been received by the Support Officer to be reviewed).
FINALISING PREVIOUS AUDIT PLANS
4. The 9 remaining audits from the previous Audit Plans are detailed in Appendix One. Considerable work has been carried out to progress 2 audits (Risk Inspections and Recording of Sickness through HR 21) which should have reached the final stage by the date of the meeting.
FINDINGS FROM COMPLETED AUDITS
5. There are no additional final reports that have been issued since the last report.:
RISK ASSESSMENT
6. There are no significant risk considerations in relation to this report
Appendix One - Update on Outstanding Audits from Previous Plans
Appendix Two - Audits in the 2020/21 Plan
Appendix Three – Findings from the Latest Completed Audits (None)
Appendix Four - Reference Tables
Background Papers: None
Reference Papers: Report by the Director of Finance and Resources to the Audit and Governance Committee on 10 March 2014 on the Contractor Annual Audit Plan 2014/15 Report by the Head of Finance and Audit to the Audit and Governance Committee on 14 March 2016 on the Internal Audit Plan 2016/17 Report by the Head of Finance and Audit to the Audit and Governance Committee on 17 March 2017 on the Internal Audit Plan 2017/18 Report by the Head of Finance and Audit to the Audit and Governance Committee on 18 March 2018 on the Internal Audit Plan 2018/19 Report by the Head of Finance and Audit to the Audit and Governance Committee on 11 March 2019 on the Internal Audit Plan 2019/20 Report by the Head of Finance and Audit to the Audit and Governance Committee on 19 October 2020 on the Internal Audit Plan 2020/21
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress ReportReport | 339 KB | DownloadRead as text |
Follow Audit and Governance Committee at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Business ContinuityRESOLVED that the Audit and Governance Committee note the contents of the report. | Noted | Open |
| 8 Sep 2026 | Corporate Complaint Handling - Performance and Learnings 2025/26RESOLVED that the Audit and Governance Committee: - (a) note the content of the Fareham Housing specific 2025/26 Comp... | Noted | Open |
| 8 Sep 2026 | Chief Internal Auditor's Quarterly ReportRESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. | Decided | Open |
| 8 Sep 2026 | Committee ReportRESOLVED that the Audit and Governance Committee: - a) notes the contents of Part One of the report, including the Co... | Approved | Open |
| 27 Jul 2026 | External Audit - Annual Plan and Fee 2026/27RESOLVED that the Audit and Governance Committee: a) approves the 2025/26 Audit Plan, attached as Appendix A to this ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.