CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Fareham Borough Council
Audit and Governance Committee, Thursday 12 March 2026 at 6.00pm

Risk Management Monitoring Report

Decided Finance 1 paper

AI summaryFareham Audit and Governance Committee accepts six monthly risk monitoring report as evidence the council Risk Management Policy is operating in practice.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedPolicy is operating in practice
MoneyNot stated
What happens nextNext six monthly cycleOther two directorates in next round
Who it affectsAll council directoratesPlus tenants, residents and partners

What was decided

The Committee reviewed the latest six monthly risk monitoring report and accepted it as evidence the current Risk Management Policy is operating effectively in practice. Report P2

Why

Officers recommended the review as a way for the Committee to test whether the policy, approved in September 2022 and based on principles rather than registers, is being applied in practice. Report P2, P3

The Committee uses the report to check that managers understand their top risks, mitigations, incidents, and cross service issues, following a process compared to neighbouring councils after a 2025/26 Peer Challenge. Report P3, P4, P5

What happens next

The Council will continue the six monthly cycle of discussions with all Directors, with the next round covering the two directorates not in this cycle. Report P4, P8

Work continues on specific mitigations, including preparation for Local Government Reorganisation, Awaab's Law compliance, a new Local Plan, and the Building Safety Levy. Report P10, P14, P27, P23

The money

  • £500k HRA Repairs and Maintenance budget overspend in 2024/25 Report P17
  • £1.3 million Potential annual budget gap identified in the 2024/25 to 2028/29 Medium Term Finance Strategy, now significantly reduced Report P44
  • £176,000 Successful bid to the Council House Building Support Fund Report P17

Implications

  • Governance: The Committee concluded that additional corporate involvement is not currently needed for Housing & Health or Planning & Regeneration directorates, with Internal Audit confirming managers could articulate their risks. Report P22, P35
  • Financial: The HRA is under ongoing pressure from new legislative requirements and an ageing housing stock, with a £500k Repairs and Maintenance overspend in 2024/25 and uncertainty over long term funding. Report P17, P19
  • Legal: Several new or changing laws are creating risk: Local Government Reorganisation, Awaab's Law, the Data Use and Access Act, the Renters Rights Act, and the Building Safety Levy. Report P10, P14, P21, P23, P36
  • Staffing: Risk of loss of professional and skilled senior staff due to retirements and LGR uncertainty, plus increasing staff safety incidents involving aggression from the public in customer facing roles. Report P11, P13
  • Risk: Severe court backlogs are delaying litigation and debt recovery, and locum legal support has been brought in to manage demand through the Southampton City Council Legal Partnership. Report P13
  • Other: Loss of Hampshire County Council Social Inclusion funding and the ending of Two Saints commissioned services on 31 March 2026 will remove the borough's only direct access hostel and rough sleeping outreach. Report P20

Who and where

  • All council directorates, including Housing & Health, Planning & Regeneration, Corporate & Community Services, Streetscene, and Finance & Technology Report P4, P8
  • Council tenants, particularly around damp and mould, Awaab's Law compliance, and housing repairs Report P14, P18, P19
  • Residents in Fareham, including those in the private rented sector affected by the Renters Rights Act Report P21
  • Rough sleepers and vulnerable residents previously supported by Hampshire County Council and Two Saints services Report P20
  • Council staff in customer facing roles facing increased aggression from the public Report P13

Timeline

  • January 2026: Discussions held with all Directors and managers in Housing & Health and Planning & Regeneration directorates Report P6, P8
  • 30 March 2026: First food waste collection scheduled Report P40
  • 31 March 2026: Two Saints commissioned services end Report P20
  • 1 April 2026: Revised Council Tax Support Scheme implementation; updated website content and complaints process under the Data Use and Access Act Report P36, P43
  • 1 May 2026: Phase 1 of the Renters Rights Act takes effect Report P21
  • October 2026: Council becomes required to collect the Building Safety Levy on residential developments; one remaining housing policy due for completion Report P15, P23
  • End of 2028: HM Land Registry aims to complete the transition of Local Land Charges from Fareham Borough Council Report P24
  • April 2028: Fareham Local Plan 2037 will no longer be classed as up to date under planning rules Report P27

Plain English for the jargon

  • LGR: Local Government Reorganisation
  • HRA: Housing Revenue Account
  • RSH: Regulator of Social Housing
  • Awaab's Law: Statutory timescales for addressing damp and mould hazards in social housing
  • SDS: Spatial Development Strategy
  • SLT: Senior Leadership Team
  • CPI: Consumer Price Index
  • UKSPF: UK Shared Prosperity Fund
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

RESOLVED that the Audit and Governance Committee reviewed the report as a source of evidence that the current Risk Management Policy is operating in practice.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Audit and Governance Committee

Summary

This is the latest six-monthly risk monitoring report highlighting the key strategic and governance risks arising from the latest rounds of discussions with managers and Directors.

Recommendation

It is RECOMMENDED that the Audit and Governance Committee review the report as a source of evidence that the current Risk Management Policy is operating in practice. INTRODUCTION

1. In September 2022, the Audit and Governance Committee approved the latest Risk Management Policy, which is based around a set of principles rather than a framework of registers. In line with this approach, discussions are held with managers to gather evidence that risk management is operating effectively in practice. In particular, the policy is considered effective if managers are able to demonstrate an understanding of: a) Their top risks, including any new or emerging risks, and changes to existing risks and opportunities. b) Actions taken to mitigate risks. c) Incidents that have occurred and actions taken to manage the incident and prevent recurrence. d) Risks and solutions shared across services or discussed with subject matter experts.

2. Since 2024/25, a revised management reporting approach has been established, whereby: a) Discussions are held with all Directors every six months as part of the risk management review process, and significant or new risks are written up for the report. b) In addition, each six-monthly reporting cycle includes focused discussions with managers across two directorates, enabling a more detailed review within those areas. c) All the cross-cutting risks are grouped together and reviewed in each report. d) Updates are provided for all previous risks discussed.

3. In addition, in response to a Corporate Peer Challenge recommendation made in 2025/26 the process has been compared to neighbouring authorities to identify any good practice that would be worth adopting. As a result, risks identified in the process are now categorised as: a) Strategic risks – which threaten delivery of corporate strategy/priorities or long- term objectives. b) Governance risks – which threaten assurance, compliance, reputation or control framework. Operational risks, which relate to day-to-day service delivery and are managed within directorates, continue to be monitored by the Senior Leadership Team and are therefore not included within the scope of the Committee Report, except where they impact on multiple services.

4. This report summarises the evidence gathered from the discussions held in January 2026. 5. Static risks are included in Appendix C. The risks have been updated to clearly identify the risk owner and the primary sources of assurance through which the risk is managed and monitored.

MANAGERS AND DIRECTORS COVERED BY THIS REPORT

6. Discussions were held with all Directors, together with managers from the Housing & Health and Planning & Regeneration directorates as part of this reporting cycle. A list of Directors and managers included within the scope of the discussions is provided in Appendix B.

STRUCTURE OF THE EVIDENCE GATHERED 7. Detailed notes were taken of each discussion and retained as evidence. The sections below give examples of the risks discussed during the interview and records an opinion as to whether: a) the director or manager was able to demonstrate examples of risk management; and b) any issues were identified where additional corporate support or intervention may be required. Cross Cutting Risks Cross Cutting (Strategic Risk)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Management Monitoring ReportReport 318 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 11 attended
PW
Councillor Paul WhittleChairman, present
JN
Councillor Jacquie NeedhamVice-Chairman, apologies, sent representative
FB
Councillor Frair BurgessCommittee Member, apologies
TE
Councillor Tina EllisCommittee Member, present
DF
Councillor David FootCommittee Member, present
GF
Councillor Gemma FurnivallCommittee Member, present
DH
Councillor David HamiltonCommittee Member, present
MD
Councillor Malcolm DaniellsCommittee Member, present as substitute
EH
Elaine HammellOfficer, expected
AW
Andrew WannellOfficer, expected
AH
Astra HughesCommittee Officer, expected

On this subject at Fareham

Search all
  1. Risk Management Monitoring ReportThis decision
  2. Risk Management Monitoring ReportDecided
  3. Risk Management Monitoring ReportApproved
  4. Risk Management Monitoring ReportDecided
  5. Risk Management Monitoring ReportDecided
  6. Risk Management Monitoring ReportDecided

More from Fareham Audit and Governance Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Business ContinuityRESOLVED that the Audit and Governance Committee note the contents of the report. Noted Open
8 Sep 2026 Corporate Complaint Handling - Performance and Learnings 2025/26RESOLVED that the Audit and Governance Committee: - (a) note the content of the Fareham Housing specific 2025/26 Comp... Noted Open
8 Sep 2026 Chief Internal Auditor's Quarterly ReportRESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. Decided Open
8 Sep 2026 Committee ReportRESOLVED that the Audit and Governance Committee: - a) notes the contents of Part One of the report, including the Co... Approved Open
27 Jul 2026 External Audit - Annual Plan and Fee 2026/27RESOLVED that the Audit and Governance Committee: a) approves the 2025/26 Audit Plan, attached as Appendix A to this ... Approved Open