Executive, Tuesday 7 December 2021 at 5.00pm

Local Authority Delivery Phase 2 (LAD2) Funding Scheme for energy efficiency measures to Council homes - Update

Agreed Executive 1 paper

Executive agreed this item on Tuesday 7 December 2021. Below is the council's own wording, with the papers it was decided on.

Item8(1)

Resolved

RESOLVED that the Executive agrees: (a) that the extension for the contract for the works which facilitate the use of LAD2 be delegated to the Deputy Chief Executive Officer; and (b) the funding mechanisms to meet the Council’s contribution toward the costs of the works.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 07 December 2021 Portfolio: Housing Local Authority Delivery Phase 2 (LAD2) Funding Subject: Scheme for energy efficiency measures to Council Homes – Update. Report of: Deputy Chief Executive Officer

Corporate Priorities: Proving housing choices

Purpose: To update the Executive on additional LAD2 funding now available to improve the energy efficiency of Council homes. This is further to the LAD2 funding approved at the October Executive.

The report seeks approval to expand the energy efficiency works originally planned and for the funding mechanisms to meet the Council’s contribution.

Executive summary: At its meeting of the 11 October 2021, the Executive discussed the LAD2 funding opportunity to improve Council owned homes. The funding and contract approach were also approved at this meeting.

Further discussions have taken place on funding availability and it has emerged that the Council could apply for more works than originally anticipated. At the current time it is not possible to determine the exact number of properties, however, work is already underway to understand this given the short timescales of this funding.

This report seeks approval to extend the contract with City Energy for energy efficiency works to the Council social housing stock. Approval is also sought for the funding arrangements. The Council would be required to fund up to £5,000 or 1/3 of the works, per property; LAD2 funding will typically cover the remaining 2/3 of the costs of the improvement measures.

A budget of £350,000 will be into the HRA capital programme over the next 2-3 financial years. This is in addition to the £150,000 agreed at the October Executive. Recommendation/Recommended Option: It is recommended that the Executive agrees:

(a) that the extension for the contract for the works which facilitate the use of LAD2 be delegated to the Deputy Chief Executive Officer; and

(b) the funding mechanisms to meet the Council’s contribution toward the costs of the works.

Reason: To meet the commitments in the Housing Greener Policy and the Fareham Borough Council Climate Change Action Plan.

Cost of proposals: The Council would be required to fund up to £5,000 or 1/3 of the works, per property; LAD2 funding will typically cover the remaining 2/3 of the costs of the improvement measures.

A budget of £350,000 will be into the HRA capital programme over the next 2-3 financial years. This is in addition to the £150,000 agreed at the October Executive.

Appendices: None.

Background papers: 11 October 2021 Executive Report - Local Authority Delivery Phase 2 (LAD2) funding scheme for energy efficiency measures to Council homes.

Reference papers: Executive Briefing Paper Date: 07 December 2021 Subject: Local Authority Delivery Phase 2 (LAD2) Funding Scheme for energy efficiency measures in Council homes Briefing by: Deputy Chief Executive Officer Portfolio: Housing

INTRODUCTION

1. At its meeting of the 11 October 2021, the Executive discussed the LAD2 funding opportunity to improve Council owned homes. The funding and contract mechanisms were also approved at this meeting.

2. Further conversations have been underway on availability of funding and it has emerged that the Council could apply for more works than originally anticipated. By extending the contract with City Energy, the company delivering these works, the Council can improve the energy efficiency in more of its social housing stock.

THE LOCAL AUTHORITY DELIVERY PHASE 2 (LAD2) SCHEME

3. LAD2 is the second phase of the Government Local Authority Delivery scheme. The intention of LAD is to improve the household energy efficiency for those on low income. The scheme is open until the end of the financial year and is aimed at properties with poor energy efficiency. These have been stipulated as homes with an Energy Performance Certificate (EPC) of D or lower. A cap of £30,000 combined income per household has also been set to ensure the works target those who need help the most.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Authority Delivery Phase 2 (LAD2) Funding Scheme for energy efficiency measures to Council homes: UpdateReport 239 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 15 attended
SW
Councillor Seán WoodwardCommittee Member, present
TC
Councillor Trevor Cartwright, MBECommittee Member, present
IB
Councillor Ian BastableCommittee Member, present
FB
Councillor Fred BirkettCommittee Member, present
SM
Councillor Simon MartinCommittee Member, present
MS
Councillor Mrs Susan WalkerCommittee Member, present
PG
Peter GrimwoodOfficer, expected
NW
Councillor Nick WalkerGuest, in attendance
RI
Richard IvoryOfficer, expected
RJ
Richard JolleyOfficer, expected
AW
Andrew WannellOfficer, expected
LA
Lindsey AnsellOfficer, expected

All 15 on the meeting page

On this subject at Fareham

Search all
  1. Local Authority Delivery Phase 2 (LAD2) Funding Scheme for energy efficiency measures to Council homes - UpdateThis decision
  2. Local Authority Housing Fund Grant FundingApproved
  3. Partnership for South Hampshire - Local Nutrient Mitigation Fund Projects Inter Authority AgreementAgreed
  4. Facilitating the use of the Local Authority Housing FundApproved
  5. Local Authority Delivery Phase 2 (LAD2) Funding scheme for energy efficiency measures to Council homesAgreed
  6. Local Authority Discretionary Grant SchemeAgreed

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies