Executive, Monday 23 March 2026 at 5.00pm

Swordfish Business Park - Masterplan

Agreed Executive 2 papers

AI summaryFareham Executive backs Swordfish Business Park masterplan, adding £374,000 and allocating £10,186,000 for phase one, funded by borrowing against future business rates.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedOptimise site development, delegate planning submission
Money£374,000 extra, £10,186,000 phase oneFunded by borrowing against future RBR receipts
What happens nextSubmit planning applicationsFor employment space, infrastructure and Taxiway B relocation
Who it affectsSwordfish Business Park at DaedalusWestern side of Fareham employment site

What was decided

The Executive noted progress and agreed the principle of optimising the site's development potential, having regard to associated risks and constraints. Report P70

The Executive approved an additional £374,000 to progress Swordfish Business Park, submit planning applications and procure infrastructure works, funded by Retained Business Rates. Report P76

The Executive allocated a capital budget of £10,186,000 for the first phase, to be funded by borrowing against future Retained Business Rates receipts. Report P84

Why

The project pursues the Daedalus Vision, addresses the reducing availability of serviced land at Faraday Business Park, and meets the Council's contractual obligations. Report P29, P30, P32

Officers prefer a planning approach that optimises the site to around 41,500 sq m of employment space, above the 34,800 sq m Local Plan allocation, on a phased basis, with risks kept under review. Report P59

The extra budget is needed because Taxiway B relocation requires a separate planning application and additional surveys and procurement not originally envisaged. Report P73

What happens next

The Director of Planning and Regeneration, after consulting the Executive Member for Policy and Resources, will submit planning applications for employment space, infrastructure and the relocation of Taxiway B. Report P72

Design of phase 1 infrastructure and procurement of works will run concurrently with the planning stage, though no contract for construction will be awarded yet. Report P35, P85

A further Executive decision will be needed to award the contract for the first phase of infrastructure and enabling works, and to commence construction. Report P85

The money

  • £374,000 Additional budget to progress Swordfish Business Park, submit planning applications and procure works Report P76
  • £10,186,000 Capital budget for first phase of development, funded by borrowing against future RBR Report P84
  • £800,000 Existing budget approved 13 January 2025 for masterplanning and planning application Report P28, P73
  • £1,174,000 Revised Stage 2 budget including additional procurement Report P73
  • £37,000,000 Added to Infrastructure Investment Plan for Daedalus on 18 March 2024 Report P61
  • £11,360,000 Estimated cost of phase 1 as currently envisaged Report P67, P83
  • £11.36m and £25.21m Estimated cost range of enabling works across the three shortlisted options Report P53
  • £65 million Combined investment in Bristow Helicopters and Eaton Aerospace facilities Report P22
  • £5.5m Investment plan at Solent Airport at Daedalus to expand commercial opportunities Report P3

Options considered

  • Considered: Three shortlisted development options producing between 21,000 sq m and 41,500 sq m of employment space. Officers prefer the higher capacity option of approximately 41,500 sq m, delivered in phases, with risks kept under review Report P51, P52, P59
  • Preferred: Two planning applications: one for Taxiway B relocation, one hybrid application for employment space and phase 1 infrastructure. The current outline consent is not considered suitable, and splitting applications reflects site constraints Report P58
  • Chosen: Funding via borrowing against future Retained Business Rates receipts. Existing unallocated RBR balances are insufficient to cover phase 1 capital costs Report P63, P67

Implications

  • Financial: Phase 1 will be funded by borrowing against future Retained Business Rates receipts, exposing the Council to repayment risk if RBR falls short. Report P67, P84
  • Risk: Significant risks include the IFA2 cable crossing for stormwater drainage, 500KVA power limit, MCA cooperation on Taxiway B, badger setts, and possible offsite highway improvements. Report P48, P50
  • Legal: Existing MCA covenants restrict parts of the site to airport related uses and impose height restrictions, and there are unresolved legal constraints to be addressed through planning. Report P40, P47
  • Equalities: The site adjoins a children's play area and is near residential areas, increasing sensitivity to traffic, design and amenity impacts that will need to be addressed. Report P44
  • Climate: A significant portion of the site is within a Solent Wader and Brent Geese designation, and Biodiversity Net Gain mitigation will increase development cost. Report P50
  • Staffing: Authority to submit planning applications and award related contracts is delegated to the Director of Planning and Regeneration, with Executive Member and S151 consultation on larger awards. Report P72, P78

Who and where

  • Fareham Borough Council as landowner and developer at Daedalus Report P1, P16
  • Solent Airport and its operations, including Taxiway B Report P27, P47
  • Marine and Coastguard Agency, given covenants and potential height restrictions on parts of the site Report P47
  • Current and prospective businesses at Daedalus, including SMEs and larger occupiers Report P20, P46
  • Residents near Swordfish Business Park and users of the adjoining children's play area Report P44
  • National Grid and statutory utilities providers, due to drainage and power constraints Report P48

Timeline

  • 2015: Daedalus 369-acre freehold site purchased from the Homes and Communities Agency Report P1
  • 18 March 2024: Executive approved addition of £37,000,000 to the Infrastructure Investment Plan for Daedalus Report P61
  • 13 January 2025: Executive approved £800,000 budget to progress Swordfish Business Park masterplanning Report P28
  • 2026-03-23: Executive agreed masterplan principle, additional £374,000 budget, delegation, and £10,186,000 phase 1 capital allocation
  • 2030: Scheduled date for upstream power upgrade works to come online Report P48

