Fareham Borough Council
Executive, Thursday 19 February 2026 at 6.00pm

Holly Hill Development

Agreed Executive 1 paper

AI summaryFareham Executive backs community-informed Holly Hill Woodland Park restoration and agrees in principle to allocate up to £297,532.96 in extra council funding if Lottery grant falls short.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedBacks consultation outcomes for Lottery bid
MoneyUp to £297,532.96From New Forest Mitigation and S.106 funds
What happens nextNLHF Delivery Phase applicationDirector to finalise allocation after grant decision
Who it affectsHolly Hill Woodland Park usersFareham's largest public open space, 36 hectares

What was decided

The Executive supports the outcomes of the community consultation so the Delivery Phase submission to the National Lottery Heritage Fund reflects residents' needs and enables an extra community-informed programme of improvements.

The Executive agrees in principle to allocate up to £297,532.96 of additional capital funding from New Forest Mitigation funds and S.106 Contributions, to be used only if the Lottery award is not received in full.

Authority is delegated to the Director of Streetscene, in consultation with the Executive Member for Streetscene, to finalise the capital allocation once the additional Lottery grant is determined and to confirm the figure to the Executive.

Why

Community consultation between June and October 2025, involving 840 people, identified that Holly Hill is a 'hidden gem' but is inaccessible to many, particularly people with disabilities, who make up 26% of Fareham's population. Report P14, P18, P19

The Design Team identified an elevated boardwalk and route B1 as the preferred option to best meet the 1:20 accessibility gradient standard, and a redesigned toilet and new arrival hub were added following consultation. Report P20, P24, P29, P30, P33

The works are expected to reduce ongoing silt build-up, potentially saving around £500,000 every 10 years, and the site's ecosystem benefits are estimated at £4.88m each year. Report P51, P55, P56

What happens next

The Director of Streetscene will finalise the capital allocation once the National Lottery Heritage Fund Delivery Phase award is determined and will report the figure back to the Executive.

The Delivery Phase application is to be submitted by the May deadline, with a Mid Term Review with the NLHF scheduled for 19th February; all costs are to be reviewed by the Quantity Surveyor beforehand. Report P40, P46

If the NLHF does not increase its contribution, value engineering with the Architect will be used to scale back the project to fit the funding available, with community-informed elements prioritised. Report P45

The money

  • £297,532.96 Additional council contribution in principle (Option 1, 50/50 split) Report P42, P43
  • £111,000 National Lottery Heritage Fund Development Phase grant secured Report P7
  • £60,000 Council contribution to the Development Phase (63% intervention rate) Report P8
  • £595,065.91 Estimated additional cost to overall project budget from consultation and design work Report P37, P38
  • £159,975 Boardwalk 1.5m wide with balustrade (best practice option) Report P28
  • £97,375 Boardwalk 1.5m wide without balustrade Report P28
  • £85,155 Boardwalk 1.2m wide without balustrade Report P28
  • £200,000 Indicative cost of toilet refurbishment works Report P31, P38
  • £75,000 Provisional costing for new Hub/arrival area Report P35, P38
  • £1,056,000 Total council match funding agreed to date Report P47
  • £425,000 Unallocated S.106 contributions already received Report P47
  • £436,000 Future CIL receipts allocated to match fund Report P47
  • £195,000 New Forest mitigation funding allocated Report P47
  • £4.88m Estimated annual ecosystem benefits of Holly Hill Report P55, P56
  • £500,000 Estimated council saving on silt management every 10 years Report P51

Options considered

  • Chosen in principle: Option 1: additional FBC contribution of £297,532.96 (intervention rate 48%, 50/50 split with NLHF). Worst-case scenario giving the strongest starting point to negotiate a higher NLHF contribution Report P42, P43, P44
  • Rejected: Option 2: additional FBC contribution of £200,000 (intervention rate 52%). Higher intervention rate makes the project less attractive to the Lottery Report P42, P43
  • Rejected: Option 3: additional FBC contribution of £100,000 (intervention rate 56%). Highest intervention rate; poorest value for money from the Lottery's perspective Report P42, P43

Implications

  • Financial: Up to £297,532.96 of additional council capital may be committed from New Forest Mitigation funds and S.106 Contributions if the NLHF award is below the level needed. Report P42, P47
  • Equalities: Project aims to make the park accessible to people with disabilities, who are 26% of Fareham's population, through the 1:20 gradient boardwalk route and redesigned toilets. Report P18, P19, P20
  • Climate: Works include biodiversity, hydrology and path improvements intended to protect and enhance the 36-hectare mature woodland, which contributes £0.064m of carbon sequestration value annually. Report P6, P12, P13, P56
  • Risk: All cost estimates are pre-Quantity Surveyor review; hydrology design, hub design and an alternative accessible pathway remain to be firmed up, and costs could change after the Mid Term Review on 19th February. Report P40
  • Risk: If the NLHF does not agree an increase, value engineering may scale back community-informed elements of the project. Report P45

Who and where

  • Visitors to Holly Hill Woodland Park, including wheelchair users and people with disabilities Report P18, P19, P20
  • Fareham residents, including children and families, identified as a key audience in consultation Report P14, P16
  • Underrepresented groups including disabled people, identified through consultation Report P18
  • Council, as asset owner and match funder Report P6, P47

