RESOLVED that, Members AUTHORISE the completion of a Deed of Variation to the Section 106 agreement: - a) To vary the obligation relating to the completion of the Down End Road/A27 capacity improvements to require the developer to use reasonable endeavours to complete those works as soon as possible following the completion of the Transforming Cities Fund Improvements by Hampshire County Council and in any event prior to the occupation of the 75 th residential unit.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
DEED OF VARIATION OF SECTION 106 UNILATERAL UNDERTAKING REGARDING TRIGGER FOR HIGHWAY WORKS AT A27/DOWNEND ROAD/SHEARWATER AVENUE JUNCTION
LAND EAST OF DOWN END ROAD, PORTCHESTER
Report By Richard Wright – direct dial 01329 824758
1.0Introduction 1.1 In October 2021 outline planning permission was granted on appeal for the construction of up to 350 dwellings on land to the east of Down End Road, Portchester (planning reference P/20/0912/OA; appeal reference APP/A1720/W/21/3272188). The planning permission is subject to a Section 106 planning obligation which secures various obligations including financial obligations and off-site highway works.
2.0Description of Proposal 2.1 As part of the development, Schedule One of the Section 106 requires the owner of the land to enter into a Highway Works Agreement pursuant to Section 278 of the Highways Act 1980 to deliver various off-site highways works. This includes a scheme of works to improve the capacity of the junction of Down End Road with the A27 and Shearwater Avenue.
2.2The developer, Miller Homes, has made a request to the local planning authority, Fareham Borough Council, to vary the Section 106. Instead of the works to the junction having to be completed prior to the occupation of the first dwelling on the site, Miller Homes have requested the wording of the Section 106 be varied to allow for up to 74 dwellings to be occupied before the works must be completed. If considered acceptable in planning terms, the Section 106 could be amended accordingly by the parties entering into a Deed of Variation.
2.3The nature of the works themselves would remain unchanged and include the provision of two southbound approach lanes on Down End Road, the introduction of MOVA technology to the traffic signals and the revision of yellow markings and lane tracking markings. 2.4 Miller Homes have explained that the reason for this request is that they are unlikely to be able to carry out the junction improvements until after March 2024. This is because a Hampshire County Council scheme of improvements to the A27, delivered under the Transforming Cities Fund (TCF), is already scheduled to begin in January 2023 and last until March 2024. The junction works are unable to take place at the same time. Miller Homes have explained that this is because HCC are not agreeable to including the junction within the TCF scheme of works and, owing to health and safety issues, it would not be possible to have two sets of contractors on the same road space concurrently. The Miller Homes works are reliant on the completion of the TCF works and so can only occur after the HCC scheme has been completed. To minimise any delays it is intended that Miller Homes’ junction works will run directly after the HCC TCF scheme is completed in March 2024. Miller Homes would then deliver its works as a second phase. Miller Homes have given a commitment to continue liaising with HCC to see if there becomes any flexibility in the TCF programme/road space booking that may allow the works to be brought forward.
2.4There would be no changes to any of the other obligations in the Section 106 such as, for example, the details or the trigger for the improvements to the Down End Road bridge.
3.0Planning Considerations 3.1 The purpose of the obligation to provide the junction improvements is, in combination with the other works secured in the Section 106, to avoid residual cumulative impacts on the road network which would be severe (in accordance with paragraph 111 of the NPPF). The principal consideration for Members in deciding whether to grant Miller Homes’ request is whether the obligation would continue to serve this purpose equally well if varied. In other words, whether the residual impact on the road network of up to 74 dwellings being occupied before the junction improvements are completed would be severe.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.