Fareham Borough Council
Planning Committee, Wednesday 10 June 2026 at 2.00pm

P/25/0436/OA - Land at Boarhunt Road Junction 11 of the M27 Fareham

Decided Planning 1 paper

AI summaryFareham Planning Committee grants outline permission for a truck stop, EV charging forecourt and port storage land at Junction 11 of the M27 near Boarhunt Road, subject to conditions and a Section 106 agreement.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to conditions in the report
MoneyNot stated
What happens nextSection 106 legal agreement requiredTo secure highway works at site access and junctions
Who it affectsNot stated

What was decided

Outline planning permission granted for a truck stop facility (Sui Generis), EV charging forecourt and ancillary building, and port open storage and operational area, with all matters reserved except access. Report P3

The decision is a departure from Policies DS1 (j)(k) and DS3 of the adopted Fareham Local Plan 2037, because the site lies in the countryside within the Portsdown Hill Area of Special Landscape Quality. Report 1.0

Authority delegated to the Head of Planning to make any necessary modifications, deletions or additions to the conditions, and to vary them to ensure consistency with heads of terms negotiated with the applicant.

Why

Officers concluded there is an overriding public need for EV charging infrastructure to support the transition to net zero, for additional HGV lorry parking along the M27/A27 corridor, and for port-related storage to support Portsmouth International Port's growth. Report 8.25, 8.41, 8.51

The proposal is considered compliant with Policy DS1(h) on overriding public need, justifying the countryside location despite not being considered previously developed land under Policy DS1(b). Report 8.12, 8.19, P98

Less than substantial harm to the settings of the Monument Farm and Fort Nelson Scheduled Ancient Monuments was identified at the lower end of the scale, and was weighed against the public benefits of the scheme. Report 7.26, 7.12

What happens next

A Section 106 legal agreement is required to secure highway works at the site access, the Boarhunt Road/unnamed link road junction, and the M27 Junction 11 roundabout. Report P41

Reserved matters applications will be required for layout, scale, appearance, landscaping and any other matters, with specific conditions requiring details on landscaping, drainage, lighting, and an Asset Protection Agreement with SGN. Report 3.2, 7.10, P54

Planning conditions must address surface water drainage, foul drainage, contamination, ecology, biodiversity net gain, archaeology, noise, air quality, and a limit on use of the port land to operations directly related to Portsmouth International Port. Report P43, 7.7, 7.10, 3.9

Options considered

  • Chosen: Grant outline planning permission with conditions and a Section 106 agreement. Officers found overriding public need for EV charging, HGV parking and port storage outweighed landscape and heritage concerns Report 8.25, 8.41, 8.51
  • Rejected: Refuse on the basis of countryside location and landscape harm. The three land uses were considered to meet an overriding public need under Policy DS1(h), and the existing hardstanding provides a baseline position Report 8.12, 8.53

Implications

  • Equalities: The truck stop would provide welfare facilities (showers, toilets, café, lounge) for HGV drivers, addressing a recognised shortage in the South Hampshire area. Report 3.6, 8.41
  • Climate: EV charging forecourt would support the transition to electric vehicles and net zero by 2050, with 54 high power charging spaces proposed. Report 3.5, 8.25
  • Legal: Less than substantial harm identified to the settings of two Scheduled Ancient Monuments, weighed against public benefits as required by NPPF paragraph 216. Report 7.26
  • Risk: The site lies within Groundwater Source Protection Zones 1 and 2 on a principal aquifer; the Environment Agency and Portsmouth Water withdrew objections subject to drainage and contamination conditions. Report 2.7, 7.7
  • Other: Decision is a formal departure from Policies DS1(j)(k) and DS3 of the Fareham Local Plan 2037 due to countryside location and Area of Special Landscape Quality. Report 1.0

Who and where

  • HGV drivers using the M27/A27 corridor Report 8.32, 8.41
  • Electric vehicle drivers on the M27 Report 3.5, 8.25
  • Portsmouth International Port and its customers Report 3.9, 8.44
  • Users of nearby heritage assets including Fort Nelson and Monument Farm Report 2.6, 7.12
  • Residents and objectors in the surrounding area Report 6.0, P31, P32, P33

Timeline

  • 2026 surfacing works complete: M27 highway construction compound to be vacated Report 2.2
  • End of 2026: Temporary planning application (P/24/1571/CC) for waste recycling facility under consideration by Hampshire County Council Report 5.0
  • By 2030: Government target of 300,000 public EV charge points; 80% of new cars required to be zero emission Report 8.22
  • By 2040: Forecast requirement of 417 HGV parking spaces on the M27/A27 corridor based on medium growth scenario

Plain English for the jargon

  • ASLQ: Area of Special Landscape Quality, a local landscape designation covering the Portsdown Hills near the site.
  • Sui Generis: A use class for land uses that do not fall within any defined use class, such as a truck stop.
  • PDL: Previously Developed Land, as defined in the National Planning Policy Framework.
  • SAM: Scheduled Ancient Monument, a nationally important archaeological site protected under the Ancient Monuments and Archaeological Areas Act.
  • NSIP: Nationally Significant Infrastructure Project, decided by the Secretary of State rather than the local planning authority.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6(2)

