Fareham Borough Council
Executive, Monday 3 November 2025 at 6.00pm

Concrete Repairs Contract to 18 blocks of Maisonettes

Decided Executive 1 paper

AI summaryFareham Executive awards a 3-year concrete repairs contract to 18 blocks of council maisonettes, covering 288 dwellings, funded from the Housing Revenue Account.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedBased on quality and cost, as in confidential Appendix A
MoneyNot disclosed (confidential)Costs in confidential Appendix A, within Housing Revenue Account budgets
What happens next3-year repair programme to beginFinancial years 2026/2027, 2027/2028 and 2028/2029
Who it affects18 blocks, 288 council and leasehold dwellingsAcross Fareham borough, including leasehold homes

What was decided

The Executive awarded a 3-year concrete repairs contract for 18 blocks of maisonettes to the contractor with the highest-scoring tender based on quality and cost. Report P7, P28

Why

The blocks show signs of concrete degradation to balconies, canopies and stairwells, mainly from age and past under-maintenance; structural surveys in 2023 and 2024 set out a repair schedule with a 10-year product guarantee. Report P8, P15, P16

The works will keep the housing stock decent under the Decent Homes Standard and ensure the maisonettes remain structurally safe and free from hazards. Report P27

What happens next

The winning contractor will deliver repairs over 3 years, with 6 blocks in Bishopsfield Road and 6 in Redlands Lane in years 1 and 2, and 6 blocks in Longfield Avenue, Nashe Way, Fairfield Avenue and St Annes Grove in year 3. Report P22

Funding will be released annually from the Housing Revenue Account, with budgets approved by the Executive each year as part of the annual review process. Report P23

Options considered

  • Chosen: Award a 3-year contract to the highest-scoring tender (quality and cost). Lowest tender sum made a shorter 3-year programme affordable and logistically workable Report P7, P21, P22

Implications

  • Financial: Costs will be met from existing Housing Revenue Account budgets and fall within amounts already allowed in the forward plan for budgeting. Report P8, P23
  • Legal: The Construction (Design and Management) Regulations 2015 apply to the contract. Report P25
  • Risk: Keeping tender details confidential is justified on grounds of commercial sensitivity and to protect the Council's ability to negotiate best value. Report P10
  • Other: No new detrimental environmental impacts are anticipated; works are needed to keep the properties structurally safe. Report P30

Who and where

  • Tenants and leaseholders in 18 blocks of council maisonettes, totalling 288 dwellings across Fareham borough Report P16, P22
  • Bidders: 8 firms tendered from 26 expressions of interest via the South-East Business Portal Report P18

Timeline

  • 3 February 2025: Executive approved Housing Revenue Account budgets, fees and charges for 2025/26 (reference paper) Report P12
  • 23 May 2025: Tender invitations published on the South-East Business Portal Report P18
  • 2023 and 2024: Structural surveys of all 18 blocks carried out in two phases Report P8
  • 3 November 2025: Executive decision to award the contract Report P1
  • 2026/2027, 2027/2028 and 2028/2029: 3-year delivery programme for concrete repairs Report P5, P22

Plain English for the jargon

  • Housing Revenue Account (HRA): A ring-fenced account that councils use for income and spending on their own housing stock.
  • Decent Homes Standard: A government standard setting minimum conditions that social housing must meet.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9(1)

Resolved

RESOLVED that the Executive awards a contract (for a 3-year programme) to the contractor achieving the highest scoring tender based on quality and cost as detailed in confidential A to the report.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 3 November 2025

Portfolio: Housing

Subject: Concrete repairs Contract to 18 blocks of Maisonettes Report of: Director of Housing and Health

Corporate Priorities: Provides Housing Choices

Purpose: To award a contract to deliver concrete repairs to all communal & private balconies, external concrete canopies and internal stairwells to 18 blocks of Council owned maisonettes across the borough over a 3-year period, for financial years 2026/2027, 2027/2028 and 2028/2029.

Executive summary: This report provides the Executive with information on tenders received, and the tender evaluation process, relating to concrete repairs to all communal & private balconies, external concrete canopies and internal stairwells to 18 blocks of council owned maisonettes across the borough, for financial years 2026/2027, 2027/2028 and 2028/2029.

Recommendation: It is recommended that the Executive awards a contract (for a 3-year programme) to the contractor achieving the highest scoring tender based on quality and cost as detailed in confidential Appendix A to this report.

Reason: To remediate concrete repairs as detailed in the structural surveys undertaken to all 18 blocks of maisonettes. Structural surveys were instructed in two phases in 2023 & 2024 to test & sample the condition and state of repair to all external concrete elements, at all 18 blocks of maisonettes. The structural reports have provided a detailed repair schedule with a remediation process using a quality product specification that includes a 10-year minimum product guarantee. Cost of proposals: The cost of these proposals are outlined in confidential Appendix A to this report. They will be met from existing Housing Revenue Account budgets. The cost falls within our estimated costs which have been included within the forward plan for budgeting purposes.

Appendices: Confidential Appendix A: Summary of tender evaluation

*It is not in the public interest to disclose this information as the appendix contains confidential and commercially sensitive information. It would prejudice the Council’s ability to operate in a commercial environment, obtain best value in contract negotiations and prejudice the Council’s relationships with third parties if they believed the Council would not honour obligations of confidentiality.

Background papers: None

Reference papers: Executive 03 February 2025 - Housing Revenue Account Budgets, Fees & Charges 2025/26’ (available here) Executive Briefing Paper Date: 3 November 2025 Subject: Concrete Repairs Contract to 18 Blocks of Maisonettes

Briefing by: Director of Housing and Health Portfolio: Housing

INTRODUCTION

1. The Council has within its housing stock, 18 blocks of Maisonettes. These blocks are showing signs of concrete degradation of the communal & private balconies, precast concrete canopies and internal communal stairwells. The current condition is primarily caused by age of the buildings and a lack of preventative maintenance over the years. Concrete structures of this era require increasing levels of maintenance as they age.

2. The specification for this project provides for the repair of all existing defects and application of protective coatings to provide a 10-year product guarantee to all communal areas of external concrete, which include all communal & private balconies, block stairwells & precast door canopies. The programme allows for 18 blocks of maisonettes, which equates to 288 dwellings. These are primarily Council owned dwellings but also includes those which are leasehold dwellings.

TENDERS RECEIVED

3. Invitations to tender were published on the open market using the South-East Business Portal on 23 May 2025. There were 26 expressions of interest, of which 8 tender submissions were received.

4. The tenders received were arithmetically and technically reviewed. An overall assessment was undertaken based on the pre-determined quality to cost ratio.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Concrete Repairs Contract to 18 blocks of MaisonettesReport 104 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 14 attended
SM
Councillor Simon MartinCommittee Member, present
IB
Councillor Ian BastableCommittee Member, present
FB
Councillor Fred BirkettCommittee Member, present
JB
Councillor Joanne BurtonCommittee Member, apologies
MD
Councillor Malcolm DaniellsCommittee Member, present
CH
Councillor Connie HockleyCommittee Member, present
RI
Richard IvoryOfficer, expected
RJ
Richard JolleyOfficer, expected
AW
Andrew WannellOfficer, expected
SW
Sarah WardOfficer, expected
RL
Robyn LyonsOfficer, expected
LU
Leigh UsherCommittee Officer, expected

All 14 on the meeting page

On this subject at Fareham

Search all
  1. Concrete Repairs Contract to 18 blocks of MaisonettesThis decision
  2. Contract Variation following award of contract for Concrete repairs Contract to 18 blocks of MaisonettesAgreed

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open