RESOLVED that the Executive agrees: (a) that the extension for the contract for the works which facilitate the use of LAD2 be delegated to the Deputy Chief Executive Officer; and (b) the funding mechanisms to meet the Council’s contribution toward the costs of the works.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 07 December 2021 Portfolio: Housing Local Authority Delivery Phase 2 (LAD2) Funding Subject: Scheme for energy efficiency measures to Council Homes – Update. Report of: Deputy Chief Executive Officer
Corporate Priorities: Proving housing choices
Purpose: To update the Executive on additional LAD2 funding now available to improve the energy efficiency of Council homes. This is further to the LAD2 funding approved at the October Executive.
The report seeks approval to expand the energy efficiency works originally planned and for the funding mechanisms to meet the Council’s contribution.
Executive summary: At its meeting of the 11 October 2021, the Executive discussed the LAD2 funding opportunity to improve Council owned homes. The funding and contract approach were also approved at this meeting.
Further discussions have taken place on funding availability and it has emerged that the Council could apply for more works than originally anticipated. At the current time it is not possible to determine the exact number of properties, however, work is already underway to understand this given the short timescales of this funding.
This report seeks approval to extend the contract with City Energy for energy efficiency works to the Council social housing stock. Approval is also sought for the funding arrangements. The Council would be required to fund up to £5,000 or 1/3 of the works, per property; LAD2 funding will typically cover the remaining 2/3 of the costs of the improvement measures.
A budget of £350,000 will be into the HRA capital programme over the next 2-3 financial years. This is in addition to the £150,000 agreed at the October Executive. Recommendation/Recommended Option: It is recommended that the Executive agrees:
(a) that the extension for the contract for the works which facilitate the use of LAD2 be delegated to the Deputy Chief Executive Officer; and
(b) the funding mechanisms to meet the Council’s contribution toward the costs of the works.
Reason: To meet the commitments in the Housing Greener Policy and the Fareham Borough Council Climate Change Action Plan.
Cost of proposals: The Council would be required to fund up to £5,000 or 1/3 of the works, per property; LAD2 funding will typically cover the remaining 2/3 of the costs of the improvement measures.
A budget of £350,000 will be into the HRA capital programme over the next 2-3 financial years. This is in addition to the £150,000 agreed at the October Executive.
Appendices: None.
Background papers: 11 October 2021 Executive Report - Local Authority Delivery Phase 2 (LAD2) funding scheme for energy efficiency measures to Council homes.
Reference papers: Executive Briefing Paper Date: 07 December 2021 Subject: Local Authority Delivery Phase 2 (LAD2) Funding Scheme for energy efficiency measures in Council homes Briefing by: Deputy Chief Executive Officer Portfolio: Housing
INTRODUCTION
1. At its meeting of the 11 October 2021, the Executive discussed the LAD2 funding opportunity to improve Council owned homes. The funding and contract mechanisms were also approved at this meeting.
2. Further conversations have been underway on availability of funding and it has emerged that the Council could apply for more works than originally anticipated. By extending the contract with City Energy, the company delivering these works, the Council can improve the energy efficiency in more of its social housing stock.
THE LOCAL AUTHORITY DELIVERY PHASE 2 (LAD2) SCHEME
3. LAD2 is the second phase of the Government Local Authority Delivery scheme. The intention of LAD is to improve the household energy efficiency for those on low income. The scheme is open until the end of the financial year and is aimed at properties with poor energy efficiency. These have been stipulated as homes with an Energy Performance Certificate (EPC) of D or lower. A cap of £30,000 combined income per household has also been set to ensure the works target those who need help the most.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.