RESOLVED that the Executive agrees: (a) that entering into a contract for the works which facilitate the use of LAD2 funding be delegated to the Deputy Chief Executive Officer; and (b) the funding mechanisms to meet the Council’s contribution towards the costs of the works.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 11 October 2021 Portfolio: Housing Local Authority Delivery Phase 2 (LAD2) funding scheme Subject: for energy efficiency measures to Council homes Report of: The Deputy Chief Executive Officer
Corporate Priorities: Providing Housing Choices
Purpose: To provide an overview of the LAD2 funding opportunity which will improve the energy efficiency of many Council homes.
Executive summary: The second phase of the Local Authority Delivery scheme (LAD) was launched in spring 2021 and is now open for applications. This funding is aimed at improving the energy efficiency of homes for low-income households. This would typically consist of improvements to insulation or, in some instances, installation of solar panels. The scheme in Fareham is being co-ordinated by the SW Energy Hub and will be delivered by City Energy.
The Council would be required to fund up to £5,000 or 1/3 of the works, per property; LAD2 funding will typically cover the remaining 2/3 of the costs of the improvement measures. A total budget of £150,000 will be incorporated into the HRA capital programme over the next 2-3 financial years to ensure this funding opportunity can be utilised.
This report seeks approval to enter into an appropriate contract with City Energy for works to the Council’s social housing stock. Approval is also sought for the funding arrangements, incorporated into the HRA capital programme over the next 2-3 financial years.
Recommendation: It is recommended that the Executive agrees:
(a) that entering into a contract for the works which facilitate the use of LAD2 funding be delegated to the Deputy Chief Executive Officer; and
(b) the funding mechanisms to meet the Council’s contribution toward the costs of the works. Reason: To meet the commitments in the Housing Greener Policy and the Fareham Borough Council Climate Change Action Plan.
Cost of proposals: The Council is required to fund up to £5,000 or 1/3 of the works, per property. A total budget of £150,000 will be incorporated into the HRA capital programme over the next 2-3 financial years in line with the required spend profile to qualify for LAD2 funding.
Appendices: None
Background papers: The Fareham Housing Greener Policy
The Fareham Borough Council Climate Change Action Plan.
Reference papers: None Executive Briefing Paper Date: 11 October 2021 Subject: Local Authority Delivery Phase 2 (LAD2) funding scheme for energy efficiency measures to Council homes Briefing by: The Deputy Chief Executive Officer Portfolio: Housing
INTRODUCTION
1. Phase 2 of the Local Authority Delivery scheme (LAD) was launched in spring 2021 with funding of £300m being allocated to Local Energy Hubs. The Hubs would then appoint delivery organisations to undertake the works in partnership with Local Authorities. The aim of the scheme is to improve the energy efficiency of homes of low-income households.
2. On 16 December 2019 the Executive approved the Fareham Housing Greener Policy. On the 7 June the Executive approved the Fareham Borough Council Climate Change Action Plan. Both documents set out actions to invest in the energy efficiency of our social housing stock, with the aim of ensuring our tenants can afford warm homes and maximise grant funding opportunities. The LAD2 funding provides the perfect opportunity to deliver on these commitments.
THE LOCAL AUTHORITY DELIVERY PHASE 2 (LAD2) SCHEME
3. LAD2 is the second phase of the Government Local Authority Delivery scheme. The intention of LAD is to improve the household energy efficiency for those on low income. The scheme is open until the end of the year and is aimed at properties with poor energy efficiency. These have been stipulated as homes with an Energy Performance Certificate (EPC) of D or lower. A cap of £30,000 combined income per household has also been set to ensure the works target those who need help the most.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.