Timeline

  • June to October 2025: Public consultation exercise undertaken (840 respondents) Report P14
  • December 2025: Progress Review Meeting held with the NLHF on cost pressures Report P41
  • Early February 2026: Quantity Surveyor to provide cost clarity on hydrology works Report P39
  • May (deadline): Delivery Phase application to be submitted and assessed competitively against other London and South-East bids Report P46
  • 19 February 2026: Mid Term Review with NLHF and Executive meeting considering this report Report P3, P40

Plain English for the jargon

  • NLHF: National Lottery Heritage Fund, the body awarding the grant
  • Intervention rate: The percentage of total project costs funded by the NLHF
  • 1:20 gradient: The maximum gradient standard for footpaths providing access to people with disabilities and wheelchair users
  • S.106 Contributions: Planning obligations paid by developers towards local infrastructure
  • CIL: Community Infrastructure Levy receipts allocated to the project
  • Delivery Phase: The main NLHF-funded implementation stage following the Development Phase
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9(1)

Resolved

RESOLVED that the Executive: (a) supports the outcomes of the community consultation to enable the Delivery Phase submission to the National Lottery Heritage Fund to reflect the needs of our residents to enable an additional community informed programme of improvements to be delivered as part of the wider restoration of Holly Hill Woodland Park; (b) agrees in principle to allocate additional capital funding of up to £297,532.96 from the New Forest Mitigation funds and S.106 Contributions, to be used in the event that the National Lottery funding award is not received in full; and (c) delegates authority to the Director of Streetscene, following consultation with the Executive Member for Streetscene, to finalise the capital allocation once the additional Lottery grant funding is determined and to confirm this figure to the Executive.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 19 February 2026 Portfolio: Streetscene

Subject: Holly Hill Development

Report of: Director of Streetscene Respond to climate change and protect the environment Corporate Priorities: Leisure opportunities for wellbeing and fun

Strong, safe and healthy communities Purpose: Responsive, inclusive and innovative Council This report provides an overview of the results of the community consultation undertaken at the part of the Holly Hill Woodland Rediscovered Project. The report seeks approval for an additional capital programme allocation as part of the Delivery Phase National Lottery Fund application to preserve and enhance this important heritage, ecological and recreational site.

Executive summary: Holly Hill is a 36-hectare woodland park is Fareham’s largest public open space and is an important site for the Council’s carbon mitigation due to the large area of established mature woodland present on site, in addition to the many recreational and health benefits that the site provides.

Fareham Borough Council has secured a Development Phase grant of £111,000 from the National Lottery Heritage Fund (NLHF) for the restoration of Holly Hill Woodland Park.

The Council are contributing a further £60,000 to the Development Phase resulting in an intervention rate of 63%. The intervention rate is the percentage of total project costs funded by the NLHF.

The Development Phase enables vital design, costing and community consultation work to be undertaken to inform the main Delivery Phase application.

An extensive public consultation exercise was undertaken between June to October 2025. The process has enabled us to understand the needs of our residents and the opportunities at Holly Hil to inform the development of the Delivery Phase application. 840 people shared their views through online surveys, pop up events, interviews and lived experience focus groups.

As a result of the consultation, it was identified that: 1. Whilst people living with disabilities would like to visit, the network of paths, including the accessible route, are too challenging in terms of gradient, width and composition. 2. The toilets at Holly Hill are of an old-fashioned design, difficult to keep clean and no longer fit for purpose to meet the needs of residents. A modern design using the existing shell of the building is needed to enhance safety and accessibility to improve the resident experience. 3. An arrival area providing a functional space with interpretation to learn more about the heritage, history and biodiversity of the site is needed. The Hub will form a place for visitors to congregate for educational activities and offer an accessible and inclusive viewing platform from which to enjoy the main lake whilst mitigating the impact of erosion.

As a result of the consultation, the costs for the Delivery Phase have increased and it is estimated that a potential additional £595,065.91 is needed to respond to the needs of our residents.

A maximum uplift in capital allocation of £297,532.96 is needed to address the funding gap. This represents 50% of the total potential additional cost with the NLHF meeting the other 50%.

If the NLHF are unable to increase their contribution, value engineering approaches will be discussed with the Architect. This does pose the risk of not delivering the community informed programme of improvements, but officers will prioritise this activity as part of the decision-making process.

Recommendation/Recommended Option: It is recommended that the Executive:

(a) supports the outcomes of the community consultation to enable the Delivery Phase submission to the National Lottery Heritage Fund to reflect the needs of our residents to enable an additional community informed programme of improvements to be delivered as part of the wider restoration of Holly Hill Woodland Park;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Holly Hill DevelopmentReport 610 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
SM
Councillor Simon MartinCommittee Member, present
FB
Councillor Fred BirkettCommittee Member, present
IB
Councillor Ian BastableCommittee Member, present
JB
Councillor Joanne BurtonCommittee Member, present
MD
Councillor Malcolm DaniellsCommittee Member, present
CH
Councillor Connie HockleyCommittee Member, present
DH
Councillor David HamiltonGuest, in attendance
RI
Richard IvoryOfficer, expected
RJ
Richard JolleyOfficer, expected
LU
Leigh UsherOfficer, expected
AW
Andrew WannellOfficer, expected
RL
Robyn LyonsOfficer, expected

All 16 on the meeting page

On this subject at Fareham

Search all
  1. Holly Hill DevelopmentThis decision
  2. Holly Hill Development UpdateNoted
  3. Holly Hill Woodland ParkDecided
  4. P/24/0844/fp - otterholme, holly hill lane, sarisbury greenDecided
  5. P/23/1583/oa - 35 holly hill lane sarisbury greenDecided
  6. Holly Hill Woodland Park RestorationApproved

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open