Resolved
RESOLVED that the Audit and Governance Committee reviewed the report as a source of evidence that the current Risk Management Policy is operating in practice.
Audit and Governance Committee decided this item on Monday 23 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Audit and Governance Committee reviewed the report as a source of evidence that the current Risk Management Policy is operating in practice.
This is the latest six-monthly risk monitoring report highlighting some of the risks arising from the latest rounds of discussions with managers and directors.
It is RECOMMENDED that the Audit and Governance Committee review the report as a source of evidence that the current Risk Management Policy is operating in practice. INTRODUCTION
1. In March 2017, the Committee approved the latest Risk Management Policy based around a set of principles rather than a framework of registers. Under this process, discussions are held with managers to gather evidence that the policy is operating in practice. In particular, the policy would be considered to be effective if managers are able to discuss:
a) what their top risks are and any new or changes in risks and opportunities that have occurred. b) actions that have been taken in the year to mitigate risks. c) incidents that have occurred and actions taken to manage the incident and prevent a repeat. d) risks and solutions shared with other services in the Council or discussed with Council experts in that subject.
2. The last progress report was compiled in March 2024. Since then, a new risk management approach has been established: • Each of the 6 monthly reports will cover all managers of two directorates. • Directors will be included in the process and will be interviewed every 6 months. • All the cross-cutting risks or significant risks for a directorate will be grouped together and updated in each report.
3. This report summarises the evidence gathered from the discussions which took place in July and August 2024. MANAGERS AND DIRECTORS COVERED BY THIS REPORT
4. Discussions were held with all managers from the Housing and Planning & Regeneration directorates as well as all Directors and Assistant Directors.
STRUCTURE OF THE EVIDENCE GATHERED 5. Detailed notes were taken of each discussion and saved as evidence. The sections below give examples of the risks discussed during the interview and records an opinion as to whether:
a) the manager was able to demonstrate examples of risk management; and b) whether there were any problems where corporate assistance might be needed. RESULTS OF THE RISK MANAGEMENT DISCUSSIONS
6. The sections below provide evidence of effective risk management for the following services: • Planning and Regeneration o Planning o Asset Management including Daedalus o Building Control Partnership o Regeneration and Economic Development o Coastal Management • Housing o Property Management o Housing Strategy and Affordable Housing Delivery o Pathways and Neighbourhoods • Other Council Directorates o Neighbourhoods o Finance and ICT o Democracy o Human Resources Cross Cutting Risk 7. From meetings conducted with Council managers and directors a cross-cutting risk was identified below:
Succession planning and staff contingency: An ageing workforce is an issue in some services, and with no upper age limit to retirement, it is hard to predict retirement dates. Furthermore, there is a potential risk of staff shortage as recruitment is challenging in the current climate particularly for qualified professional staff Actions in who would be responsible for delivering Council services. Progress Corporate actions such as the recent restructure in the Council services and the actions outlined in the People Strategy such as workforce planning, the provision of training and development and the intention to recruit more graduates and junior staff members will help mitigate this risk. Planning and Regeneration Planning and Regeneration
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management Monitoring ReportReport | 306 KB | DownloadRead as text |
Follow Audit and Governance Committee at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Business ContinuityRESOLVED that the Audit and Governance Committee note the contents of the report. | Noted | Open |
| 8 Sep 2026 | Corporate Complaint Handling - Performance and Learnings 2025/26RESOLVED that the Audit and Governance Committee: - (a) note the content of the Fareham Housing specific 2025/26 Comp... | Noted | Open |
| 8 Sep 2026 | Chief Internal Auditor's Quarterly ReportRESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. | Decided | Open |
| 8 Sep 2026 | Committee ReportRESOLVED that the Audit and Governance Committee: - a) notes the contents of Part One of the report, including the Co... | Approved | Open |
| 27 Jul 2026 | External Audit - Annual Plan and Fee 2026/27RESOLVED that the Audit and Governance Committee: a) approves the 2025/26 Audit Plan, attached as Appendix A to this ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.