Fareham Town Centre Regeneration Programme and Masterplan

Approved Executive 3 papers

AI summaryFareham Executive approves town centre masterplan and £2.6m capital for next design stage, including partial demolition of shopping centre's eastern third.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNext design stage of Town Centre Masterplan to proceed
Money£2,604,610 capital plus £262,200 revenueTotal capital for 2026/27 from unallocated receipts
What happens nextOutline planning applicationContinued arcading and car park design work
Who it affectsFareham town centre and visitorsIncludes partial demolition of shopping centre

What was decided

The Executive approved the emerging Town Centre Masterplan and progression to the next design stage, with delegated authority to the Director of Planning and Regeneration to take the outline planning application through to determination. Report P10

Continued work on the arcading, car parking options and other Town Centre Masterplan delivery workstreams was approved, with delegated authority to progress these to the next design stage and negotiate with partners and tenants. Report P11

Maximum capital expenditure of £1,165,162 for the next stage of masterplan development and £1,439,448 for arcading, car parking and other workstreams was approved, with contract award thresholds set at £250,000 and S151 officer consultation required above that. Report P12, P13, P14, P15

Why

The Council has a corporate priority to accelerate regeneration of Fareham Town Centre under the adopted Fareham Town Centre Regeneration Strategy 2025-2035, and significant progress has been made since the shopping centre was acquired in 2023. Report P5, P40, P42

Stage One Masterplanning has been completed, including a tested proposal for partial demolition of about one third of the eastern side of Fareham Shopping Centre, retention of the Civic Offices as an economic anchor, like-for-like reprovision of car parking, and improved north-south movement through an upgraded arcade. Report P6, P64, P65

What happens next

Officers will prepare and submit an outline planning application with detailed elements, supported by further technical assessments, public engagement and pre-application discussions with the local planning authority. Report P108, P109, P110

A further round of public engagement is scheduled in March 2026, with a final round before the planning application is submitted. Report P48, P96

Reports on an Interim 5 Year Asset Management Plan for the Civic Offices (Summer 2026), a full business case for the arcading (Summer 2026) and a full business case for car parking options (Autumn 2026) will be brought back to the Executive. Report P44, P70, P122, P129

The money

  • £1,165,162 Capital for next stage of masterplan development and outline planning application Report P12, P63
  • £388,398 Capital for next stage of arcading detailed design Report P70, P155
  • £423,535 Capital for next stage of car parking options design and testing Report P76, P155
  • £627,515 Capital for other town centre masterplan delivery workstreams Report P79, P155
  • £1,439,448 Total capital for arcading, car parking and other delivery workstreams Report P14, P155
  • £262,200 Revenue budget increase for 2026/2027 and ongoing for regeneration delivery Report P16, P158
  • £142,160 Revenue increase for masterplan staffing Report P158
  • £110,040 Revenue increase for wider regeneration staffing Report P158
  • £10,000 Revenue increase to town centre events budget Report P86, P158
  • £2,604,610 Total capital request for this phase of the masterplan Report P18, P155

Options considered

  • Chosen: Demolish approximately one third (eastern section) of Fareham Shopping Centre. Found to be the most cost effective, sustainable, balanced and deliverable solution supporting town centre regeneration aims. Report P63, P64, P65
  • Rejected: Demolish approximately half of the shopping centre footprint. Considered but not the preferred option after cutline study testing of capital, carbon, tenancy and deliverability impacts. Report P63, P64
  • Rejected: Convert Civic Offices to residential after 2030. Economic Impact Assessment shows significantly lower economic value, limited employment and GVA impacts and weak market demand for resulting flats. Report P42, P90, P92
  • Rejected: Continue operating Civic Offices with only essential maintenance (Option 1 baseline). Would leave the building unfit for continued occupation after 2030 and risk losing the economic contribution of 399 jobs and over £45.5m annual value. Report P36, P38, P85
  • Chosen: Replace the FSC multi-storey car park with decked levels at Fareham Live A Car Park plus a smaller surface car park. Early testing indicates it could consolidate parking close to key cultural and leisure destinations while releasing land for development; full testing continues into next design stage. Report P71, P72, P104

