RESOLVED that delegation be GRANTED to the Head of Planning in consultation with the Solicitor to the Council to complete a deed of variation to the existing Section 106 legal agreement dated 20 th January 2021 to: Amend the off-site affordable housing contribution required from £245,520.00 to £204,600.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
DEED OF VARIATION TO AN AGREEMENT PURSUANT TO SECTION 106 OF THE TOWN AND COUNTRY PLANNING ACT 1990 DATED 20 JANUARY 2021, RELATING TO APPLICATION P/18/0107/OA SEEKING VARIATION OF OBLIGATION FOR FINANCIAL CONTRIBUTION TOWARDS OFF-SITE AFFORDABLE HOUSING PROVISION
LAND TO EAST AND WEST OF GREENAWAY LANE (PHASE 1), WARSASH
Report By Susannah Emery – direct dial 01329 824526
1.0Introduction 1.1 In January 2021 outline planning permission (access only) was granted on land surrounding 79 Greenaway Lane for the erection of up to 30 residential units and associated detached garages with access from Greenaway Lane (P/18/0107/OA).
1.2Policy CS18 of the Core Strategy, which was the relevant local plan policy at that time, required the provision of 40% affordable units or an equivalent off- site contribution.
1.3The planning permission is subject to a Section 106 planning obligation which secures various obligations, including Affordable Housing obligations within Schedule 1.
2.0Description of Proposal
2.1Schedule 1 of the Section 106 planning obligation requires the owner of the land to pay to the Council an off-site affordable housing contribution for the six houses to be built on the frontage of the site. Payment of this contribution is linked to the transfer of each of the first four plots to a subsequent owner in four separate instalments. A standard formula was used to establish a figure for the contribution based on a policy compliant requirement for 40% affordable housing for six dwellings using local market information. The sum of the off-site affordable housing contribution to be secured for the frontage properties was £245,520.00. 2.2 The remainder of the site subject to the outline consent extending to the rear of the frontage properties was required to deliver 40% affordable housing on- site and the extent of this area was shown hatched on a plan appended to the S106.
2.3In September 2022 a further full planning application at the site (P/21/1823/FP) was permitted. Instead of the remaining 24 homes being constructed on the land, permission was granted for six detached dwellings. The red line boundary for this application overlapped the rear of the site that had previously been subject to the outline planning permission, incorporating the aforementioned hatched area. The frontage properties permitted by the outline application became known as Phase 1 with the six dwellings permitted at the rear by the full permission becoming known as Phase 2.
2.4It was agreed by Officers that an off-site affordable housing contribution would be accepted for Phase 2 of the development in lieu of on-site provision which again was calculated on the basis of a policy compliant 40% affordable housing and the provision of six dwellings using local market information. The additional contribution of £294,889.88 for Phase 2 was secured within a Section 106 planning obligation dated 16 September 2022.
2.5Development on Phase 1 of the development is now substantially complete. The plots were sold off individually and have been constructed as self-build dwellings with now all but one occupied. However, there are only five dwellings on the Greenaway Lane frontage and not the six that originally had been anticipated when the terms of the S106 were agreed. The reason for this is that access to Phase 2 of the development from Greenaway Lane is shared with Phase 1 and in order to access the rear part of the site it was necessary to remove one of the plots.
2.6The off-site affordable housing contribution secured within the S106 has not been paid in full for Phase 1 of the development. The applicant/liable party has requested that the Council agrees to a reduction by 1/6th to account for the loss of the sixth dwelling. Whilst construction works on Phase 2 of the development are still on-going the affordable housing contribution for Phase 2 has been paid in full.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.