RESOLVED that the deed of variation to the legal agreement to enable the provision of the temporary access arrangements in accordance with the advice of the Highway Authority into the site for residents and the occupation of no more than 30 dwellings on site until the primary access road from Peak Lane is constructed and completed be APPROVED.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Q/0826/23 STUBBINGTON WARD PERSIMMON HOMES SOUTH COAST AGENT: PERSIMMON HOMES
DEED OF VARIATION TO SECTION 106 UNILATERAL UNDERTAKING DATED 10 NOVEMBER 2021 REGARDING APPLICATION P/20/0522/FP, RELATING TO TEMPORARY ACCESS ARRANGEMENTS TO ENABLE OCCUPATION OF DWELLINGS IN ADVANCE OF COMPLETION OF MAIN SITE ACCESS ROAD FROM PEAK LANE
LAND EAST OF CROFTON CEMETERY AND WEST OF PEAK LANE, STUBBINGTON, FAREHAM
Report By Peter Kneen – direct dial 01329 824363
1.0Introduction 1.1 Planning permission was granted for this site on appeal in January 2022 under appeal reference APP/A1720/W/21/3275237 for the following proposal:
Development comprising 206 dwellings, access road from Peak Lane maintaining link to Oakcroft Lane, stopping up of a section of Oakcroft Lane (from Old Peak Lane to access road), with car parking, landscaping, substation, public open space and associated works.
1.2Planning permission was granted on the basis that a new access road would be formed between the site and Peak Lane (just south of the Stubbington By- pass junction) before any of the properties were occupied. The developer gave a legal undertaking to this effect.
1.3The legal undertaking secured the provision of a realignment of Oakcroft Lane through the provision of a dedicated access road from Peak Lane to the site, before re-connecting to Oakcroft Lane westwards. The existing eastern access to Oakcroft Lane would subsequently become a ‘no through road’, with access only to those properties east of the development site.
1.4Within the Section 106 Unilateral Undertaking, Schedule One (Highways and Travel Plan Obligations), paragraph 2.1 states:
“The Owner covenants not to Occupy nor permit Occupation of the Development unless and until the Highway Works have been carried out and completed to Completion Certificate Standard under a s278 Agreement entered into with the County Council”.
1.5Those ‘Highway Works’ are defined in the Section 106 Unilateral Undertaking, Schedule One as being:
“Access works and pedestrian infrastructure to connect to a new pedestrian refuge on Peak Lane as shown in principle in drawing 048.0013.001 Rev D…”
1.6The development of the site is now well progressed and the first dwellings will be ready for occupation at the beginning of December 2023. A section of the new access road has been constructed. Whilst the Section 278 application with the County Council was submitted some time ago, it has only recently been concluded with works scheduled to take place to finalise the connections between Peak Lane and Oakcroft Lane starting in January 2024. These final highway works are anticipated to take 3 months to complete, with the main length of the access road having already been constructed. Only the connections to the wider road network need to be undertaken. However, as those discussions and negotiations regarding the Section 278 application took considerably longer than expected, the developer is seeking to vary the terms of the obligation set out above, to enable up to 30 dwellings to be occupied before the new access road defined as ‘Highway Works’ is completed and available for use.
1.7Subsequently a variation of the Section 106 Agreement is sought to provide a safe means of access to the site for residents via Oakcroft Lane to enable up to 30 properties to be occupied in advance of the formal completion of the dedicated access road from Peak Lane to the development site.
2.0Consultations
Highway Authority – Hampshire County Council 2.1 No objections in respect of highway safety concerns, subject to compliance with the Technical Note 048.0013/TN/7, which stipulates:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.