Broadcut Depot - Decarbonisation Scheme & 5 Year Asset Management Plan
AgreedExecutive1 paper
AI summaryFareham Borough Council Executive approved a £1,847,000 decarbonisation scheme and 5 year asset management plan for Broadcut Depot, funded by £450,000 of government money and £1,397,000 from council reserves.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedDecarbonisation scheme and 5 year asset management plan
Money£1,847,000 total£450,000 government, £1,397,000 council reserves
What happens nextTenders late 2025Works planned complete by September 2026
Who it affectsFareham Borough residentsDepot supports waste, recycling and fleet services
What was decided
The Executive approved delivery and funding of the Depot Decarbonisation Scheme, including enabling works, and delegated award of the contract to the Director of Planning and Regeneration. Report P11, P12, P17
Members noted the award of £450,000 of government funding under the Public Sector Decarbonisation Scheme Phase 4 and the Council's £140,000 matched funding contribution. Report P10, P11, P53
The Executive approved delivery and funding of a new 5 Year Depot Asset Management Plan covering overheating, roof, yard, staff facilities, fire and security, doors, lighting, services and solar PV. Report P19, P22, P45
Why
The depot's main boiler is nearly 20 years old, with the heating system life expired and operating inefficiently, making it a strong candidate for decarbonisation funding. Report P5, P9
The Council won £450,000 of government funding under the Public Sector Decarbonisation Scheme Phase 4 to support detailed design, a new heating system and air source heat pumps. Report P9, P10
Continued investment in the depot is considered worthwhile because it is a critical, well located operational asset that will be needed by any future unitary authority. Report P51, P53
What happens next
Tenders will be sought in late 2025 through the South East Business Portal, with works starting on site in early 2026 and completing by September 2026. Report P15, P16
Officers will investigate overheating measures and look to deliver improvements to the office area at an early stage of the asset management plan. Report P25
An annual review of depot assets and the planned programme will be carried out, informed by the rolling fleet review. Report P50
The money
£1,847,000 Total cost of Decarbonisation Scheme and 5 Year Asset Management Plan Report P53, P55
£450,000 Government funding from Public Sector Decarbonisation Scheme Phase 4 Report P10, P53, P54
£1,397,000 Council capital reserves earmarked for asset improvements Report P53, P55
£140,000 Council matched funding for decarbonisation enabling works Report P11, P54
£150,000 New 500KVA substation on site Report P12, P54
£200,000 New electrical connection, main distribution panel and internal distribution Report P12
£350,000 Total Decarbonisation Scheme electrical enabling works across 2025/26 and 2026/27 Report P54
£907,000 Total 5 Year Asset Management Plan across 2025/26 to 2029/30 Report P58
Options considered
Rejected: Replace the depot heating system like for like rather than decarbonise. Costs significantly more than a like for like replacement, and the Council wanted to reduce carbon emissions and access government funding Report P3, P5, P9
Rejected: Decarbonise the depot under the Local Carbon Skills Fund Phase 5. The Council's application for feasibility funding was unsuccessful Report P6, P7
Implications
Climate: Scope 1 gas emissions at the depot will fall from 64 tCO2e to zero, with overall site emissions expected to drop by 44 tCO2e from 94 tCO2e to about 50 tCO2e. Report P64, P65
Financial: Total investment of £1,847,000 will be spent over 2025/26 to 2029/30, with the largest spend of £1,131,500 falling in 2026/27. Report P53, P55
Other: The depot will no longer use gas for heating or hot water once the new system is operational. Report P13, P44
Risk: Officers note that Local Government Review means the depot will continue to play a key role in operational service delivery for any new unitary authority, justifying continued investment. Report P51
Equalities: Overheating of office accommodation in summer is identified as a significant concern for staff and is to be addressed early in the plan. Report P23, P25
Who and where
Residents of Fareham Borough, who receive waste, recycling and other frontline services operated from the depot Report P2, P53
Depot staff, who will get a new heating system and improvements to office, changing and welfare areas Report P23, P33, P34
Future unitary authority that may inherit the depot as an operational asset Report P51
Timeline
2025-11-03: Executive approves Decarbonisation Scheme and 5 Year Asset Management Plan
Next three months from 2025: Vehicle wash bay reconstruction due to complete under the previous depot plan Report P1
Late 2025: Tenders obtained for the Decarbonisation Scheme via the South East Business Portal Report P15, P16
Early 2026: Planned start on site, beginning with the new power supply and replacement of electrical control equipment Report P15
Spring 2026: Old heating system removed Report P15
Summer 2026: New heating system and air source heat pumps installed Report P15
September 2026: All Decarbonisation Scheme works planned to be complete Report P15
2025/26 to 2029/30: Five year spending period for the Asset Management Plan Report P54, P58
Plain English for the jargon
