1 and 2 Dean Park Farm Cottages and 70 Kiln Road (Welborne)
AgreedExecutive1 paper
AI summaryFareham Executive delegates authority to require Welborne Land Limited to buy three residential properties used to clear land for the Welborne Garden Village.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedDirector of Planning and Regeneration authorised to serve Put Option Notice
Money£5,000 + VATLegal fees funded from existing revenue budgets
What happens nextServe Put Option Notice on WLLAnd enter a deferred payment agreement once terms are finalised
Who it affectsWelborne Land LimitedRequired to buy three Council owned properties in Fareham
What was decided
The Executive considered the proposals to dispose of 1 and 2 Dean Farm Cottages and 70 Kiln Road to Welborne Land Limited. Report P12
Authority was delegated to the Director of Planning and Regeneration, after consulting the Executive Member for Policy and Resources and the S151 Officer, to agree deferred payment terms and serve the Put Option Notice. Report P13, P14, P15
Why
The properties were acquired between 2016 and 2017 to support the delivery of Welborne Garden Village, and an Option Agreement with WLL was completed in May 2022 to arrange their future disposal. Report P6, P25
The Junction 10 works were implemented on 17 October 2024, triggering the Put Option Period, and WLL has not used its Call Option, leaving the Council exposed to holding costs and financial risk. Report P7, P8, P28, P30
What happens next
The Director of Planning and Regeneration will finalise deferred payment terms, ensure compliance with the Subsidy Control Act 2022 and best value, and serve the Put Option Notice on WLL. Report P9, P13, P15, P31
After the Notice is served and a purchase price agreed, completion must take place within 15 working days, with price being the greater of the Council's acquisition and maintenance costs or open market value at service of the Notice. Report P29
Chosen: Exercise the Council's Put Option to require WLL to buy the three properties. Avoids further holding costs and supports delivery of Welborne Garden Village, with WLL acknowledging the Council's right to do so Report P8, P30, P31
Rejected: Allow WLL to continue holding its Call Option without action. Would leave the Council exposed to financial risk and ongoing holding costs for properties within the Junction 10 works footprint Report P8, P30
Implications
Financial: Continued Council ownership of the properties carries increasing financial risk and holding costs, which the disposal is intended to remove. Report P8, P30
Legal: Any deferred payment terms must comply with the Subsidy Control Act 2022 and best value requirements, and some professional advice is still outstanding. Report P9, P31
Financial: Legal fees of £5,000 plus VAT will be funded from existing revenue budgets. Report P17
Who and where
Welborne Land Limited (WLL), the developer of Welborne Garden Village Report P5, P6, P25
Residents and future occupants of the Welborne Garden Village development Report P5, P16, P33
Fareham Borough Council as owner of the three residential properties Report P6, P25
Timeline
22 February 2016: Executive approved acquisition of 1 and 2 Dean Farm Cottages for Welborne Report P25
6 February 2017: Executive approved purchase of 70 Kiln Road, Fareham Report P25
10 January 2022: Executive authorised the Council to enter the Option Agreement with WLL Report P25
17 May 2022: Option Agreement with WLL completed Report P6, P25
17 October 2024: Junction 10 works contract awarded, treated as the Implementation Date, triggering the Put Option Period Report P7, P28
23 March 2026: Executive considered the report and delegated authority to serve the Put Option Notice Report P1
By 27 May 2027: WLL's Call Option expires, subject to extension in writing and a long-stop date of 17 May 2032 Report P27
Plain English for the jargon
Put Option: A right for the Council to require WLL to buy the properties once the Implementation Date has passed.
Call Option: A right for WLL to require the Council to sell the properties, expiring on 27 May 2027 unless extended.
Implementation Date: The date the Junction 10 works were implemented, recorded here as 17 October 2024 when the works contract was awarded.
Welborne Land Limited (WLL): The developer of the Welborne Garden Village project.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12(1)
Resolved
RESOLVED that the Executive: (a) considers the proposals set out in this report; and (b) delegates authority to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources and the S151 Officer, to: (i) agree the deferred payment terms should they vary from those outlined; and; (ii) serve the Put Option Notice on WLL to require them to purchase the properties and enter into a deferred payment agreement with WLL once the terms are agreed.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Purpose: To seek Executive approval to delegate authority to the Director of Planning and Regeneration to exercise the Council’s Put Option under the Option Agreement with Welborne Land Limited (WLL), subject to agreeing to enter into deferred payment arrangements for the disposal of 1 and 2 Dean Farm Cottages and 70 Kiln Road, to support the delivery of Welborne Garden Village.
Executive summary: The Council owns three residential properties, 1 and 2 Dean Farm Cottages and 70 Kiln Road, Fareham, acquired between 2016 and 2017 to facilitate the delivery of Welborne Garden Village. In January 2022, the Executive approved the Council entering into an Option Agreement with WLL to enable the future disposal of these properties, supporting land assembly and timely delivery of the development. The Option Agreement was completed in May 2022.
Under the Agreement, WLL holds a Call Option to purchase the properties, while the Council retains a corresponding Put Option requiring WLL to purchase the properties, exercisable once the Implementation Date has passed. The Implementation Date, defined as the date the Junction 10 works were implemented, occurred on 17 October 2024, triggering the Put Option Period. WLL has not exercised its Call Option, and the Council is now entitled to require WLL to proceed with the purchase.
As the properties fall within the Junction 10 works footprint, continued Council ownership exposes it to increasing financial risk and ongoing holding costs, contrary to the original intent of the Agreement. Officers therefore consider it appropriate to exercise the Put Option to secure disposal of the properties as soon as possible.
Extensive discussions with WLL have confirmed acceptance of the Council’s right to exercise the Put Option, although WLL has requested deferred payment terms. Officers have progressed negotiations on these terms, while ensuring compliance with best value requirements and the Subsidy Control Act 2022. Some professional advice remains outstanding.
To avoid further delay, approval is sought to delegate authority to serve the Put Option Notice and enter into a deferred payment agreement, subject to appropriate terms being finalised.
Recommendation: It is recommended that the Executive:
(a) considers the proposals set out in this report; and
(b) delegates authority to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources and the S151 Officer, to:
(i) agree the deferred payment terms should they vary from those outlined; and;
(ii) serve the Put Option Notice on WLL to require them to purchase the properties and enter into a deferred payment agreement with WLL once the terms are agreed. .
Reason: To support the delivery of Welborne Garden Village, as agreed by the Executive in February 2016, February 2017 and January 2022.
Cost of proposals: Exercising the Put Option constitutes a disposal of Council assets. Other than legal advice, there are no direct costs arising from the proposal. Legal fees are estimated at £5,000 + VAT which will be funded from existing revenue budgets.
Appendices: A: *Confidential Appendix
*It is not in the public interest to publish this information as it contains commercial sensitive information relating to the Council’s business.
Background papers: None
Reference papers:
Executive report 22 February 2016: Delivery of Welborne Decision - Delivery of Welborne
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.