Resolved
RESOLVED that the Audit and Governance Committee:- a) notes the progress and findings arising from Internal Audit work; and b) approves the proposed full plan for the 2024/25 audit year as set out in Appendix Three.
Audit and Governance Committee approved this item on Monday 11 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Audit and Governance Committee:- a) notes the progress and findings arising from Internal Audit work; and b) approves the proposed full plan for the 2024/25 audit year as set out in Appendix Three.
This report is a standard item on the Audit and Governance Committee agenda with the aim of providing Members with the assurances arising from the latest internal audit work. It also gives an update on the progress being made with setting and delivering the audit plans.
It is RECOMMENDED that the Audit and Governance Committee: a) notes the progress and findings arising from Internal Audit work; and
b) approves the proposed full plan for the 2024/25 audit year as set out in Appendix Three. INTRODUCTION
1. This report provides the assurances arising from the latest internal audit work and gives an update on the progress being made with setting and delivering the audit plans.
PROGRESS OF THE 2023/24 AUDIT PLAN
2. Work has commenced on 20 (91%) of the 22 audits in the current internal audit plan, as noted in Appendix One, such that 11 of the audits have been finalised, 7 are at Stage 4 (The Auditor has started to deliver the agreed scope of work) and 1 is at Stage 3 (The Terms of Reference for the Assignment have been issued) and 1 is at Stage 1 (The Audit teams have started drawing up the scope of coverage for the assignment).
3. As part of the restructure of the finance department, a new Chief Internal Auditor, Mark Somerset, will be appointed from the audit partnership from 1st April 2024. The Key Finance System Data Analytics audit from the 2023/24 plan has been postponed until early 2024/25, and to allocate that time from the partnership agreement for the completion of the 2024/25 audit plan. This will also allow the relevant data extracts to be available for testing.
FINALISING PREVIOUS PLANS
4. There are 5 outstanding audits from the previous Audit Plans. Work is continuing to review all outstanding recommendations. The S106 contributions audit has now been completed and work has been undertaken to resolve some previous issues. Going forward there will be quarterly meetings during 2024/25 between the Finance, Planning Strategy and Street Scene teams to discuss new monies received.
FINDINGS FROM COMPLETED AUDITS
5. 8 audits have been completed since the last report as highlighted in the table below. There are no significant findings to highlight.
Recommendations Made Assurance Outstanding Audit New New Previous Opinion Essential Important Essential or Important
Local Government Software package Strong - - -
Benefits Strong - - 1
Income Management Strong - - 1
Housing Grants and Home Improvement Loans Strong - - -
Energy Rebates - data matching of 2022/23 N/A - 1 - payments Recommendations Made Assurance Outstanding Audit New New Previous Opinion Essential Important Essential or Important
Process Flow for S106 Contributions (22/23 N/A - 5 - audit plan)
Annual Procurement Transaction Testing N/A - 13 1
Home working - Risk Assessments and N/A - 20 - Confidentiality Arrangements
6. The inhouse audit team have recently completed a piece of assurance work looking at Home Working in relation to the completeness of employee risk assessments and confidentiality arrangements whilst working at home. Interviews were carried out with a sample of employees and overall working from home was seen as a positive. No issues were found with the adequacy of the management of the home work station assessments which was the main reason for the audit. Other suggestions for improvement of management of home working the arrangements were raised following all the interview work carried out and a corporate action plan has been created which will help inform a wider workforce plan.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Strategy 2019Appendix Four | 393 KB | Download |
PDF |
Head of Internal Audits Quarterly Report and Annual PlanReport | 231 KB | DownloadRead as text |
Follow Audit and Governance Committee at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Business ContinuityRESOLVED that the Audit and Governance Committee note the contents of the report. | Noted | Open |
| 8 Sep 2026 | Corporate Complaint Handling - Performance and Learnings 2025/26RESOLVED that the Audit and Governance Committee: - (a) note the content of the Fareham Housing specific 2025/26 Comp... | Noted | Open |
| 8 Sep 2026 | Chief Internal Auditor's Quarterly ReportRESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. | Decided | Open |
| 8 Sep 2026 | Committee ReportRESOLVED that the Audit and Governance Committee: - a) notes the contents of Part One of the report, including the Co... | Approved | Open |
| 27 Jul 2026 | External Audit - Annual Plan and Fee 2026/27RESOLVED that the Audit and Governance Committee: a) approves the 2025/26 Audit Plan, attached as Appendix A to this ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.