Plain English for the jargon

  • RBR: Retained Business Rates, the business rates the Council keeps from the Solent Enterprise Zone to reinvest locally
  • MCA: Marine and Coastguard Agency, which holds covenants over parts of the Daedalus site
  • IFA2: Interconnexion France-Angleterre, the electricity interconnector whose cables run near the site
  • S106: Section 106 planning obligation, a legal agreement between a developer and a local authority
  • S151 officer: The Council's Chief Finance Officer, designated under section 151 of the Local Government Act 1972
  • B2, B8, E(g)(ii)/(iii): Use classes for general industrial, storage and distribution, and employment uses such as offices, research and light industry
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12(3)

Resolved

RESOLVED that the Executive: (a) notes the progress made with the progression of Swordfish Business Park and agrees the principle of seeking to optimise the development potential/capacity of the site whilst having regard to the associated risks and constraints; (b) subject to recommendation (a) delegates authority to the Director of Planning and Regeneration following consultation with the Executive Member for Policy and Resources to submit a planning application(s) for employment and associated infrastructure/enabling works, including the relocation of Taxiway B; (c) approves an additional £374,000 to progress Swordfish Business Park, submit planning application(s) for employment space and associated infrastructure (including Taxiway B relocation), and procure the infrastructure works; (d) subject to recommendation (c) delegates authority to the Director of Planning and Regeneration to award contracts within the agreed budgets necessary for the submission of planning application(s) for employment space and associated infrastructure/enabling works, including the relocation of Taxiway B and for the procurement of the associated works as follows: · individual contracts for £250,000 and under, or · following consultation with the S151 officer for any individual contract awards over £250,000; and (e) allocates a capital budget of £10,186,000 for the first phase of development, which will be funded by borrowing against future Retained Business Rates (RBR) receipts.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 23 March 2026 Portfolio: Policy and Resources

Subject: Swordfish Business Park – Masterplan

Report of: Director of Planning and Regeneration

Promote Economic Development. Corporate Priorities: Responsive, Inclusive and Innovative Council.

Purpose: The purpose of this report is to update the Executive on progress and seek approvals to move the Swordfish Business Park masterplanning project into the next Stage. Specifically, the report is intended to:

• Summarise progress to date on the masterplanning and feasibility work, particularly the completion of Stage 1 (Feasibility). • Set out the key constraints and findings affecting the development of Swordfish Business Park, including planning, infrastructure, environmental, operational and market considerations. • Present the shortlisted development options for the site, including the range of potential employment floorspace and the estimated costs of enabling infrastructure. • Explain the preferred approach, which is to optimise the site’s development capacity/potential on a phased basis, while acknowledging the associated delivery and funding risks.

Executive summary: Swordfish Business Park forms part of the Daedalus site, a key Corporate Priority for delivering economic growth, skilled employment and investment. While significant progress has been made at Faraday Business Park and within the Skills and Innovation area, Swordfish Business Park has not yet been brought forward and remains an undeveloped parcel of land on the western side of the site. The Local Plan allocates Swordfish Business Park for up to 34,800 sq. m of employment floorspace. In January 2025, the Executive approved a budget of £800,000 to progress masterplanning and prepare a planning application for Swordfish Business Park. The project is now nearing completion of Stage 1 (Feasibility), and this report summarises the work undertaken, the key constraints identified, the shortlisted development options, and the proposed next steps.

The feasibility work confirms that Swordfish Business Park has the potential to deliver serviced employment land across use classes E(g)(ii)/(iii), B2 and B8, with a commercial advantage arising from its proximity to Solent Airport and the opportunity for airside access. However, the site is subject to a number of significant constraints, including Marine and Coastguard Agency covenants, the presence of Taxiway B, ecological designations, badger setts, drainage requirements, power capacity limitations and the need to carefully manage development phasing.

Three development options have been shortlisted, delivering between approximately 21,000 sq. m and 41,500 sq. m of employment floorspace. All options focus on the delivery of enabling infrastructure to create serviced development plots rather than the direct delivery of built accommodation. The early estimated cost of enabling works ranges from £11,360,000 to £25,210,000 depending upon the option selected, with development expected to be phased from north to south to manage costs, risk and market demand. More detailed work is required prior to any planning application.

Following consideration of the shortlisted options, the Council’s current preference is to progress a planning application that optimises the development capacity/potential of the site, delivering serviced development sites for approximately 41,500 sq m of employment space on a phased basis. At present the projected cost of the anticipated first phase is approximately £11,360,000, which will deliver serviced development areas for approximately 21,000 sq m. This approach to optimise the capacity/development potential of the site is recognised as carrying increased delivery and funding risk, and these risks will be kept under review as the project progresses. The strategy will be revised should the risks become too significant.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Location of Swordfish Business Park and associated Local Plan Policy (3)Appendix A 2.7 MB Download
PDF
Swordfish Business Park: MasterplanReport 206 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
SM
Councillor Simon MartinCommittee Member, present
FB
Councillor Fred BirkettCommittee Member, present
IB
Councillor Ian BastableCommittee Member, present
JB
Councillor Joanne BurtonCommittee Member, present
MD
Councillor Malcolm DaniellsCommittee Member, present
CH
Councillor Connie HockleyCommittee Member, present
RI
Richard IvoryOfficer, expected
RJ
Richard JolleyOfficer, expected
LU
Leigh UsherOfficer, expected
AW
Andrew WannellOfficer, expected
RL
Robyn LyonsOfficer, expected
IC
Ian CollinsOfficer, expected

All 16 on the meeting page

On this subject at Fareham

Search all
  1. Swordfish Business Park - MasterplanThis decision
  2. Daedalus Swordfish Business Park MasterplanNoted

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies