AI summaryFareham Borough Council Executive approves 2025/26 capital outturn, adds £45,000 for Innovation Centre lighting and £125,000 for depot fuel infrastructure, and notes treasury management activity.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCapital programme outturn agreed, new items added
MoneyNot stated
What happens nextImplementation of new capital itemsLighting and depot fuel works proceed
Who it affectsCouncil capital programme and financesGeneral Fund and HRA capital spending

What was decided

The Executive approved the General Fund capital programme for 2025/26 to be financed as set out in the report. Report P20

Additional expenditure of £11,537 was agreed to be financed retrospectively from unallocated capital resources. Report P18, P19

Two new capital items were added: £45,000 for lighting replacement at Fareham Innovation Centre (Solent Enterprise Zone retained business rates) and £125,000 for Depot Fuel Infrastructure Investment (additional revenue contributions to capital). Report P5, P6

Why

The report set out the final capital and treasury outturn for 2025/26 in line with the CIPFA Code of Practice for Treasury Management. Report P1

No significant risk considerations were identified in relation to the report. Report P3

The Depot Decarbonisation Scheme is expected to eliminate gas use on site, cutting Scope 1 emissions to zero, while the lighting upgrade at Fareham Innovation Centre is projected to deliver a 12 tCO₂e reduction per annum. Report P5, P6

What happens next

Officers will implement the newly added lighting and depot fuel infrastructure capital items, funded as set out in the decision.

Treasury management activity and prudential indicators for 2025/26 were noted, with no LGR or Mayoral Combined Authority implications identified. Report P8

The money

  • £11,537 Additional expenditure financed retrospectively from unallocated capital resources Report P18
  • £45,000 Lighting Replacement at Fareham Innovation Centre, funded from Solent Enterprise Zone retained business rates
  • £125,000 Depot Fuel Infrastructure Investment, funded from additional revenue contributions to capital
  • 6,716,268 Total General Fund capital actual expenditure 2025/26 Report P20
  • 2,048,398 Total underspend carried forward to 2026/27 Report P20
  • 12,334 HRA actual capital expenditure 2025/26 (£'000) Report P44
  • 19,051 Total actual capital expenditure 2025/26 (£'000) Report P44, P45
  • 118,992 Total Capital Financing Requirement at 31 March 2026 (£'000) Report P48, P49

Options considered

  • Chosen: Finance £11,537 additional Depot Asset Management Works expenditure retrospectively from unallocated capital resources. Reported as additional expenditure requiring retrospective approval Report P18
  • Chosen: Add £45,000 to the Capital Programme for Lighting Replacement at Fareham Innovation Centre. Improves energy efficiency and reduces emissions Report P6
  • Chosen: Add £125,000 to the Capital Programme for Depot Fuel Infrastructure Investment. Funded from additional revenue contributions to capital

Implications

  • Financial: Financing costs as a proportion of net revenue stream were 5% for General Fund and 12% for HRA, both lower than revised estimates. Report P57, P58
  • Climate: The Depot Decarbonisation Scheme is expected to eliminate gas use and reduce Scope 1 emissions to zero; Innovation Centre lighting upgrade is projected to cut 12 tCO₂e per annum. Report P5, P6
  • Risk: The treasury advisers noted continued market volatility from US trade tariffs and the US/Israel conflict with Iran, with Bank Rate held at 3.75% and outlook highly uncertain. Report P22, P25, P29, P39
  • Other: No significant Local Government Reorganisation or Mayoral Combined Authority implications were identified. Report P7, P8

Who and where

  • Fareham Borough Council General Fund capital programme Report P20, P44
  • Fareham Borough Council Housing Revenue Account Report P70, P72
  • Depot operations and decarbonisation works Report P5, P18
  • Fareham Innovation Centre Report P6
  • Treasury management counterparties and lenders Report P35, P36, P37

Timeline

  • 2025/26: Capital and treasury management outturn period Report P1, P20
  • December 2025: Bank of England cut Bank Rate to 3.75% Report P29
  • February 2026: MPC voted 5-4 to hold rates; US/Israel war with Iran began Report P25, P29
  • March 2026: MPC unanimously held rates; FTSE 100 and 250 fell around 10% over the month from the start of the conflict to year end Report P29, P33
  • 31st March: SONIA averaged 4.01% over the 12 months Report P34
  • 2026-07-06: Executive meeting date approving the outturn and new capital items

Plain English for the jargon

  • CIPFA: Chartered Institute of Public Finance and Accountancy, the professional body for public finance.
  • Capital Financing Requirement (CFR): A measure of the council's underlying need to borrow for capital purposes.
  • Minimum Revenue Provision (MRP): The minimum amount a council must set aside from revenue each year to repay capital debt.
  • SONIA: Sterling Overnight Index Average, the benchmark overnight interest rate for sterling.
  • tCO₂e: Tonnes of carbon dioxide equivalent, a standard unit for measuring greenhouse gas emissions.
  • HRA: Housing Revenue Account, the ring-fenced account for council housing income and spending.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11(3)

