Planning Committee, Wednesday 14 January 2026 at 2.00pm

Actual Revenue Expenditure 2024-25

Noted Planning 1 paper

AI summaryFareham Borough Council's Planning Committee noted that its 2024/25 revenue expenditure was £902,236, £13,664 (0.02%) below the revised budget of £915,900. Higher planning fees and pre application advice income offset overspends on consultant and legal work.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the revenue expenditure report
Money£902,236£13,664 below revised budget of £915,900
What happens nextNot stated
Who it affectsNot stated

What was decided

The Committee noted the content of the report on actual revenue expenditure for 2024/25. Report P2

Why

Planning Applications was £3,258 over budget due to £38,800 of extra consultant and legal work on major applications and £12,800 of extra staff cover costs, partly offset by £30,000 more in planning fees than expected and an £18,300 Biodiversity Net Gain grant from DEFRA. Report P12, P13, P14, P6, P38

Planning Advice was £27,576 under budget, mainly because pre application advice income was £19,310 higher than expected and employee costs were £15,177 lower. Report P15, P16, P41, P42, P43

Planning Enforcement was £1,839 over budget due to higher external legal costs on enforcement cases, and Planning Appeals was £11,514 under budget due to lower consultancy and employee costs. Report P18, P20, P21, P6, P47, P51

What happens next

The council will continue to monitor and manage the ongoing costs of planning appeals within existing resources. Report P22

The money

  • £902,236 Total actual net revenue expenditure for Planning Committee 2024/25 Report P3, P7, P29
  • £915,900 Revised budget for Planning Committee 2024/25 Report P3, P6, P28
  • £13,664 Underspend against revised budget (0.02%) Report P3, P7, P29
  • £400,258 Actual net spend on Planning Applications Report P6, P38
  • £108,524 Actual net spend on Planning Advice Report P6, P43
  • £137,939 Actual net spend on Planning Enforcement Report P6, P47
  • £235,186 Actual net spend on Planning Appeals Report P6, P51
  • £30,000 Planning fees income above expected budget Report P12
  • £18,300 Biodiversity Net Gain grant received from DEFRA Report P12
  • £38,800 Overspend on consultant and legal work for major applications Report P13

Implications

  • Financial: Net underspend of £13,664 (0.02%) against the revised budget, with £20,329 of in service accounting adjustments (including additional pension costs) removed from the overall council position. Report P3, P7, P9
  • Financial: Across the Committee, employee costs were £8,880 below the £899,100 budget, while supplies and services were £44,549 above the £253,800 budget and fees and charges income was £52,113 above the £521,400 budget. Report P31, P32, P33
  • Risk: Planning Appeals costs are ongoing and being monitored within existing council resources. Report P22

Who and where

  • Fareham Borough Council Planning Committee services: Planning Applications, Planning Advice, Planning Enforcement and Planning Appeals Report P4, P6

Timeline

  • 2024/25: Financial year covered by the report Report P3
  • January 2025: Revised budget of £915,900 agreed by this committee Report P3
  • 2026-01-14: Planning Committee noted the actual revenue expenditure report

Plain English for the jargon

  • Biodiversity Net Gain: A planning policy requiring developments to deliver measurable improvements for habitats and species.
  • DEFRA: Department for Environment, Food and Rural Affairs, the UK government department responsible for environment, food and rural policy.
  • Revised budget: An updated budget figure agreed during the financial year, replacing the original estimate.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED that the Committee note the content of the report.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Planning Committee

Summary

This report sets out for the information of Members details of the actual revenue expenditure for 2024/25 in respect of the services for which this Committee is responsible.

Recommendation

The Committee is asked to note the content of the report. INTRODUCTION

1. The final accounts for the financial year for this Committee shows that the actual expenditure of £902,236 was £13,664 (0.02%) below the revised budget of £915,900 which was agreed by this committee in January 2025.

2. The actual net revenue expenditure for the year analysed over the main services provided by this committee is shown in the following table:-

Revised Budget Actual 2024/25 2024/25 Variation £ £ £

Planning Committee Planning Applications 397,000 400,258 3,258 Planning Advice 136,100 108,524 -27,576 Planning Enforcement 136,100 137,939 1,839 Planning Appeals 246,700 235,186 -11,514 915,900 881,908 -33,992

Accounting Adjustments In service 0 20,329 20,329 915,900 902,236 -13,664

3. The main reason for the variance was because of additional income for specialist pre planning advice given to support applicants and planning fees exceeding the budgeted income.