Resolved

RESOLVED that: - (i) GRANT outline planning permission, subject to: - (a) the Conditions in the report; THEN (ii) Authority DELEGATED to the Head of Planning to: - (a) Make any necessary modification, deletion or addition to the proposed conditions. (b) Make any necessary changes arising out of detailed negotiations with the applicant which may necessitate the variation, addition or deletion of the conditions and heads of terms as drafted to ensure consistency between the two sets of provisions.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Planning Committee

OFFICER REPORT FOR COMMITTEE DATE: 10/06/2026

P/25/0436/OA WALLINGTON & DOWNEND WARD ELECTRIC@ J11 LTD AGENT:TURLEY

OUTLINE PLANNING APPLICATION FOR THE CONSTRUCTION OF A TRUCK STOP FACILITY (SUI GENERIS); ELECTRIC VEHICLE CHARGING FORECOURT AND ANCILLARY BUILDING (SUI GENERIS); PORT OPEN STORAGE AND PORT OPERATIONAL AREA (USE CLASS B8 & SUI GENERIS) WITH ASSOCIATED SITE INFRASTRUCTURE INCLUDING STRUCTURAL LANDSCAPING; INTERNAL ROADS AND UTILITIES INFRASTRUCTURE (ALL MATTERS RESERVED EXCEPT ACCESS) (ENVIRONMENTAL IMPACT ASSESSMENT DEVELOPMENT ACCOMPANIED BY AN ENVIRONMENTAL STATEMENT)

LAND AT BOARHUNT ROAD, JUNCTION 11 OF THE M27, FAREHAM

Report By Susannah Emery – direct dial 01329 824526

1.0Introduction 1.1 This major planning application is being brought before the Planning Committee due to the number of third party representations received. The recommendation would also result in a departure from Policies DS1 (j)(k) and DS3 of the adopted Fareham Local Plan 2037.

2.0Site Description 2.1 The site is located within the countryside and lies to the north of the M27 close to junction 11. The site also falls within the Portsdown Hill Area of Special Landscape Quality (ASLQ).

2.2A large part of the site is temporarily being used as a construction compound by the firm Morgan Sindall in association with the National Highways upgrade works to the M27 Motorway. The compound comprises hardstanding used for car parking, vehicle movement and turning in addition to the outdoor storage of materials and machinery. There are also a number of double height portacabins stationed within the compound which are used for offices and facilities. The compound enjoys the benefit of being permitted development as it is being used in connection with works being carried out on behalf of Highways England, a strategic highways company, and so does not require planning permission from the Council. The compound is due to be vacated on completion of the M27 surfacing works in 2026. 2.3 Within the south western part of the application site there is currently an active aggregate recycling facility. The applicant maintains that this land use constitutes permitted development as it is used in association with the highway compound, however this Council has not been provided with any evidence to demonstrate this or that the use is lawful. As the use relates to the processing of waste, it is for Hampshire County Council as the Minerals and Waste Planning Authority to consider the matter of whether the use is lawful. A temporary planning application (FBC reference P/24/1571/CC) is currently being considered by Hampshire County Council for its retention on a temporary basis until the end of 2026.

2.4Prior to the use of the site for the processing of waste and as a temporary highways compound commencing, the lawful use of the site was for agriculture. Aerial photography of the site shows this to be the case in 2017, with the site in arable use, by 2020 both the highway compound and waste recycling facility are evident. No planning permission has been granted by the Council for development on the site, including for the site to be used for any particular purposes.

2.5The site abuts a gas governor (regulator) which is positioned centrally along the southern boundary. Medium and high pressure gas lines traverse the application site east to west. These gas lines require a 3 metre wide easement to either side to be maintained. Another compound which provides gas generated electrical power also abuts the southern boundary, positioned to the east of the gas governor.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P/25/0436/OA: Land at Boarhunt Road Junction 11 of the M27 FarehamReport 1.2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
SD
Councillor Steve DuganChairman, present
IB
Councillor Ian BastableVice-Chairman, present
JB
Councillor Joanne BurtonCommittee Member, present
GF
Councillor Gemma FurnivallCommittee Member, present
SI
Councillor Stephen IngramCommittee Member, present
KM
Councillor Kay MandryCommittee Member, present
JN
Councillor Jacquie NeedhamCommittee Member, present
PN
Councillor Paul NotherCommittee Member, present
KW
Councillor Kirsten WiltshireCommittee Member, present
AF
Anna FloyerCommittee Officer, expected
LS
Lee SmithOfficer, expected

More from Fareham Planning Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 12 August 2026 be confirmed and signed as a c... Decided Open
9 Sep 2026 Q/0559/26 - Land Between 75 & 77 Church Road Warsash Southampton SO31 9GDRESOLVED that Members delegate authority to the Head of Planning, in consultation with the Solicitor to the Council, ... Agreed Open
9 Sep 2026 P/26/0722/FP - Single Storey Side Extension at 44 Crispin Close Locks Heath SO31 6TDRESOLVED that: - (i) IT BE CONFIRMED that had the planning application for a side extension at 44 Crispin Close (as p... Decided Open
9 Sep 2026 P/26/0791/AD - Barchester Care Home Stubbington Lane Stubbington PO14 2NFRESOLVED that: - (i) Advertisement Consent for Five Years be GRANTED , subject to:- (a) the Conditions in the report;... Decided Open
12 Aug 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 15 July 2026 be confirmed and signed as a cor... Decided Open