RESOLVED that the Executive approves: (a) the preparation of a Fareham Town Centre Masterplan Supplementary Planning Document (SPD) be prepared using the remaining £253,000 allocated for the Civic Quarter masterplan; (b) the appointment of the preferred bidder for the construction of Fareham Live outlined in confidential Appendix A to the report; (c) a revised budget of £16.69m for the Fareham Live project to be funded through current and future CIL receipts; and (d) the replacement of Osborn Road Multi Storey car park, with a 120-space surface car park at a cost of £1.96m
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 16 May 2022 Portfolio: Policy & Resources
Regeneration of Fareham town centre, including Subject: Fareham Live and Osborn Road Multi-Storey car park
Director of Planning and Regeneration Report of: Director of Leisure and Community Deputy Chief Executive Officer Maintain and extend prosperity Corporate Priorities: Leisure opportunities for health and fun Providing housing choices
Purpose: The future shape of Fareham town centre is starting to take form. Two major projects in the Civic Quarter, with an agreed combined budget allocation of £19.075 million, have been analysed in detail and are now ready to progress at a total cost of £18.65 million. This will result in a new surface car park to replace the decaying multi-storey at Osborn Road, sitting alongside Fareham Live, an exciting new arts and entertainment venue.
This report provides background information on the opportunities ahead and presents proposals to prepare a Fareham Town Centre Masterplan Supplementary Planning Document (SPD), appoint a construction contractor for the Fareham Live project and provide a 120 space surface car park to replace Osborn Road Mutli-Storey with the aim of transforming the town centre and kick starting its regeneration.
Executive summary: The Council’s current Corporate Strategy 2017-23 commits to starting the regeneration of the town centre and the creation of a new arts and entertainment venue.
The development of plans for the future of Fareham town centre as a whole and both Fareham Live and Osborn Road Multi-Storey Car Park have evolved over a number of years.
Fareham Town Centre Regeneration
A budget of £275,000 was approved by the Executive on 9 July 2018, to fund the development and delivery of master-planning work in the Civic Quarter. As would be expected of initiatives of this size, the Fareham Live and Osborn Road Car Park projects have taken up the majority of the available officer resource during the last few years, meaning that only £22,000 of the master-planning budget has so far been spent.
Changing retail patterns, the loss of key retailers and the COVID-19 pandemic have had a significant impact on Fareham town centre and there is a clear need to progress and deliver regeneration proposals for the town centre. The Local Plan 2037 identifies a central area of the town centre that could accommodate around 620 new homes with a mixture of retail, commercial, food and leisure uses alongside the new Fareham Live venue.
The report proposes that the remaining master-planning budget be used to fund the preparation a Fareham Town Centre Masterplan Supplementary Planning Document (SPD) to provide greater clarity on development proposals and guide investment.
Fareham Live
The cost of raw materials and building resources for constructions projects have inevitably rapidly increased since the start of the pandemic. This resulted in the construction costs rising from £12.57m in late 2020 to £13.35m when Executive approved the restarting of the project following a 10-month pause on the 30 September 2021.
Following the resumption of the project, tenders were sought from the building contractors shortlisted for the project prior to the pause in 2020.
Completed tenders were returned on 30 January 2022, with refinements following further clarification questions. Each submission was higher than the £13.35m estimated by the project’s cost consultants in September 2020.
The preferred bidder scored equal lowest on the tendered sum and highest in terms of quality and is presented for approval at confidential Appendix A. The overall project budget has increased to £16.69m when the non-construction related costs, such as contingencies, consultant fees and furniture, fittings and equipment purchases are included.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.