4. There was additional spend on employee costs due to additional pension costs that are removed from the overall council position. These have been removed from the service spend in the table above leaving the true cost of the services to be £33,992 underspent.

5. A detailed breakdown of the actual cost of the individual services is shown in Appendix A. The main variations which exceed £5,000 from the approved budgets are detailed below.

PLANNING APPLICATIONS

6. The service was overspent by just over £3,200. The main reason for variance was additional income received over expected budget. Collected planning fees were £30,000 over the expected budgeted income, along with the receipt of a Biodiversity Net Gain grant of £18,300 awarded by DEFRA.

7. There was additional use of consultant advice and legal works to determine major planning applications contributing to a £38,800 overspend in this area.

8. There was an overspend in the employee budget of just over £12,800 due to increase costs of staff cover. PLANNING ADVICE

9. The overall underspend for this service was £27,600. This was due to an underspend in the employee budget of just over £15,000.

10. Income was more than budgeted by almost £19,300 due to a volume increase in chargeable pre-application advice.

PLANNING ENFORCEMENT

11. The overall overspend for this service was just under £2,000 which was mainly due to an increase in external legal costs relating to enforcement cases.

PLANNING APPEALS

12. The overall underspend for this service was £11,500.

13. The expected consultancy spend on planning appeals was approximately £8,500 under budget, along with an underspend in employees of just under £3,000.

14. The council notes the ongoing costs of appeals. This is being monitored and managed within existing council resources.

CONCLUSION

15. The cost of the services provided by this Committee was £13,664 lower than anticipated when the revised budgets were prepared and the reasons for this are set out in this report.

Enquiries: For further information on this report please contact Neil Wood on 01329 824506

Background papers

Reference Papers: APPENDIX A PLANNING COMMITTEE

ACTUAL OF EXPENDITURE AND INCOME 2024/25

Revised Budget Actual 2024/25 2024/25 Variation £ £ £ Planning Committee Planning Applications 397,000 400,258 3,258 Planning Advice 136,100 108,524 -27,576 Planning Enforcement 136,100 137,939 1,839 Planning Appeals 246,700 235,186 -11,514 915,900 881,908 -33,992

Accounting Adjustments In service 0 20,329 20,329 915,900 902,236 -13,664

Revised Budget Actual SUBJECTIVE ANALYSIS 2024/25 2024/25 Variation £ £ £

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Actual Revenue Expenditure 2024-25Report 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 21 attended
HL
Heather LealanLead Officer, expected
DF
Councillor David FootChairman, present
IB
Councillor Ian BastableVice-Chairman, present
JB
Councillor Joanne BurtonCommittee Member, present
SD
Councillor Steve DuganCommittee Member, present
SI
Councillor Stephen IngramCommittee Member, present
JN
Councillor Jacquie NeedhamCommittee Member, present
PN
Councillor Paul NotherCommittee Member, present
PW
Councillor Paul WhittleCommittee Member, present
KW
Councillor Kirsten WiltshireCommittee Member, present
PJ
Paul JohnstonOfficer, expected
LS
Lee SmithOfficer, expected

All 21 on the meeting page

On this subject at Fareham

Search all
  1. Actual Revenue Expenditure 2024-25This decision
  2. Actual Revenue Expenditure 2024/25Decided
  3. Actual Revenue Expenditure 2023/2024Decided
  4. Actual Revenue Expenditure 2023-24Decided
  5. Actual Revenue Expenditure 2022/23Decided
  6. Actual Revenue Expenditure 2022/23Noted

More from Fareham Planning Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 12 August 2026 be confirmed and signed as a c... Decided Open
9 Sep 2026 Q/0559/26 - Land Between 75 & 77 Church Road Warsash Southampton SO31 9GDRESOLVED that Members delegate authority to the Head of Planning, in consultation with the Solicitor to the Council, ... Agreed Open
9 Sep 2026 P/26/0722/FP - Single Storey Side Extension at 44 Crispin Close Locks Heath SO31 6TDRESOLVED that: - (i) IT BE CONFIRMED that had the planning application for a side extension at 44 Crispin Close (as p... Decided Open
9 Sep 2026 P/26/0791/AD - Barchester Care Home Stubbington Lane Stubbington PO14 2NFRESOLVED that: - (i) Advertisement Consent for Five Years be GRANTED , subject to:- (a) the Conditions in the report;... Decided Open
12 Aug 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 15 July 2026 be confirmed and signed as a cor... Decided Open