RESOLVED that the Executive:- (a) approves that the General Fund capital programme for 2024/25 be financed as set out in this report; (b) agrees that the additional expenditure incurred, amounting to £506,335 be financed retrospectively from unallocated capital resources; and (c) notes the treasury management activity for 2024/25.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Subject: Capital and Treasury Management Outturn 2024/25
Report of: Assistant Director (Finance and ICT)
Corporate Priorities: A Responsive, Inclusive and Innovative Council
Purpose: This report provides the Executive with details of the capital and treasury management outturn for 2024/25 to comply with the reporting requirements of the Code of Practice for Treasury Management. The report also seeks approval for the proposed methods of financing the General Fund capital programme.
Executive summary: Actual capital expenditure on General Fund schemes in 2024/25 was £13,370,221 (£31.2 million in 2023/24) compared with the revised capital programme of £15,511,300. Overall the programme has been underspent by £2,141,079. A detailed analysis of the variations is given in Appendix A to this report.
Total savings from individual projects of £263,245 were achieved, additional expenditure of £506,335 on others was incurred and a total of £2,384,169 will be carried forward into 2025/26. Details of the various methods used to finance this expenditure are set out in this report.
Full details of Treasury Management investment and borrowing activity in 2024/25 are also set out in this report and is summarised below. This shows that there has been a slight decrease in the Council’s net borrowing position.
31 March 2024 2024/25 31 March 2025 Actual Movement Actual £’000 £’000 £’000 Total borrowing 64,589 (2,753) 61,836 Total investments (13,588) (3,915) (17,503) Net borrowing 51,001 (6,668) 44,333
Net interest received from investments in 2024/25 was £57,388 and net interest paid on borrowing for the HRA was £2,011,719 The overall investment property portfolio increased in value by £103,000 and contracted income was approximately £4,890,000.
During 2024/25, the Council complied with its legislative and regulatory requirements of the Prudential Code.
Recommendation: It is recommended that the Executive:
(a) approves that the General Fund capital programme for 2024/25 be financed as set out in this report;
(b) agrees that the additional expenditure incurred, amounting to £506,335
(c) be financed retrospectively from unallocated capital resources;
(d) notes the treasury management activity for 2024/25.
Reason: To provide the Executive with details of the capital and treasury management outturn in 2024/25 and to comply with the reporting requirements of the Code of Practice for Treasury Management.
Cost of proposals: The necessary resources are available to finance the General Fund capital programme for 2024/25 including the additional expenditure of £506,335.
Appendices: A: Capital Expenditure 2024/25 B: Economic Commentary by Treasury Advisors, Arlingclose C: Prudential and Treasury Indicators 2024/25
Background papers: None
Reference papers: Capital Programme and Capital Strategy 2024/25, Council, 8 January 2024
Finance Strategy, Capital Programme, Revenue Budget and Council Tax 2024/25, Executive Committee, 5 February 2024
Treasury Management Strategy and Prudential Indicators 2024/25, Council, 23 February 2024
Capital and Treasury Management Monitoring 2024-25, Executive Committee, 4 November 2024
Updated Budgets and Council Tax 2025-26, Executive Committee, 13 February 2025 Capital Programme and Capital Strategy 2025/26, Council, 14 February 2025
CIPFA Code of Practice for Treasury Management
CIPFA Prudential Code Executive Briefing Paper Date: 7 July 2025 Subject: Capital and Treasury Management Outturn 2024/25
Briefing by: Assistant Director (Finance and ICT) Portfolio: Policy and Resources
INTRODUCTION
1. This report provides the Executive with details of the capital and treasury management outturn for 2024/25 to comply with the reporting requirements of the Code of Practice for Treasury Management.
GENERAL FUND CAPITAL OUTTURN REPORT 2024/25
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.