PSDS: Public Sector Decarbonisation Scheme, a government grant programme
tCO2e: Tonnes of carbon dioxide equivalent, a standard measure of greenhouse gas emissions
Scope 1, 2 and 3 emissions: Council categories of direct emissions, indirect electricity emissions, and other indirect emissions respectively
AMP: Asset Management Plan, a rolling programme of works to maintain a building
KVA: Kilovolt ampere, a unit of electrical power capacity
PV: Photovoltaic, meaning solar panels that generate electricity
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11(1)
Resolved
RESOLVED that the Executive: (a) agrees the delivery of the Depot Decarbonisation Scheme at Broadcut Depot as set out in the Executive Briefing Paper; (b) approves the funding of the Depot Decarbonisation Scheme works including enabling works as detailed in the Financial Implications section of the Executive Briefing Paper; (c) notes the award of government funding of £450,000 to support the depot Decarbonisation Scheme; (d) agrees the delivery of the Depot 5 Year Asset Management Plan as set out in the Executive Briefing Paper; (e) approves the funding of the Depot 5 Year Asset Management Plan as detailed in the Financial Implications section of the Executive Briefing Paper; and (f) approves that the award of contract for the depot Decarbonisation Scheme be delegated to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy Resources.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 3 November 2025
Portfolio: Policy and Resources
Broadcut Depot – Decarbonisation Scheme and 5 Year Subject: Asset Management Plan
Report of: Director of Planning and Regeneration
Corporate Priorities: Respond to Climate Change and Protect the Environment Responsive, Inclusive and Innovative Council
Purpose: To agree funding for a programme of works to deliver a Decarbonisation Scheme and five-year Asset Management Plan of essential repairs, maintenance and improvements for the Broadcut Depot.
To seek delegated authority to appoint a contractor to deliver the Decarbonisation Scheme, following a thorough procurement/tendered process.
Executive summary: This report provides details of works to deliver a Decarbonisation Scheme for the Broadcut Depot over the next 12 months, which has been specifically designed to maximise the significant government support available and now secured for this project.
Alongside this scheme, the proposed Asset Management Plan ensures the provision of safe and well-maintained premises at Broadcut Depot. Officers have undertaken a condition survey to identify essential repairs, maintenance and improvements required in the financial years 2025/26 to 2029/30. The information from the condition survey has been formulated into an Asset Management Plan that identifies the phased capital investment required over the next five years. The report provides a summary of the essential repairs, maintenance and improvements required and an estimated budget figure for the works.
This report seeks Executive agreement to appoint a contractor to deliver the Depot Decarbonisation Scheme and this will allow a start early in 2026. Recommendation: It is recommended that the Executive:
(a) agrees the delivery of the Depot Decarbonisation Scheme at Broadcut Depot as set out in the Executive Briefing Paper;
(b) approves the funding of the Depot Decarbonisation Scheme works including enabling works as detailed in the Financial Implications section of the Executive Briefing Paper;
(c) notes the award of government funding of £450,000 to support the depot Decarbonisation Scheme;
(d) agrees the delivery of the Depot 5 Year Asset Management Plan as set out in the Executive Briefing Paper;
(e) approves the funding of the Depot 5 Year Asset Management Plan as detailed in the Financial Implications section of the Executive Briefing Paper; and
(f) approves that the award of contract for the depot Decarbonisation Scheme be delegated to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources.
Reason: The Depot Decarbonisation Scheme and Depot 5 Year Asset Management Plan provide several benefits including: • Allows us to deliver our carbon reduction plans; • Provides access to significant government funding; • Supports the continued delivery of Council services; • Ensures the Council provides appropriate facilities for our staff.
Cost of proposals: The total cost of the proposal is £1,847,000, with £1,397,000 to be funded from capital reserves earmarked for improvements to Council assets, and the remaining £450,000 provided through Government funding, namely the Public Sector Decarbonisation Scheme (Phase 4).
The costs associated with the Depot Decarbonisation Scheme include £450,000 of Government funding allocated for heating works, £140,000 of Council funded works covering new insulated doors, hot water systems and a building management system, and an additional £350,000 of Council funded electrical enabling works.
The Council funded works outlined in the Depot 5 Year Asset Management Plan are estimated at £907,000.
Appendices: None
Background papers: File of correspondence
Reference papers: None Executive Briefing Paper Date: 3 November 2025 Subject: Broadcut Depot – Decarbonisation Scheme and 5 Year Asset Management Plan Briefing by: Director of Planning and Regeneration Portfolio: Policy and Resources
INTRODUCTION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.