Resolved
RESOLVED that the Audit and Governance Committee notes the progress and findings from the Internal Audit Work.
Audit and Governance Committee decided this item on Monday 27 November 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Audit and Governance Committee notes the progress and findings from the Internal Audit Work.
This report is a standard item on the Audit and Governance Committee agenda with the aim of providing Members with the assurances arising from the latest internal audit work. It also gives an update on the progress being made with setting and delivering the audit plans.
It is RECOMMENDED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. INTRODUCTION
1. This report provides the assurances arising from the latest internal audit work and gives an update on the progress being made with setting and delivering the audit plans.
PROGRESS OF THE 2023/24 AUDIT PLAN
2. Work has commenced on 13 (59%) of the 22 audits in the current internal audit plan, as noted in Appendix One, such that 4 of the audits have been finalised, 2 are at stage 5 (A first draft of the report has been received by the Support Officer to be reviewed), 6 are at Stage 4 (The Auditor has started to deliver the agreed scope of work) and 1 is at Stage 2 (A scoping meeting has been held with the Sponsor in the client service).
FINALISING PREVIOUS PLANS
3. There were 6 outstanding audits from the previous Audit Plans. Work has been concentrating on the review of all outstanding audit recommendations which continues to be progressed. 270/420 (64%) of the recommendations have now been allocated to individual auditors leaving 150 to cover by the end of the year.
4. Considerable progress has also been made on the wider piece of work looking at S106 contribution balances and the process flow, which is likely to be concluded by the end of the calendar year.
5. The scope of the Homelessness audit for 2023/24 has also been adapted to allow the closedown of the Housing Options debtors audit from 2018/19, on completion of the review.
FINDINGS FROM COMPLETED AUDITS
6. Four audits have been completed since the last report as highlighted in the table below. There are no significant findings to highlight.
Recommendations Made Assurance Audit New New Outstanding Opinion Previous Essential Essential Important or Important
Planning Applications 2023/24 Strong - - -
Treasury Management 2023/24 Strong - 2 -
Service Charges and Recharges – Reasonable - 3 - Leaseholders - 2022/23
IT Recommendation Follow Up 2023/24 N/A - - 3 RISK ASSESSMENT
7. There are no significant risk considerations in relation to this report.
Appendices: Appendix One - Audits in the 2023/24 Plan Appendix Two – Reference Tables
Background Papers: Head of Audit’s quarterly report to the Audit and Governance Committee on 25th September 2023. Head of Audit’s quarterly report (including 2022/23 Audit Plan) to the Audit and Governance Committee on 13th March 2023.
Reference Papers: None
Enquiries: For further information on this report please contact Clare Rogers. (Tel: 01329 824691) APPENDIX ONE AUDITS IN THE 2023/24 PLAN
Direction of New Recommendations Previous Recs. (E and I only) Progress Stage reached Days Assurance Travel & Audit Title & Report Number report where Errors of 10* in Plan Opinion Date of last In Not included Found Essential Important Implemented Cancelled audit Progress Implemented ? Y/N
FUNDAMENTAL SYSTEM AUDITS
Income Management (1279) 5 12
Main Accounting System & Not started 8 Budgetary Control (1280)
November Treasury Management (1281) 10 12 Strong 19/20 2023 N 2
Vehicle Management Invoice Not started 10 Management (1282)
Benefits (1283) 5 12
SERVICES AND SYSTEMS - HIGH RISK
Homelessness (1284) 4 15
Housing Grants and Home 4 5 Improvement Loans (1285)
September Leisure Centres (1286) 10 12 Strong 17/18 2023 N - 1 - - - -
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Head of Internal Audits Quarterly ReportReport | 148 KB | DownloadRead as text |
Follow Audit and Governance Committee at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Business ContinuityRESOLVED that the Audit and Governance Committee note the contents of the report. | Noted | Open |
| 8 Sep 2026 | Corporate Complaint Handling - Performance and Learnings 2025/26RESOLVED that the Audit and Governance Committee: - (a) note the content of the Fareham Housing specific 2025/26 Comp... | Noted | Open |
| 8 Sep 2026 | Chief Internal Auditor's Quarterly ReportRESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. | Decided | Open |
| 8 Sep 2026 | Committee ReportRESOLVED that the Audit and Governance Committee: - a) notes the contents of Part One of the report, including the Co... | Approved | Open |
| 27 Jul 2026 | External Audit - Annual Plan and Fee 2026/27RESOLVED that the Audit and Governance Committee: a) approves the 2025/26 Audit Plan, attached as Appendix A to this ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.