RESOLVED that a deed of variation to enable the occupation of up to 95 dwellings on the site prior to the completion of the works to create the Ecological Mitigation Land in accordance with the Ecological Mitigation Land Plan and its subsequent transfer to Fareham Borough Council be AUTHORISED.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Q/1533/24 STUBBINGTON WARD PERSIMMON HOMES SOUTH COAST AGENT: PERSIMMON HOMES
DEED OF VARIATION OF S106 TO AMEND THE TRIGGER FOR THE TRANSFER OF THE ECOLOGICAL ENHANCEMENT AREA (NORTH OF OAKCROFT LANE) TO FAREHAM BOROUGH COUNCIL FROM PRIOR TO THE OCCUPATION OF THE 50TH DWELLING, TO PRIOR TO THE OCCUPATION OF THE 150TH DWELLING - PLANNING APPLICATION P/20/0522/FP
LAND EAST OF CROFTON CEMETERY AND WEST OF PEAK LANE, STUBBINGTON
Report By Peter Kneen – direct dial 01329 824363
1.0Introduction 1.1 Planning permission was granted for this site on appeal in January 2022 under appeal reference APP/A1720/W/21/3275237 for the following proposal:
Development comprising 206 dwellings, access road from Peak Lane maintaining link to Oakcroft Lane, stopping up of a section of Oakcroft Lane (from Old Peak Lane to access road), with car parking, landscaping, substation, public open space and associated works.
1.2Planning permission was granted on the basis that the land north of Oakcroft Lane up to the Stubbington By-pass (Daedalus Way) and to Peak Lane to the east would form an ecological enhancement area for use by Brent geese and Solent wader species. The land would be transferred to Fareham Borough Council once laid out to the satisfaction of the Council and prior to the occupation of the 50th dwelling on the development site. The developer gave a legal undertaking to this effect.
1.3Within the section 106 Unilateral Undertaking dated 10th November 2021, Schedule Four (Environmental Obligations), which relates to the Ecological Mitigation Land and the Solent Recreation Mitigation Strategy states under paragraphs 2.1 and 2.2:
‘Not to Occupy of permit Occupation of more than 50 (fifty) Residential Units until the Ecological Mitigation Land has been laid out in accordance with the Ecological Mitigation Land Plan to the reasonable written satisfaction of the Borough Council. Not to Occupy or permit Occupation of more than 50 (fifty) Residential Units until the Owner has (by executing and sending an Ecological Mitigation Land Transfer to the Borough Council and releasing the same to the Borough Council for completion) offered to transfer the freehold interest in the Ecological Mitigation Land PROVIDED THAT no such offer shall be made prior to the laying out of the Ecological Mitigation Land in accordance with paragraph 2.1’.
1.4Whilst the works to the Ecological Mitigation Land were undertaken at the outset from the commencement of the development, the works were not undertaken in accordance with the Ecological Mitigation Land Plan, in that the scrapes and swales were too small, and failed to match those from the plan. Additionally, the hedgerow and tree planting around the perimeter in part failed to establish, and poor planting by the contractor meant long sections of the hedgerow were single species plants, rather than mixed species plants. This resulted in additional works needing to be undertaken by Persimmon Homes to ensure it was undertaken in accordance with the approved Plan, and in an acceptable condition for its transfer to the Borough Council.
1.5The proposed variation seeks to enable the transfer to the Borough Council to take place prior to the occupation of the 150th dwelling on the site. This would give sufficient time to complete the additional work on the site and enable an inspection of the site by Council Officers before the formal transfer begins.
1.6Subsequently a variation of the Section 106 Agreement is sought to provide this additional time, and to ensure that future occupations of properties on the development site are not held up.
2.0Consultations 2.1 No consultations were undertaken with this proposed deed of variation although ongoing discussion with the Council’s Head of Street Scene and the Ecologist at Hampshire County Council continue to take place on the works being undertaken to the Ecological Mitigation Land to ensure the transfer can take place at the earliest opportunity.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.