Resolved

RESOLVED that the Executive: (a) approves that the General Fund capital programme for 2025/26 be financed as set out in this report; (b) agrees that the additional expenditure incurred, amounting to £11,537 be financed retrospectively from unallocated capital resources; (c) agrees to add £45,000 to the Capital Programme for Lighting Replacement at Fareham Innovation Centre to be funded from Solent Enterprise Zone retained business rates; and (d) agrees to add £125,000 to the Capital Programme for Depot Fuel Infrastructure Investment to be funded from additional revenue contributions to capital; (e) notes the treasury management activity for 2025/26.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 6 July 2026 Portfolio: Policy and Resources

Subject: Capital and Treasury Management Outturn 2025/26

Report of: Chief Finance and Technology Officer

Corporate Priorities: A Responsive, Inclusive and Innovative Council

Purpose: This report provides the Executive with details of the capital and treasury management outturn for 2025/26 to comply with the reporting requirements of the Code of Practice for Treasury Management. The report also seeks approval for the proposed methods of financing the General Fund capital programme and the inclusion of two additional schemes.

Executive summary: Actual capital expenditure on General Fund schemes in 2025/26 was £6,716,268 (£13.4 million in 2024/25) compared with the revised capital programme of £8,862,100. Overall, the programme has been underspent by £2,145,832. A detailed analysis of the variations is given in Appendix A to this report.

Total savings from individual projects of £108,971 were achieved, additional expenditure of £11,537 on others was incurred and a total of £2,048,398 will be carried forward into 2026/27. Details of the various methods used to finance this expenditure are set out in this report.

Full details of Treasury Management investment and borrowing activity in 2025/26 are also set out in this report and is summarised below. This shows that there has been a decrease (improvement) in the Council’s net borrowing position.

31 March 2025 2025/26 31 March 2026 Actual Movement Actual £’000 £’000 £’000 Total borrowing 61,836 (8,336) 53,500 Total investments (17,503) (4,244) (21,747) Net borrowing 44,333 (12,580) 31,753

Net interest received from investments in 2025/26 was £582,213 and net interest paid on borrowing for the HRA was £1,932,368. The overall investment property portfolio decreased in value by £1,862,000 and contracted income was approximately £4,700,000.

During 2025/26, the Council complied with its legislative and regulatory requirements of the Prudential Code.

Recommendation: It is recommended that the Executive:

(a) approves that the General Fund capital programme for 2025/26 be financed as set out in this report;

(b) agrees that the additional expenditure incurred, amounting to £11,537 be financed retrospectively from unallocated capital resources;

(c) agrees to add £45,000 to the Capital Programme for Lighting Replacement at Fareham Innovation Centre to be funded from Solent Enterprise Zone retained business rates; and

(d) agrees to add £125,000 to the Capital Programme for Depot Fuel Infrastructure Investment to be funded from additional revenue contributions to capital;

(e) notes the treasury management activity for 2025/26.

Reason: To provide the Executive with details of the capital and treasury management outturn in 2025/26 and to comply with the reporting requirements of the Code of Practice for Treasury Management.

Financial Implications: The necessary resources are available to finance the General Fund capital programme for 2025/26 including the additional expenditure of £11,537, and the new schemes for the lighting replacement at Fareham Innovation Centre and Depot Fuel Infrastructure Investment.

Appendices: A: Capital Expenditure 2025/26 B: Economic Commentary by Treasury Advisors, Arlingclose C: Prudential and Treasury Indicators 2025/26

Background papers: None

Reference papers: Capital Programme and Capital Strategy 2025/26, Executive Committee, 13 January 2025

Updated Budgets and Council Tax 2025/26, Executive Committee, 13 February 2025 Treasury Management Strategy and Prudential Indicators 2025/26, Council, 14 February 2025

Capital and Treasury Management Monitoring, Executive Committee, 3 November 2025

Updated Budgets and Council Tax 2026/27, Executive Committee, 2 February 2026 Executive Briefing Paper Date: 6 July 2026 Subject: Capital and Treasury Management Outturn 2025/26

Briefing by: Chief Finance and Technology Officer Portfolio: Policy and Resources

INTRODUCTION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital & Treasury Management Outturn 2025/26Report 295 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 9 attended
SM
Councillor Simon MartinCommittee Member, present
IB
Councillor Ian BastableCommittee Member, apologies
FB
Councillor Fred BirkettCommittee Member, present
FB
Councillor Frair BurgessCommittee Member, present
JB
Councillor Joanne BurtonCommittee Member, present
MD
Councillor Malcolm DaniellsCommittee Member, apologies
AW
Andrew WannellLead Officer, expected
SW
Samantha WightmanCommittee Officer, expected
AH
Astra HughesCommittee Officer, expected

On this subject at Fareham

Search all
  1. Capital & Treasury Management Outturn 2025/26This decision
  2. Capital and Treasury Management MonitoringDecided
  3. Capital & Treasury Management MonitoringDecided
  4. Capital and Treasury Management OutturnApproved
  5. Capital and Treasury Management Monitoring 2024/25Decided
  6. Capital and Treasury Management Outturn 2023-24Decided

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open