Implications

  • Financial: Capital request of £2,604,610 to be funded from unallocated capital receipts and expected 2026/27 receipts from Daedalus land disposals; revenue increase of £262,200 met from existing revenue reserves. Report P18, P98, P156, P158
  • Legal: Confidential Appendix C is withheld under Schedule 12A of the Local Government Act 1972 to protect the Council's negotiating position and value for money on future contracts. Report P22, P23, P24
  • Risk: Officers flag risks around phasing, parking re-provision, third-party lease interests, and the need to manage tenants, public service providers and key retailers through relocation. Report P22, P50, P98, P102
  • Staffing: Additional revenue covers increased staffing for masterplan (£142,160) and wider regeneration (£110,040) and an events budget uplift (£10,000). Report P99, P158
  • Other: An outline planning application with detailed elements is the planned next step, with pre-application discussions and a further round of public engagement scheduled for March 2026. Report P48, P59, P96, P108

Who and where

  • Fareham Shopping Centre tenants, including the Library, NHS services (including GP surgery) and Job Centre, who will be involved in managed relocations Report P50, P98, P102
  • Town centre businesses, operators and Fareham College students, through continued business breakfasts, operator meetings and student engagement Report P54, P55, P88, P95
  • Residents, visitors and local business community, through ongoing surveys via the Town Centre Perception Panel and public engagement events Report P53, P94, P96, P97
  • Civic Offices staff and other tenants of the building, given the building is to be retained as an economic anchor Report P30, P34, P45, P92
  • Hampshire County Council, First Bus and Network Rail partners working on bus and train station improvements Report P10

Timeline

  • September 2023: Council completed acquisition of Fareham Shopping Centre and associated West Street properties Report P41
  • February 2025: Executive adopted the Fareham Town Centre Regeneration Strategy 2025-2035 Report P42, P58
  • October 2025: Executive approved annual review of Corporate Strategy designating town centre regeneration as a Category 1 Accelerate project Report P40
  • November to December 2025: Public engagement on emerging masterplan proposals; around 580 attendees and over 230 feedback forms Report P46, P94
  • March 2026: Further round of public engagement on emerging masterplan scheduled Report P48, P96
  • 2026/2027: Next design stage of masterplan, arcading and car parking workstreams to be delivered Report P7, P63, P70, P76
  • By October 2026: First phase of West Street Public Realm Improvements to be delivered Report P11
  • Summer 2026: Reports expected on Civic Offices Interim 5 Year Asset Management Plan and arcading full business case Report P44, P70
  • Autumn 2026: Car parking options full business case to be reported to the Executive Report P76

Plain English for the jargon

  • RIBA Stage 2: The second stage of the Royal Institute of British Architects' plan of work, covering concept design; the current masterplan work has reached this stage.
  • Daedalus: A site in Fareham whose land disposals are expected to generate capital receipts funding the masterplan.
  • LGR: Local Government Reorganisation, the structural changes to local government in the area which may create a new unitary authority.
  • S151 officer: The Council's chief finance officer, designated under section 151 of the Local Government Act 1972, who must be consulted on contract awards above £250,000.
  • FSC: Fareham Shopping Centre, acquired by the Council in 2023 and the focus of the Town Centre Masterplan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10(1)

Resolved

RESOLVED that the Executive: (a) approves the emerging Town Centre Masterplan as set out in Appendix A and progression to the next design stage, and delegates authority to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources, to progress all aspects of the planning application, including its preparation, submission, ongoing management, and progression through to determination; (b) approves continued work on the arcading, car parking options and other identified Town Centre Masterplan delivery workstreams, and delegates authority to the Director of Planning and Regeneration to progress these workstreams through the next design stage, including detailed design development, technical assessments, costing, and all necessary ongoing negotiations with partners, stakeholders and affected tenants as required; (c) subject to the approval of recommendation (a) above, approves a maximum capital expenditure of £ 1,165,162 for the next stage of development of the Town Centre Masterplan and delegates authority to the Director of Planning and Regeneration to enter into contracts to secure this, within the agreed budget as follows: · individual contracts for £250,000 and under, or · following consultation with the S151 officer for any individual contract awards over £250,000 (d) subject to the approval of recommendation (b) above, approves a maximum capital expenditure of £1,439,448 for the arcading, car parking options and other identified Town Centre Masterplan delivery workstreams and delegates authority to the Director of Planning and Regeneration, to enter into contracts to secure this, within the agreed budget as follows: · individual contracts for £250,000 and under, or · following consultation with the S151 officer for any individual contract awards over £250,000 (e) approves an increase to the base revenue budget of £262,200 for 2026/2027 (and ongoing) for the continued delivery of regeneration workstreams; and (f) notes and agrees the overarching financial approach as detailed in the confidential Appendix C to this report.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 19 February 2026

Portfolio: Policy and Resources

Subject: Fareham Town Centre Regeneration Programme and Masterplan Report of: Director of Planning and Regeneration Promote Economic Development Provide Housing Choices Leisure Opportunities for Wellbeing and Fun Corporate Priorities: Strong, Safe and Healthy Communities Respond to Climate Change and Protect the Environment Responsive, Inclusive and Innovative Council

Purpose: To seek Executive approval for the continuation of the Fareham Town Centre regeneration programme and the associated budgets for 2026/27 in line with the adopted Fareham Town Centre Regeneration Strategy 2025-2035.

