RESOLVED that: - (i) PLANNING PERMISSION be granted, subject to: - i) The conditions in the report; ii) The additional Condition 19 as set out in the Update Report; and Then: (ii) AUTHORITY BE DELEGATED to the Head of Development Management to make any necessary modification, deletion or addition to the proposed conditions.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
DEVELOPMENT OF CREMATORIUM WITH ASSOCIATED ACCESS, LANDSCAPING AND MEMORIAL GARDENS
“HORSE FIELD”, LAND NORTH OF BRUNE LANE, FAREHAM
Report By Mark Wyatt – direct dial 01329 824704
1.0Introduction 1.1 This application is reported to the Planning Committee in accordance with the Scheme of Delegation given the number of representations received.
2.0Site Description 2.1 The application site is located to the east of Broom Way and north of Brune Lane.
2.2The land is broadly rectangular in shape extending to 6.5 acres (2.6 hectares), generally flat and is used for the grazing of horses. The site is open and visible from Broom Way on the western side of the site. The northern edge of the site is well screened by established mature tree planting with Rowner Road beyond running east from Peel Common roundabout. Mature landscaping lines the eastern boundary also. This planting is designated as a Site of Importance for Nature Conservation (SINC). Beyond the eastern boundary is the golf course. The southern boundary to Brune Lane is hedged but thinner than the east and north boundaries such that views, especially in the winter months, are afforded into the site.
3.0Description of Proposal 3.1 The application proposes a new, single chapel, crematorium with access, parking and memorial gardens.
3.2The access will be taken from Brune Lane into the site. The access and parking area is to the western edge of the site with the building positioned to the eastern side. The proposed memorial garden is to the north of the building.
3.3The proposal will provide ninety-four parking spaces for visitors plus six staff parking. The main access and parking areas are to be finished with a resin bonded gravel material and curves in form along the western side of the site. Sixty-two formal parking spaces are provided, including six disabled spaces. A further twelve spaces are provided for visitors to the memorial garden (although these spaces are not exclusive to the garden and could be used by any visitor to the site) in an area to be finished with grasscrete giving a total of seventy- four formal spaces.
3.4Additional areas of grasscrete parking for use in cases of over overspill are also provided for. These total twenty further parking spaces with three on the east side of the access entrance, along the verges to the south side of the building (twelve spaces) and along the western edge (left hand side as you enter) of the driveway into the site (five spaces). Including these grasscrete verges gives an overall parking capacity of approximately ninety-four spaces for mourners. A further six spaces for staff are provided for at the rear of the building including two electric vehicle charging bays. Deliveries will be taken in the rear yard.
3.5The building is single storey and is of a contemporary flat, sedum, roof design. The finished height of the chapel itself will be 7m at its highest with lower elements of roof serving the administrative parts of the building and the entrance porte cochere (a roofed structure covering a driveway at the entrance of a building. It provides shelter for people entering or leaving vehicle) are 6m tall with the entrance vestibule just under 4m high. Three flues will project above the roof 3m higher than the finished roof.
3.6The capacity of the crematorium chapel will be 90 seats, but internal folding doors could increase this capacity to 130 if the entrance vestibule is utilised. The Crematorium is designed to have a flow through the building. Visitors would enter the building at the main entrance, through the chapel, and leave to the south through the exit porte cochere through the flower garden.
3.7As well as the sedum roof the building is proposed to be finished with a simple material palette including cedar cladding, stone and steel. Projecting out from the building will be “living walls”
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.