Executive summary: The Council has a clear corporate priority to accelerate the regeneration of Fareham Town Centre in line with the adopted Fareham Town Centre Regeneration Strategy 2025–2035. Significant progress has been made since acquisition of Fareham Shopping Centre (FSC) in 2023 and the approval of the Strategy in 2025.

Stage One Masterplanning has now been completed, including proposals for the partial demolition of the eastern third of the Shopping Centre, the retention of the Civic Offices as a key economic anchor, the like for like reprovision of car parking, the creation of new development plots for homes and mixed uses, and improved movement through a new north–south route and upgraded arcading.

This report seeks Executive approval to progress the Masterplan to the next design stage, including preparation of an outline planning application with detailed elements, continued design development of arcading proposals, testing of car parking solutions, delivery of early enabling work, and advancement of wider regeneration workstreams.

The associated capital request totals £2.60m for 2026/27, funded by sufficient capital receipts, alongside £262,200 in revenue funding from reserves. Approving these recommendations will maintain momentum, provide financial certainty, and ensure continued delivery of a comprehensive, phased regeneration programme that strengthens Fareham’s economy, enhances public spaces, increases housing supply, and creates a more vibrant, accessible and resilient town centre for residents, businesses and visitors.

Recommendation: It is recommended that the Executive:

(a) approves the emerging Town Centre Masterplan as set out in Appendix A and progression to the next design stage, and delegates authority to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources, to progress all aspects of the planning application, including its preparation, submission, ongoing management, and progression through to determination;

(b) approves continued work on the arcading, car parking options and other identified Town Centre Masterplan delivery workstreams, and delegates authority to the Director of Planning and Regeneration to progress these workstreams through the next design stage, including detailed design development, technical assessments, costing, and all necessary ongoing negotiations with partners, stakeholders and affected tenants as required;

(c) subject to the approval of recommendation (a) above, approves a maximum capital expenditure of £1,165,162 for the next stage of development of the Town Centre Masterplan and delegates authority to the Director of Planning and Regeneration to enter into contracts to secure this, within the agreed budget as follows:

• individual contracts for £250,000 and under, or • following consultation with the S151 officer for any individual contract awards over £250,000

(d) subject to the approval of recommendation (b) above, approves a maximum capital expenditure of £1,439,448 for the arcading, car parking options and other identified Town Centre Masterplan delivery workstreams and delegates authority to the Director of Planning and Regeneration, to enter into contracts to secure this, within the agreed budget as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Masterplan Design Progress Report (1)Appendix A 18 MB Download
PDF
Economic Impact Assessment (1)Appendix B 2.9 MB Download
PDF
Fareham Town Centre Regeneration Programme and MasterplanReport 226 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
SM
Councillor Simon MartinCommittee Member, present
FB
Councillor Fred BirkettCommittee Member, present
IB
Councillor Ian BastableCommittee Member, present
JB
Councillor Joanne BurtonCommittee Member, present
MD
Councillor Malcolm DaniellsCommittee Member, present
CH
Councillor Connie HockleyCommittee Member, present
DH
Councillor David HamiltonGuest, in attendance
RI
Richard IvoryOfficer, expected
RJ
Richard JolleyOfficer, expected
LU
Leigh UsherOfficer, expected
AW
Andrew WannellOfficer, expected
RL
Robyn LyonsOfficer, expected

All 16 on the meeting page

On this subject at Fareham

Search all
  1. Fareham Town Centre Regeneration Programme and MasterplanThis decision
  2. Fareham Town Centre Masterplan Delivery - Fareham Shopping Centre Investment - shopping arcade, entrances and associated improvement worksApproved
  3. Fareham Town Centre Masterplan Delivery - Fareham Shopping Centre Investment: Shopping Arcade, Entrances and associated improvement worksNoted
  4. Fareham Town Centre Regeneration - West Street Public RealmApproved
  5. Fareham Town Centre Regeneration - North/South Evening RouteApproved
  6. Lets Talk Progress: Fareham Town Centre - PresentationDecided

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies